17-Oct-18
SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 1 of 5
CONTRACT NO. PROJECT NO ULDF 18-0322AE
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR
ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF
REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL
1. Lightgage metal framing systems 010110 1.02 A.1a 1 `
RESUBMITTAL
2. Steel doors 010110 1.02 A.1b 1
RESUBMITTAL
3. Steel door frames 010110 1.02 A.1c 1
RESUBMITTAL
4. Gypsum board systems 010110 1.02 A.1d 1
RESUBMITTAL
5. Painting 010110 1.02 A.1e 1
RESUBMITTAL
6. Record drawings 010110 3.02 1
RESUBMITTAL
7. Maintenance manuals 010110 3.04 1
RESUBMITTAL
8. Fabrication drawings 215901 1.02 A. 1
RESUBMITTAL
9. Piping systems 215901 1.02 B.1a 1
RESUBMITTAL
SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 2 of 5
CONTRACT NO. PROJECT NO ULDF 18-0322AE
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR
ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF
REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL
10. Pipe hanger and supports 215901 1.02 B.1b
RESUBMITTAL
11. Sprinklers 215901 1.02 B.2
RESUBMITTAL
12. Record drawings 215901 1.02 B.3
RESUBMITTAL
13. Maintenance manuals 215901 1.02 B.4
RESUBMITTAL
14. Piping systems 235001 1.02 A.1a
RESUBMITTAL
15. Pipe hangers and supports 235001 1.02 A.1b
RESUBMITTAL
16. Insulation systems 235001 1.02 A.1c
RESUBMITTAL
17. Fire stopping 235001 1.02 A.1d
RESUBMITTAL
18. Heat exchangers 235001 1.02 A.2a
SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 3 of 5
CONTRACT NO. PROJECT NO ULDF 18-0322AE
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR
ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF
REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL
19. Pumps 235001 1.02 A.2b
RESUBMITTAL
20. Hydronic system accessories 235001 1.02 A.2c
RESUBMITTAL
21. Flow meters 235001 1.02 A.2d
RESUBMITTAL
22. Steam pressure reducing stations 235001 1.02 A.2i
RESUBMITTAL
23. Initial cleaning and water conditiong 235001 1.02 A.2j
RESUBMITTAL
24. Automatic temperature controls 235001 1.02 A.2o
RESUBMITTAL
25. Air & hydronic systems test & balance 235001 1.02 A.2p
RESUBMITTAL
26. Gauges, thermometers, etc 235001 1.02 A.2q
RESUBMITTAL
27. Identification 235001 1.02 A.2r
SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 4 of 5
CONTRACT NO. PROJECT NO ULDF 18-0322AE
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR
ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF
REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL
28. Adjustable frequency controllers 235001 1.02 A.2s
RESUBMITTAL
29. Motors 235001 1.02 A.2t
RESUBMITTAL
30. Motor starters 235001 1.02 A.2u
RESUBMITTAL
31. Record drawings 235001 1.02 A.3
RESUBMITTAL
32. Maintenance manuals 235001 1.02 A.4
RESUBMITTAL
33. Wire and conduit 266010 1.07 A.1a
RESUBMITTAL
34. Supporting systems 266010 1.07 A.1b
RESUBMITTAL
35. Overcurrent protection devices 266010 1.07 A.1c
RESUBMITTAL
36. Identification 266010 1.07 A.1d
SCHEDULE OF MATERIALS SUBMITTALS - 100% CONSTRUCTION DOCUMENTS Page 5 of 5
CONTRACT NO. PROJECT NO ULDF 18-0322AE
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF REQUIRED DATE / TIME OF DATE FOR RETURN DATE CONTRACTOR
ITEM / TYPE OF SUBMITTAL CONTRACT REFERENCE COPIES SUBMITTALS AFTER NTP. DATE IFKO WARDED SUSPENSE NOTIFIED OF
REQ'D BRIEF AT PRECON RECEIVED TO IFOC DATE APPROVAL / DISAPPROVAL
37. Luminaires 266010 1.07 A.2a
RESUBMITTAL
38. Receptacles and switches 266010 1.07 A.2b
RESUBMITTAL
39. Occupancy sensors 266010 1.07 A.2c
RESUBMITTAL
40. Panel boards 266010 1.07 A.2d
RESUBMITTAL
41. Disconnects/safety switches 266010 1.07 A.2e
RESUBMITTAL
42. Fire alarm/mass notification system 266010 1.07 A.2f
RESUBMITTAL
43. Emergency lighting system 266010 1.07 A.2g
RESUBMITTAL
44. Exit lights 266010 1.07 A.2h
RESUBMITTAL
45. Lighting control systems 266010 1.07 A.2i