About this file

This is a bid schedule template for the Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project, issued by the Department of the Interior Bureau of Indian Affairs. The schedule outlines 14 line items requiring unit pricing, including mobilization and preparatory work, Tribal Employment Rights Ordinance compliance, dewatering and canal access, demolition, structural support for screens, traveling water screens, fall arrest system, safety boom, mobile generator, gate actuators, electrical work, telecommunications, sitework, and demobilization.

All items are to be priced as lump sum (LS) quantities, with each line item requiring a unit price and total bid amount. The document specifies that payment for items includes full compensation for all equipment, materials, labor, transportation, and services needed to complete the work according to specifications. The pricing must include all costs for furnishing, hauling, storing, and handling materials, whether listed separately or incorporated into other line items.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project

Solicitation No. XXX

Bid Schedule

B - 1

SECTION B – SUPPLIES OR SERVICES AND PRICES /COSTS

Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project

B.1 SCHEDULE

Payment for the various priced items set forth in the Schedule shall constitute full compensation to the Contractor for providing all plant, equipment, machinery, materials, tools, supplies, transportation, labor and all other property, services, and expenditures for performing all operations required to complete the work in conformity with the Specifications and all other requirements of this Contract.

(1) All costs for work required by this Contract not specifically mentioned in the following Schedule; or not specifically mentioned in measurement, payment, and cost statements shall be deemed to be included in the prices for the most applicable Schedule items.

(2) When a separate item which includes furnishing of a material is provided in the Schedule, include the cost of furnishing, hauling, storing, and handling in the price offered in the Schedule for the item.

(3) When a separate item is not provided in the Schedule for furnishing a material, include the cost of furnishing, hauling, storing, and handling in the price offered in the Schedule for work for which the material is required.

(4) Payment for an item of work will be made only once. Work measured and paid for under a CLIN will not be measured and paid for under any other item of work.

Definitions:

(1) LS – Lump sum.

(2) LF – Linear feet.

Item No.

Description Unit Estimated Quantity

Unit Price Bid Amount

1 Mobilization and Preparatory Work

LS 1 $

2 Tribal Employment Rights Ordinance

LS 1 $

3 Dewatering and Canal Access

LS 1 $

Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project

Solicitation No. XXX

Bid Schedule

B - 2

Item No.

Description Unit Estimated Quantity

Unit Price Bid Amount

4 Demolition LS 1 $

5 Structural Support for Screens

LS 1 $

6 Traveling Water Screens LS 1 $

7 Fall Arrest System LS 1 $

8 Safety Boom LS 1 $

9 Mobile Generator LS 1 $

10 Gate Actuators LS 1 $

11 Electrical LS 1 $

12 Telecommunications LS 1 $

13 Sitework LS 1 $

14 Demobilization LS 1 $

TOTAL FOR SCHEDULE $_________________