This is a Statement of Work for the Potomac Pavement Preservation Project on the Monongahela National Forest. The scope of work encompasses pothole repairs, crack sealing, traffic control, and mobilization on Forest Roads 1, 104, and 112 within the Potomac Ranger District. Different levels of asphalt repair are required as detailed in the project plan set, with traffic control to be conducted in accordance with MUTCD standards. The contract incorporates WVDOT 2023 Standard Specifications for Roads and Bridges by reference for materials and installation purposes; however, special contract specifications govern in cases of conflict, and WVDOT specifications shall not govern measurement, payment, or acceptance determinations. Acceptance is based on conformance to contract requirements as verified through required testing and visual inspection.
The Period of Performance runs from May 5, 2026, through October 5, 2026, with work blackout periods during May 22-29, 2026, June 29-July 7, 2026, and September 3-11, 2026. The deliverables table specifies quantities in square feet for patch repairs and linear feet for crack sealing, with specific locations identified in the accompanying project plans. The acquisition is a Total Small Business Set-Aside under NAICS code 237310 (Highway, Street, and Bridge Construction) with a small business size standard of $45 million. The solicitation was issued as RFQ 12445526Q0033 by the Department of Agriculture Forest Service, with a questions deadline of March 9, 2026, at 2:00 p.m. Eastern Time.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 6 - Wage Determination WV20260061 Randolph CTY.pdf | ||
| Attachment 1 - Solicitation Terms and Conditions REV 12445526Q0033.pdf | ||
| Attachment 4 - Specifications.pdf | ||
| Attachment 2 - Schedule of Items REV.xlsx | XLSX spreadsheet | |
| Attachment 5 - Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work – Potomac Pavement Preservation Project Potomac Pavement Preservation
General Information
1.0 Scope of Work
The base bid consists of pothole repairs, crack sealing, traffic control, and mobilization. All operations are confined to Forest Roads 1, 104, and 112 on the Potomac Ranger District. Different levels of asphalt repair are required and are described in the project plan set. Traffic Control shall be in accordance with the MUTCD.
2.0 Background
Forest Roads 1, 104, and 112 are asphalt paved roads in need of repairs. These are single lane roads in the remote area of Spruce Mountain on the Potomac Ranger District. The WVDOT 2023 STANDARD SPECIFICATIONS for ROADS AND BRIDGES are hereby incorporated into this contract when referenced by the special contract specifications for the purposes of materials and installation. In case of conflict, the special contract specifications shall govern. Under no circumstance shall the WVDOT specifications govern measurement and/or payment. Acceptance will be based on conformance to contract requirements as determined by required testing and visual inspection. 100 Series Specifications from the WVDOT specifications do not apply. Requirements in the plans shall govern over any specification requirements.
3.0 Deliverables / Schedule
The Period of Performance is 5/5/2026 – 10/5/2026.
No work is permissible 5/22/26-5/29/26, 6/29/26-7/7/26, and 9/3/26-9/11/26.
See the table on page 2 for deliverables and approximate location. SF = Square Feet. LF = Linear Feet.
See plans and specifications for details regarding Dig-Out Patches and Mill Patches.