Sched of Materials

EXAMPLE SUBMITTAL REGISTERProject Title:Contract Number:
Project Location:Contractor:
TO BE COMPLETED BY CONTRACTOR QUALITY CONTROL MANAGER OR PROJECT SUPERINTENDANT
Item NumberSpecification Section
and Pargraph NumberDESCRIPTION OF ITEM SUBMITTEDCLASSIFICATIONTYPE OF SUBMITTALSContractor ActionGovernment ActionREMARKS
Government Approval (GA)For Information Only (FIO)CERTIFICATIONSSCHEDULESHOP DRAWINGSSAMPLESMANUFACTURER'S RECOMMENDATIONS/INSTRUCTIONSO & M MANUALS, INSTRUCTIONS, AND WARRANTIESPRODUCT DATATEST REPORTSDESIGN DATAPLANSOTHERDate Quality Control Review CompletedDate Submitted to GovernmentDate Submittal Returned to ContractorSubmittal Approval Code
1010150 - 2.2.AAccident Prevention PlanX
2010150 - 2.2.BMechanical CertificatesX
3010150 - 2.2.CHAZMAT Test ReportsX
4010150 - 2.2.DSafety Meeting and Inspection ReportsX
5010150 - 3.6Construction ScheduleX
6010150 - Part 6Operation and Maintenance ManualsX
7010150 - 7.5 BProject Record DocumentsXDue 15 days before Final Inspection
8024116 - 1.4.A,B,C,D EStructure DemolitionXXX
9033000 - 1.2.ACast-In-Place ConcreteXXXXX
10061000 - 1.2.ARough CarpentryXX
11061600 - 1.2.ASheathingX
12061753 - 1.3.AShop-Fabricate Wood TrussesXX
13066400 - 1.3.A & BFiberglass Reinforced Plastic PanelsXXXX
14072100 - 1.2.AThermal InsulationXX
15073113 - 1.3.A & BAsphalt ShinglesXXXXXProvide extra material.
16074646 - 1.2.A & BFiber Cement SidingXXXXXProvide extra material.
17076200 - 1.2.ASheet Metal Flashing and TrimXXX
18079200 - 1.2.A & BJoint SealantsXXXXProvide Joint-Sealant Schedule
19081113 - 1.2.ASteel Doors and FramesX
20083613 - 1.2.A & BSectional DoorsXXX
21087110 - 1.3.A & BDoor HardwareXX
22092900 - 1.2.AGypsum BoardXX
23099113 - 1.3 & 1.4PaintingXXXXProvide extra material
24102000 - 1.2 ALouvers and VentsX
25220500 - 1.2.APlumbing ProductsX
26221116 - 1.2.A & BDomestic Water PipingXXX
27221123 - 1.2.A & BDomestic Water PumpsXXXX
2822136 - 1.4.A & BSanitary Waste and Vent PipingXX
29223000 - 1.3.A, B, & CProcess Water Treatment SystemsXXXX
30223050 - 1.2.A & BProcess Water System ControlsXXXX
31230500 - 1.3.A & BHVAC ProductsXX
32231126 - 1.4.A & BLiquefied-Petroleum Gas Tank and PipingXXX
33260500 - 1.5.A. & BElectrical ProductsXX
34262210 - 1.3.A.Meter SocketX
35267000 - 1.4.A & BOff-Grid Power SystemXXXX
36312250 - 1.4.A & BEarthworkXX
37312317 - 1.3.A & BTrenching, Bedding, and Backfill for UtilitiesXXXX
38312500 - 1.2.ATemporary Erosion and Sedimentation ControlXX

NOTES: The contractor is ultimately responsible for identifying and providing all submittals required by this contract. Production of this document by the contractor does not relieve the contractor of this responsibility. The Contractor shall review the submittal register for completeness within 10 days of NTP. The Contractor shall notify the CO if any submittals are missing or if additional submittals need to be added to the register.