This is a Statement of Work (SOW) for road rehabilitation and drainage improvements on Forest Service Road 107, a Maintenance Level 3 (ML-3) roadway within the Lincoln National Forest's Smokey Bear Ranger District near Ruidoso, New Mexico.

The contractor must rehabilitate approximately 6.0 miles of roadway and complete all work including roadway reconditioning (blading and shaping), placement of approximately 9,100 tons of crushed aggregate surfacing meeting FP-14 Grading C requirements, roadside brushing and vegetation clearing, drainage ditch and lead-off restoration, and culvert cleaning, removal, upsizing, and installation. Key technical requirements include restoring roadway geometry to ML-3 standards with a minimum 3 percent center crown, compacting aggregate surfacing to a minimum 4-inch depth across a 12-foot travel lane using Compaction Method B with a 7–9 metric ton roller, maintaining 14-foot vertical clearance above the traveled way, and installing new corrugated metal pipe (CMP) or HDPE culverts of increased diameter as specified by the Contracting Officer's Representative (COR). Work must meet Maintenance Level 3 standards with a smooth, compacted, drained surface; effective drainage systems; properly installed culverts; and no continuous ruts, potholes, or obstructions remaining.

Deliverables due within specified timeframes include a Contractor Work Plan, Project Schedule, Traffic Control Plan (MUTCD-compliant), Safety Plan, Equipment List, Culvert Installation Summary, Daily Work Reports, Final Cleanup Certification, and Final Inspection Acceptance, all submitted to the COR. The contractor must furnish all labor, materials, equipment, and supervision, with measurement and payment made at contract unit prices for completed and accepted work. No government-furnished property is provided, and the contractor must designate a Contract Manager with full authority to act on all contract matters.

View the file

Other files

File Type Posted
127EAX26Q0059 Amendment 01.pdf PDF
Attachment 2 - Road Repair Map.pdf PDF
Attachment 4 - Wage Determination.txt TXT text file
Attachment 1 - Schedule of Items.docx DOCX document
127EAX26Q0059 - Forest Service Road 107.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Forest Service Road 107 (FSR 107) – Maintenance Level 3 Road RehabilitaƟon Agency: U.S. Department of Agriculture (USDA), Forest Service Forest: Lincoln NaƟonal Forest District: Smokey Bear Ranger District LocaƟon: Ruidoso, New Mexico Road ClassificaƟon: Maintenance Level 3 (ML-3)

1.0 PROJECT DESCRIPTION

The Contractor shall perform road rehabilitaƟon and drainage improvements on approximately

6.0 miles of Forest Service Road (FSR) 107, a Maintenance Level 3 (ML-3) roadway within the Smokey Bear Ranger District.

The objecƟve of this project is to restore roadway surface condiƟons, improve drainage performance, and remove and install upsized culverts to ensure safe and reliable access for Forest Service administraƟve and public use vehicles.

2.0 SCOPE OF WORK

The Contractor shall furnish all labor, materials, equipment, supervision, and incidentals necessary to complete the work described herein. Work includes, but is not limited to:

Roadway recondiƟoning (blading and shaping)

Placement of new aggregate surfacing

Roadside brushing and vegetaƟon clearing

Drainage ditch and lead-off restoraƟon

Culvert cleaning, removal, upsizing, and installaƟon

MobilizaƟon and site cleanup

3.0 TECHNICAL REQUIREMENTS

3.1 Roadway RecondiƟoning

The Contractor shall:

Blade and shape the traveled way, shoulders, turnouts, and intersecƟons.

Remove potholes, ruts, corrugaƟons, and wash boarding.

Restore roadway geometry consistent with ML-3 standards.

Drainage Requirements:

Restore a minimum 3 percent center crown, unless otherwise directed by the ContracƟng Officer’s RepresentaƟve (COR).

Remove berms created during operaƟons that impede drainage.

Clean and shape lead-off ditches to ensure water exits the roadway prism immediately.

Roadway recondiƟoning is complete when the surface is smooth, compacted, shaped to drain, and free of conƟnuous defects.

3.2 Aggregate Surfacing

Furnish and place approximately 9,100 tons of crushed aggregate surfacing meeƟng FP- 14 Grading C requirements.

Spread aggregate uniformly over the recondiƟoned roadway surface.

CompacƟon:

Moisture-condiƟon aggregate prior to compacƟon.

Compact using CompacƟon Method B with a 7–9 metric ton pneumaƟc, steel, or vibratory roller.

Compact across the full width of the traveled way unƟl no visible evidence of further consolidaƟon is observed.

Finished Surface Requirements:

Minimum 4-inch compacted depth across a 12-foot travel lane.

Aggregate shall not obstruct ditches, culverts, or drainage structures.

3.3 Roadside Brushing and Clearing

Cut and remove woody vegetaƟon within 10 feet of the road shoulder.

Maintain a minimum 14-foot verƟcal clearance above the traveled way.

Dispose of cut material so it does not obstruct drainage features or the roadway.

3.4 Culvert Cleaning, Removal, and InstallaƟon

1. Clean ExisƟng Culverts

Remove sediment, debris, and vegetaƟon to restore drainage funcƟon.

2. Remove ExisƟng Culverts

Remove undersized or damaged culverts as directed by the COR.

3. Install New Upsized Culverts

Furnish and install new corrugated metal pipe (CMP) or HDPE culverts of increased diameter, as specified by the COR.

Install culverts to proper line and grade to ensure posiƟve drainage.

4. Bedding, Backfill, and RestoraƟon

Provide suitable bedding material.

Backfill and compact material in liŌs to prevent seƩlement.

Restore the roadway prism and surfacing to ML-3 standards.

5. Inlet and Outlet Treatment

Shape and armor inlets and outlets to prevent erosion and undermining.

OperaƟon of equipment in live streams is prohibited.

3.5 MobilizaƟon

MobilizaƟon includes the movement of personnel, equipment, and materials necessary to perform the work. MobilizaƟon is complete when all required resources are available at the project site.

4.0 QUALITY STANDARDS

Work shall meet Maintenance Level 3 (ML-3) standards and is considered acceptable when:

The roadway surface is smooth, compacted, and shaped to drain

Drainage systems funcƟon effecƟvely

Culverts are properly installed and operaƟonal

No conƟnuous ruts, potholes, or obstrucƟons remain

5.0 DELIVERABLES

The Contractor shall submit the following deliverables to the ContracƟng Officer’s RepresentaƟve (COR):

Deliverable DescripƟon Due Date

Contractor Work Plan

WriƩen plan describing work approach, sequencing, equipment, staffing, and schedule

Within 7 calendar days of award

Project Schedule Timeline idenƟfying major work acƟviƟes and milestones

With Contractor Work Plan

Traffic Control Plan MUTCD-compliant plan appropriate for ML-3 roads

With Contractor Work Plan

Safety Plan Job hazard analysis and safety procedures With Contractor Work Plan

Equipment List List of major equipment to be used With Contractor Work Plan

Culvert InstallaƟon Summary

LocaƟon, material type, diameter, and length of new culverts installed

Prior to final inspecƟon

Daily Work Reports Summary of daily acƟviƟes and quanƟƟes completed

Daily or as requested

Final Cleanup CerƟficaƟon

WriƩen confirmaƟon of site cleanup At project compleƟon

Final InspecƟon Acceptance

ParƟcipaƟon in final walkthrough and correcƟon of deficiencies

At project compleƟon

6.0 MEASUREMENT AND PAYMENT

Measurement and payment shall be made at the contract unit prices for completed and accepted work. No separate payment will be made for incidental work required to complete the project.

7.0 SAFETY

The Contractor shall comply with all applicable safety and health requirements and conduct operaƟons to minimize hazards to the public, Forest Service personnel, and property.

8.0 GOVERNMENT-FURNISHED PROPERTY

None.

9.0 CONTRACTOR KEY PERSONNEL

The Contractor shall designate a Contract Manager with authority to act on behalf of the Contractor on all contract maƩers.