Attachment 4 - AE Supplement B - FINAL.pdf
PDF 129 KB Posted
- Attached to
- Construct Substance Rehab Building - Augusta
- Solicitation number
- 36C77621R0110
About this file
This presolicitation notice seeks Standard Form 330 submissions from architecture and engineering firms for design services. Firms must submit qualifications by May 31, 2021 for the design of a Substance Abuse Rehabilitation Building at the Togus VA Medical Center in Augusta, Maine. The Veterans Health Administration intends to award a firm-fixed-price design contract with an estimated construction cost between $5-10 million and 150-day period of performance. Selection will be based on specialized experience designing similar healthcare facilities, knowledge of VA requirements, past performance, professional qualifications of staff, and capacity to complete the work on schedule. Submissions must not exceed 30 pages and include a draft project schedule and CPARS data. This is a 100% SDVOSB set-aside and the selected firm must demonstrate the ability to meet the 50% SDVOSB performance requirement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUPPLEMENT “B”
A/E SUBMISSIONS
OF DESIGN REVIEW MATERIAL
FIRST REVIEW (Conceptual – Preliminary User Group Meetings & Field Surveys) 2 Sets of reduced size and PDF preliminary layout plans with proposed alternates per meeting 2 Sets of conceptual estimates with proposed alternates per meeting 2 Sets bound Basis of Design narrative/analysis for each technical discipline 2 Sets of healing pallets by department/area consistent with the VISN standard and proposed alternates per meeting
SECOND REVIEW (30% Submittal – Schematics)
2 Sets of AutoCAD & PDF schematic drawings in accordance with SOW 2 Sets of full size bound schematic layout plans/details – 36 inches by 24 inches 2 Sets of reduced size bound schematic layout plans/details 2 Sets of MS Word draft specifications in accordance with SOW 2 Sets of spiral bound draft specifications with Mylar front and back cover sheets 2 Sets of schematic estimates 2 Sets of draft phasing plans 0 Sets of artist’s 3D mounted renderings for project area 2 Sets bound Basis of Design narrative/analysis for each technical discipline 2 Sets of healing pallets by department/area consistent with the VISN standard
THIRD REVIEW (60% Submittal – “DD” Design Development) 2 Sets of AutoCAD & PDF design drawings in accordance with SOW 2 Sets of full size bound design development layout plans/details – 36 inches by 24 inches 2 Sets of reduced size bound design development layout plans/details 2 Sets of MS Word design specifications in accordance with SOW 2 Sets of spiral bound design specifications with Mylar front and back cover sheets 2 Sets of design development estimates 2 Sets of design development phasing plans 0 Sets of artist’s 3D colorized mounted renderings of project area 2 Sets bound Basis of Design narrative/analysis for each technical discipline 2 Sets of healing pallets by department/area consistent with the VISN standard (if changed from 30% submission)
FOURTH REVIEW (90% Submittal – “CD” Construction Documents)
2 Sets of AutoCAD & PDF construction drawings in accordance with SOW 2 Sets of full size bound construction documents plans/details – 36 inches by 24 inches 2 Sets of reduced size bound construction documents plans/details 2 Sets of Adobe PDF construction specifications in accordance with SOW 2 Sets of spiral bound construction specifications with Mylar front and back cover sheets 2 Sets of construction documents estimates 2 Sets of construction documents phasing schedules 0 Sets of architectural 3D colorized mounted renderings of project area
2 Sets bound Basis of Design narrative/analysis for each technical discipline 2 Sets of healing pallets by department/area consistent with the VISN standard (if changed from 60%
FIFTH REVIEW (100% Submittal – Bid [Final] Documents)
2 Sets of AutoCAD & PDF bid drawings in accordance with SOW 2 Sets of approved full size bid plans/details with PE stamps 0 Sets of reproducible full size bid drawings on vellum with PE stamps 2 Sets of approved reduced size bound bid plans/details with PE stamps 0 Sets of full size Mylar bound bid plans/details with PE stamps rolled in individual mailing tubes 2 Sets of MS Word final specification sections in accordance with SOW 2 Sets of Adobe PDF final specification sections merged in accordance with Supplement “A” 2 Sets of final specifications boxed on single sided sheets
0 Sets of 3-ring bound final specifications paginated front to back with Mylar front/back cover 2 Sets of final estimates 2 Sets of final phasing schedules 0 Sets of architectural 3D colorized mounted and framed renderings of project area 2 Sets of healing pallets by department/area consistent with the VISN standard (if changed from 90%
SIXTH REVIEW (Project Close Out Submittal – “As-Built” Construction Documents)
2 Sets of AutoCAD & PDF As-Built drawings in accordance with SOW 2 Set of approved full size As-Built drawings with PE stamps 2 Sets of approved reduced size As-Built plans/details with PE stamps
Date: Monday, April 26, 2021 Project Design Schedule Page 1 of 1
Facility: Togus, ME VAMC A/E Firm:
Project Title: Construct Substance Abuse Residential Rehab Building Project Number: 402-318 Notice of Award (NOA): Contract: --- Duration: 150 Calendar Days
ID Milestone Task Description Duration Schedule Date
Actual Date
1 User Group Preliminary Mtg (Review Scope, Site Survey Investigation) 1 Day NOA + 3
2 Preliminary Investigation of Existing Conditions As Needed
3 Submit Conceptual Layout Schemes with Proposed Alternates --- NOA + 16
4 User Group Mtg (Review Proposed Schemes) 1 Day
5 Submit Revised Conceptual Layout Plans with Proposed Alternates ---
6 User Group Mtg (Review Conceptual Plans) 1 Day
7 Submit Revised Conceptual Layout Design for Approval --- NOA + 27
8 User Group Mtg (Review/Approve Conceptual Plans) 1 Day
9 Prepare 30% Schematic Design Submissions ---
Survey Existing Conditions, Coordinate Design with Consultants & VA Comments As Needed
10 Submit 30% Schematic Design Package --- NOA +57
VA Engineering 30% Review 5 Days (Min)
11 User Group 30% Schematic Design Review Meeting 1 Day
12 Prepare 60% “DD” Design Development Submissions ---
Confirm Existing Conditions, Coordinate Design with Consultants & VA Comments As Needed
13 Submit 60% “DD” Design Development Package --- NOA + 105
VA Engineering 60% Review 5 Days (Min)
14 User Group 60% “DD” Review Meeting 1 Day
15 Prepare 90% “CD” Construction Document Submissions ---
Coordinate Design with Consultants, Existing Conditions & VA Comments As Needed
16 Submit 90% “CD” Construction Documents Package --- NOA + 138
VA Engineering 90% Review 5 Days (Min)
17 User Group 90% “CD” Review Meeting 1 Day
18 Prepare 100% Bid Final Documents ---
Finalize Coordination with Consultants, Existing Conditions & VA Comments As Needed
19 Submit 100% Bid Final Documents with PE Stamps --- NOA + 150