Attachment 3 Schedule of Material Submittals.pdf

PDF 51 KB Posted

Attached to
Convert Steam to Hot Water Heating, Building 106
Solicitation number
FA875120B0001
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

17-Oct-18

SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 1 of 5

CONTRACT NO. PROJECT NO ULDF 18-0322AE

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR

ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF

REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL

1. Lightgage metal framing systems 010110 1.02 A.1a 1 `

RESUBMITTAL

2. Steel doors 010110 1.02 A.1b 1

RESUBMITTAL

3. Steel door frames 010110 1.02 A.1c 1

RESUBMITTAL

4. Gypsum board systems 010110 1.02 A.1d 1

RESUBMITTAL

5. Painting 010110 1.02 A.1e 1

RESUBMITTAL

6. Record drawings 010110 3.02 1

RESUBMITTAL

7. Maintenance manuals 010110 3.04 1

RESUBMITTAL

8. Fabrication drawings 215901 1.02 A. 1

RESUBMITTAL

9. Piping systems 215901 1.02 B.1a 1

RESUBMITTAL

SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 2 of 5

CONTRACT NO. PROJECT NO ULDF 18-0322AE

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR

ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF

REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL

10. Pipe hanger and supports 215901 1.02 B.1b

RESUBMITTAL

11. Sprinklers 215901 1.02 B.2

RESUBMITTAL

12. Record drawings 215901 1.02 B.3

RESUBMITTAL

13. Maintenance manuals 215901 1.02 B.4

RESUBMITTAL

14. Piping systems 235001 1.02 A.1a

RESUBMITTAL

15. Pipe hangers and supports 235001 1.02 A.1b

RESUBMITTAL

16. Insulation systems 235001 1.02 A.1c

RESUBMITTAL

17. Fire stopping 235001 1.02 A.1d

RESUBMITTAL

18. Heat exchangers 235001 1.02 A.2a

SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 3 of 5

CONTRACT NO. PROJECT NO ULDF 18-0322AE

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR

ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF

REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL

19. Pumps 235001 1.02 A.2b

RESUBMITTAL

20. Hydronic system accessories 235001 1.02 A.2c

RESUBMITTAL

21. Flow meters 235001 1.02 A.2d

RESUBMITTAL

22. Steam pressure reducing stations 235001 1.02 A.2i

RESUBMITTAL

23. Initial cleaning and water conditiong 235001 1.02 A.2j

RESUBMITTAL

24. Automatic temperature controls 235001 1.02 A.2o

RESUBMITTAL

25. Air & hydronic systems test & balance 235001 1.02 A.2p

RESUBMITTAL

26. Gauges, thermometers, etc 235001 1.02 A.2q

RESUBMITTAL

27. Identification 235001 1.02 A.2r

SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 4 of 5

CONTRACT NO. PROJECT NO ULDF 18-0322AE

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR

ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF

REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL

28. Adjustable frequency controllers 235001 1.02 A.2s

RESUBMITTAL

29. Motors 235001 1.02 A.2t

RESUBMITTAL

30. Motor starters 235001 1.02 A.2u

RESUBMITTAL

31. Record drawings 235001 1.02 A.3

RESUBMITTAL

32. Maintenance manuals 235001 1.02 A.4

RESUBMITTAL

33. Wire and conduit 266010 1.07 A.1a

RESUBMITTAL

34. Supporting systems 266010 1.07 A.1b

RESUBMITTAL

35. Overcurrent protection devices 266010 1.07 A.1c

RESUBMITTAL

36. Identification 266010 1.07 A.1d

SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 5 of 5

CONTRACT NO. PROJECT NO ULDF 18-0322AE

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR

ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF

REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL

37. Luminaires 266010 1.07 A.2a

RESUBMITTAL

38. Receptacles and switches 266010 1.07 A.2b

RESUBMITTAL

39. Occupancy sensors 266010 1.07 A.2c

RESUBMITTAL

40. Panel boards 266010 1.07 A.2d

RESUBMITTAL

41. Disconnects/safety switches 266010 1.07 A.2e

RESUBMITTAL

42. Fire alarm/mass notification system 266010 1.07 A.2f

RESUBMITTAL

43. Emergency lighting system 266010 1.07 A.2g

RESUBMITTAL

44. Exit lights 266010 1.07 A.2h

RESUBMITTAL

45. Lighting control systems 266010 1.07 A.2i

File details come from the government source that posted it. Updated .