Attachment 3 - PWS Generator Maintenance and Testing.pdf

PDF 448 KB Posted

Attached to
J030--Generator and Fuel Maintenance - Services
Solicitation number
36C25026Q0829
Issued by

About this file

This is a Performance Work Statement (PWS) for the service, testing, and maintenance of emergency generators for Cincinnati VAMC and Fort Thomas Domiciliary.

The contract is a firm fixed price/indefinite quantity award with a base year running from September 1, 2026, to April 30, 2027, followed by four one-year option periods exercisable at government discretion through April 30, 2031. The contractor must provide on-site maintenance, inspection, testing, major service, and load bank testing for six emergency power generators and fuel quality testing and maintenance for seven underground fuel storage tanks and six day tanks located at Cincinnati Veterans Affairs Medical Center in Ohio and Fort Thomas Domiciliary in Kentucky. Testing and maintenance shall be performed mid-November of the base year, mid-October of option year one, mid-September of option year two, and mid-August of option years three and four. The contract is awarded under FAR Part 12 for commercial products and services.

Key contractor responsibilities include providing all equipment, supplies, parts, personnel, labor, and management necessary for preventive maintenance; performing annual load bank testing for four continuous hours with prescribed load percentages and documented measurements; conducting annual fuel conditioning, polishing, and quality analysis testing on underground storage tanks per ASTM methods; performing day tank maintenance including float switch and pump testing; replacing all generator batteries during option year two; and performing major cooling system service on two generators during the base year. All maintenance must comply with original manufacturer specifications and recommendations. The contractor must maintain OEM training and certifications, submit a Quality Control Plan, provide a contract manager available within 24 hours, ensure proper waste disposal of hazardous materials and used oil per EPA and state regulations, maintain required insurance coverage (general liability minimum $1,000,000 per occurrence), and submit comprehensive service reports within ten business days of completing work. The government will provide facility access and utilities but no office space or storage facilities. Payment is made monthly in arrears on a lump-sum basis after proper invoice submission and verification that all required work has been completed in accordance with contract stipulations.

View the file

Other files

File Type Posted
36C25026Q0829 0001.docx DOCX document
36C25026Q0829.docx DOCX document
Attachment 2 - SCA 2015-4719.pdf PDF
Attachment 1 - VHA Directive 1192-01.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Service, Testing and Maintenance of Emergency Generators for Cincinnati VAMC and Fort Thomas Domiciliary

Performance Work Statement

1. GENERAL

1.1. Purpose: The intention of this Performance Work Statement (PWS) is to obtain on-site maintenance, inspection, testing, major service, and load bank testing for six (6) emergency power generators and fuel quality testing and maintenance for seven (7) underground fuel storage tanks and six (6) day tanks located at the Cincinnati Veterans Affairs Medical Center (VA) and the Fort Thomas Domiciliary (located in Fort Thomas KY) by means of a firm fixed price/indefinite quantity Contract with a base year and four (4) one-year option periods to be exercised at the discretion of the Government.

1.2. PERIOD OF PERFORMANCE: The period of performance for this requirement is summarized as follows:

• Base Year from: 9/01/2026 to 4/30/2027

• Option Year One (OY1) from: 5/01/2027 to 4/30/2028

• Option Year Two (OY2) from: 5/01/2028 to 4/30/2029

• Option Year Three (OY3) from: 5/01/2029 to 4/30/2030

• Option Year Four (OY4) from: 5/01/2030 to 4/30/2031

1.3. GENERAL REQUIREMENTS

A. Contractor shall provide all management, supervision, personnel, labor, parts, supplies, materials, tools, equipment, incidental engineering services, overtime pay, weekend and holiday premium pay, travel expenses, and transportation necessary to perform all maintenance, inspection, testing, and other services required to maintain emergency generators and associated fuel storage systems in a safe and working condition as originally specified by the equipment manufacturer.

B. Maintenance and services shall be provided for each emergency generator in accordance with manufacturer’s recommendations.

C. Services shall be executed to interfere as little as possible with normal functioning of the Medical Center as a whole.

D. Testing and maintenance shall be performed as follows:

• Mid-November of the base year.

• Mid-October of option year 1.

• Mid-September of option year 2.

• Mid-August of option years 3, and 4.

1.3.1. Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall identify and define the management concept for ensuring compliance with all contract requirements. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor will have an ongoing quality assurance and /or quality improvement program designed to objectively and systematically measure, assess, and improve performance to enhance patient care and all patient care services. The contractor’s quality control program is the means by which the contractor assures that all work complies with the requirement of the contract. The contractor shall provide a copy of the QCP with their offeror as specified by the Contracting Officer and upon request thereafter. After acceptance of the quality control plan, the contractor shall immediately notify the contracting officer of any proposed changes to their quality control program and submit a change request in writing to the contracting officer. The contractor shall furnish copies of these records if requested by the Contracting Officer, GOVERNMENT PM or individual(s) designated by the GOVERNMENT PM and/or CO in writing. The contractor’s quality control program shall include the following:

• Defined roles and responsibilities for quality control personnel.

• Regularly scheduled audits and inspections.

• Procedures for the identification and correction of deficiencies.

• Continuous feedback and improvement mechanisms.

• Detailed documentation and record-keeping processes.

• Timely reporting of quality control activities and findings to the Contracting Officer.

• Training programs for staff on quality control standards and practices.

1.3.2. Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s):

• The performance standards will be applied based on the specific criteria outlined in the contract, focusing on key performance indicators (KPIs) relevant to the services provided.

• The frequency of surveillance will be determined by the criticality of the service areas and may include daily, weekly, monthly, or quarterly evaluations, depending on the nature of the work and associated risks.

• The minimum acceptable defect rate(s) will be established in consultation with relevant stakeholders and will be specific to each service area, ensuring that the contractor maintains a high level of performance and consistent quality.

• The Quality Assurance Surveillance Plan will also include detailed procedures for the documentation and reporting of surveillance activities, ensuring transparency and accountability. Any discrepancies or deficiencies identified during the surveillance will be promptly communicated to the contractor for immediate corrective action. The Government will maintain comprehensive records of all surveillance activities, findings, and any –

• + actions taken, and will use this information to continuously assess and improve the effectiveness of the quality assurance process.

1.3.3. Federally Recognized Holidays: The contractor is not anticipated but may be required to provide service on Federally recognized holidays in accordance with the terms and conditions established in this PWS to include but not limited to the following:

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Juneteenth Christmas Day Independence Day

Any other day specifically declared by the President of the United States to be a federal holiday. When one of the holidays falls on Sunday, the following Monday shall be observed as a Federal Holiday. When a holiday falls on a Saturday, the preceding Friday shall be observed as a Federal Holiday.

1.3.4. Hours of Operation: The business hours of operation for Cincinnati VA Medical Center (VAMC) in Ohio and Fort Thomas Domiciliary in Kentucky is Monday through Friday from 7:00 AM to 3:30 PM EST, except on Federally recognized holidays.

1.3.5. Place of Performance: The contractor shall furnish services in accordance with the terms and conditions of this contract as requested by the authorized government representative(s) designated in writing by the GOVERNMENT PM and/or CO in accordance with the procedures specified within this PWS for the following location:

Cincinnati VA Medical Center

3200 Vine Street

Cincinnati, Ohio 45220-2213

Cincinnati VA Medical Center - Ft. Thomas

1000 South Ft. Thomas Ave.

Ft. Thomas Ky. 41075-2305

1.3.6. Type of Contract: The government intends to award a single-award firm-fixed price (FFP) contract for the effort specified herein. The base and option periods (if any) specified in the PRICE/COST SCHEDULE shall be exercised at the discretion of the government. The authority that will be utilized to award this effort is FAR Part 12 (Acquisition of Commercial Products and Commercial Services).

1.3.7. Security Requirements and Background Checks: All contractor and subcontractor employees must comply with

Federal, State, Local, and Department of Veterans Affairs security requirements and background checks to perform services in support of VA medical facilities in the states of Ohio and Kentucky. Services must be performed in accordance with contract terms at the contractor’s facility unless otherwise required (e.g., meetings, site visits), which must be coordinated with the Government Program Manager. Personnel requiring access to any VAMC property must consent to background checks or will be denied facility access. Required information for background checks includes: full name, driver’s license number and/or social security number, date of birth, and a completed background check questionnaire.

1.3.8. AMC/VAACC Identification Badges: The contractor shall ensure that all personnel obtain VAMC/VAACC identification badges from the VAMC/VAACC security personnel office as appropriate in compliance with all federal and local VAMC/VAACC facility policies in coordination with the government program manager if required.

1.3.9. Employment Eligibility and Credentialing Requirements: Contractors shall ensure their employees and those of their Subcontractors possess proper credentials allowing them to work in the United States. No compensation will be provided for delays or expenses related to compliance with this requirement. Contractors are not excused from proceeding with the Contract due to credentialing issues.

1.3.10. POST AWARD CONFERENCE/PERIODIC PROGRESS MEETINGS: The contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, government program manager, and other government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.3.11. GOVERNMENT PROGRAM MANAGER (GOVERNMENT PM): The government PM will be identified by the cognizant government Contracting Officer in writing. The PM monitors all technical aspects of the contract and assists in contract administration. The PM is authorized to perform the following functions: assure that the contractor performs the technical requirements of the contract: maintain written and oral communications with the contractor concerning technical aspects of the contract that are within scope: monitor contractor's performance and notifies both the contracting officer and contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of contractor personnel. The PM shall be specified in writing by the CO and is not authorized to change any of the terms and conditions of the resulting contract.

1.3.12. KEY PERSONNEL: The following personnel are considered key personnel by the government: Project Manager/Alternate Project Manager and Officer in Charge. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.

1.3.13. IDENTIFICATION OF CONTRACTOR EMPLOYEES: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.3.14. CONTRACTOR TRAVEL: Not Applicable

1.3.15. OTHER DIRECT COSTS: Not Applicable

1.3.16. DATA RIGHTS: Not Applicable

1.3.17. ORGANIZATIONAL CONFLICT OF INTEREST: Not Applicable

1.3.18. PHASE-IN / PHASE-OUT PERIOD: Not Applicable

2. DEFINITIONS AND ACRONYMS

2.1. DEFINITIONS:

• COMMUNITY LIVING CENTER (CLC). The Community Living Centers (CLCs) are inpatient units for VAMC nursing homes.

• CONTRACT TASK ORDERS. Award of a funded contract task order for the appropriate period of performance is required prior to the commencement of any/all work in accordance with FAR part 16.506 as specified herein.

• CONTRACTOR. A vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime contractor and its employees. The contractor is fully responsible for performance of their sub-contractor(s) and shall ensure that their subcontractor(s) are fully compliant with the terms and conditions of this contract at all-times.

• CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

• CONTRACTING OFFICER'S TECHNICAL REPRESENTATIVE (COTR). An employee of the U.S. Government appointed by the Contracting Officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

• DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

• DELIVERABLE. Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.

• GOVERNMENT PROGRAM MANAGER (PM): An individual specified by the contracting officer in writing to provide technical guidance for work within the scope of this contract. This individual has authority to provide technical direction to the contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications.

• KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

• NOT TO EXCEED (NTE). The price and/or quantity that the contract or purchase order shall not exceed.

• PATIENT BUSINESS SERVICES. An administrative department which processes patients’ medical records, appointments, etc.

• PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

• PROGRAM MANAGER (PM) - GOVERNMENT: An individual specified by the contracting officer in writing to provide technical guidance for work within the scope of this contract. This individual has authority to provide technical direction to the contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications.

• QUALITY ASSURANCE. The government procedures to verify that services being performed by the contractor are performed according to acceptable standards.

• QUALITY CONTROL. All necessary measures taken by the contractor to assure that the quality of an end product or service shall meet contract requirements.

• QUALITY ASSURANCE EVALUATOR(S): Government personnel responsible for surveillance of contractor performance.

• QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be utilized by the government for surveillance of contractor performance.

• QUALITY CONTROL PLAN (QCP): The QCP is the contractor's management plan for executing the contract which shall be provided to the government upon request and whenever updated by the contractor. The contractor QCP describes the way in which the contractor will produce the deliverables, and the step-by-step approach that will be taken to ensure the quality of service provided to the government.

• SUBCONTRACTOR(S). A subcontractor is one who enters into a contract with a contractor (or prime contractor).

• THE JOINT COMMISSION (TJC). A national not-for-profit organization dedicated to administering accreditation programs that improve the care, safety and treatment of patients in a health care facility and environment.

2.2. ACRONYMS:

AQL Access Control List CBOC Community Based Outpatient Clinic CFR Code of Federal Regulations CLC Community Living Centers

CO Contracting Officer CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer’s Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 LEADS Law Enforcement Agency Data System NEC National Electric Code NFPA National Fire Protection Association NHCU Nursing Home Care Unit NTE Not to Exceed NTP Notice to Proceed OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs OAC Ohio Administrative Code ORC Ohio Revised Code PBS Patient Business Services PIPO Phase In/Phase Out PACS Physical Access Control System PO Purchase Order issued by the CO/COR POC Point of Contact PM Program Manager PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Plan QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SaaS Software as a Service SDS Safety Data Sheet provided by Contractor SMS Security Management System SSA Site Support Agreement TE Technical Exhibit VAAR Veteran’s Administration Acquisition Regulation VA United States Department of Veterans Affairs VAPS VA Police System VISTA Veteran’s Health Information Systems and Technology Architecture VSC VHA Service Center VAACC Veteran’s Administration Ambulatory Care Clinic VAMC Veteran’s Administration Medical Center VHA V eteran’s Health Administration VHA PM Veteran’s Health Administration Procurement Manual

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1. SERVICES: Not applicable.

3.2. FACILITIES: The VA will provide access to all equipment and areas as needed for servicing, maintenance, and inspection of all serviced equipment on VA premises. The VA will not provide office space, storage, or operational facilities to the Contractor. The Contractor is responsible for securing and maintaining any required office and storage space at their own expense.

3.3. UTILITIES: The VA will furnish the following services at existing outlets, for use in those facilities provided by the VA/VAMC and as required for the work to be performed under this Contract: electricity, fresh water, sewage service, and non-hazardous refuse collection (from existing collection points). Disposal of equipment and construction debris is the responsibility of the Contractor.

3.4. EQUIPMENT: Not applicable.

3.5. MATERIALS: Not applicable.

4. CONTRACTOR RESPONSIBILITIES AND REQUIREMENTS:

1.1. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

A. The contractor shall provide all equipment (including diagnostic and repair tools), supplies, specialty items, and materials (such as lubricants, cleaning supplies, low VOC paints) necessary to perform all services as defined in this PWS. All supplies and replacement parts needed for preventive maintenance activities (e.g. filters, fluids, belts, hoses, batteries) must be provided. The contractor must ensure that all lubricants, cleaners, and chemicals utilized meet or exceed original manufacturer recommendations.

B. The contractor shall provide all personnel, supervision, management, incidental engineering services, overtime pay, weekend and holiday pay, travel expenses and transportation, and other items necessary to perform all services under this contract as defined in this PWS and in accordance with the terms and conditions of this contract.

C. Contractor shall not make any alteration or additions to the equipment without prior written approval from the

CO/COR.

D. Contractor shall immediately notify the CO/COR of any equipment or environmental conditions which impair or jeopardize the safe and continuous functioning of the equipment.

1.2. CONTRACTOR REQUIREMENTS:

A. Contractor Experience and References Requirements: Contractor is currently engaged in maintenance, repair, inspection, and testing of emergency power generation equipment. Contractor shall have a minimum of five (5) years within the last seven (7) years of successful experience maintaining emergency power generation equipment identical or similar to the equipment listed in this Contract. Offerors shall submit references for the five (5) years of experience including names, addresses, and telephone numbers of specific companies and key personnel to contact.

B. Contract Manager Availability and Authority: The Contractor shall provide a Contract Manager who shall be responsible for the performance of all work. The name of the Contract manager and an alternate shall be designated in writing to the CO/COR prior to the Contract start date. Changes to personnel shall be submitted to the Government within five (5) working days of changes. The Contract Manager or alternate shall have full authority to act on all Contract matters relating to the daily operation of the Contract. The Contract Manager or alternate shall be available to speak/meet with the CO or COR within twenty-four (24) hours of request during normal operating hours, and or within the next business day after Friday or a Federal holiday.

C. Technician Qualifications: All mechanics/technicians must possess OEM training and certifications for the specific manufacturer and model of emergency generator or fuel system serviced under this contract.

Documentation of certifications shall be submitted to the CO/COR within 30 days of award and updated annually.

D. Employee Appearance/Conduct: Contractor shall ensure that personnel always present a professional appearance and that their conduct shall not reflect discredit upon this installation or the Department of

Veterans Affairs. Contractor shall remove from the job site any employee for reasons of misconduct or security. The removal from the job site of such a person shall not relieve the Contractor of the requirement to provide sufficient personnel to perform adequate and timely service. Contractor's employees shall observe and comply with all local and VA Medical Center, regulations, and procedures concerning fire, safety, environmental protection, sanitation, security, tobacco usage, gratuities, and possession of firearms or other lethal or illegal weapons or substances.

E. Waste Disposal:

1. The Contractor shall be responsible for the characterization, packaging, removal, transportation, and final treatment/disposal of all hazardous waste, universal waste, and used oil generated under this contract, in accordance with the Resource Conservation and Recovery Act (RCRA), implementing EPA regulations, and all applicable Ohio and Kentucky statutes, regulations, and local ordinances.

2. The Contractor shall ensure that all waste streams generated (including used oil, used oil filters, sorbents and other cleanup materials, fuel samples, laboratory residuals, and any associated containers) are evaluated and managed under the appropriate regulatory framework (RCRA hazardous waste, universal waste, used oil management standards, or non-hazardous solid waste) and shall not rely solely on generator status assumptions.

3. The Contractor shall provide all necessary containers, labels, and documentation and shall ensure that the VA facilities maintain compliance with applicable generator, storage, and land disposal restriction (LDR) requirements for any hazardous waste generated as a result of the services performed.

F. Used Oil Management and Disposal:

1. Used oil generated from generator fuel oil testing, equipment maintenance, and associated activities under this contract shall be managed in accordance with EPA’s Used Oil Management Standards at 40 CFR Part 279 and all applicable state and local requirements, including Ohio Administrative Code Chapter 3745-279 and Kentucky Administrative Regulations Title 401, Chapter 44 (Standards for the Management of Used Oil).codes.

2. Unless the VA specifically directs disposal as hazardous waste, used oil shall be managed and shipped for legitimate recycling under the used oil standards; if disposal as hazardous waste is required (e.g., failure of halogen or PCB criteria), the Contractor shall implement all applicable hazardous waste generator, manifesting, and disposal requirements on behalf of the VA facilities.

The contractor shall:

• Contractor Responsibilities – Regulatory Compliance:

1. The Contractor shall ensure full compliance with EPA regulations at 40 CFR Part 279 and all applicable Ohio and Kentucky used oil, hazardous waste, and universal waste requirements, including but not limited to Ohio OAC Chapter 3745-279 and Kentucky 401 KAR 44, for all activities conducted under this contract.

2. The Contractor shall maintain current knowledge of regulatory changes affecting used oil and hazardous/universal waste management in Ohio and Kentucky during the contract term and shall notify the VA in writing within thirty (30) days of any regulatory change that materially affects the contract obligations or VA facility practices.

• Storage, Handling, and Labeling:

1. The Contractor shall implement proper storage and handling procedures to ensure that used oil is accumulated only in tanks and containers that are in good condition, not leaking, and compatible with the oil being stored, and that all such tanks and containers are clearly marked with the words “Used Oil” in a visible and durable manner, consistent with 40 CFR 279 and corresponding Ohio and Kentucky rules.

2. The Contractor shall ensure that used oil is not mixed with hazardous waste, except where expressly allowed by regulation for very small quantity generators and only with prior written approval from the VA Contracting Officer; any used oil that is mixed with hazardous waste or otherwise fails the rebuttable presumption (e.g., total halogens greater than 1,000 ppm or PCBs ≥ 50 ppm) shall be managed and shipped as hazardous waste.

3. The Contractor shall provide written procedures and training materials to its personnel performing work at the VA facilities describing proper used oil segregation, labeling, spill prevention, and response practices; these materials shall be made available to VA Environmental staff upon request.

• Transportation and Final Disposition:

1. The Contractor shall utilize only properly registered and permitted transporters for used oil and hazardous/universal waste, including transporters with valid EPA identification numbers and any required state registrations for Ohio and Kentucky.

2. Used oil managed for recycling shall be shipped only to authorized used oil processors, re-refiners, burners, or marketers that operate in compliance with 40 CFR Part 279 and applicable state regulations.

3. Any used oil or waste determined to be hazardous shall be shipped only to RCRA-permitted treatment, storage, and disposal facilities (TSDFs), with appropriate manifests and land disposal restriction documentation, in accordance with federal and state requirements.

4. The Contractor shall ensure that no used oil generated under this contract is applied as a dust suppressant, disposed via surface impoundments or waste piles, or otherwise managed in a manner prohibited under federal or state used oil regulations.

• Documentation and Recordkeeping:

1. For used oil shipments managed under 40 CFR Part 279, the Contractor shall maintain shipping records (e.g., bills of lading or equivalent documentation) for at least three (3) years from the date of shipment, including at minimum: date of shipment; quantity shipped; VA facility name and address; transporter name and EPA ID number; and destination processor, re-refiner, burner, marketer, or disposal facility name and address.

2. For waste streams shipped as hazardous waste, the Contractor shall prepare and use RCRA hazardous waste manifests and retain copies of all manifests, land disposal restriction (LDR) notifications, and related documentation for at least three (3) years from the date of shipment, or longer if required by applicable regulations or permit conditions.

3. The Contractor shall provide the VA facility with copies (electronic or hard copy) of all used oil shipping records and hazardous/universal waste manifests within fifteen (15) calendar days of each shipment and shall maintain a consolidated waste management log covering all waste streams generated under this contract.

4. Upon request, the Contractor shall provide summary reports to the VA Environmental staff at least annually, documenting volumes, destinations, and disposition methods for used oil and other wastes generated by this contract.

• Testing, Classification, and Certification:

1. The Contractor shall arrange for representative analytical testing of used oil generated under this contract, at a frequency agreed upon with the VA (e.g., per batch or per defined volume), to determine total halogens, and as applicable, PCBs and other parameters necessary to determine regulatory status (on-spec vs off-spec used oil, hazardous waste determination, and any TSDF acceptance criteria).

2. Used oil containing more than 1,000 ppm total halogens shall be presumed to be hazardous waste under the rebuttable presumption unless the Contractor provides analytical and technical documentation demonstrating that the halogens are from sources allowed under 40 CFR 279 (e.g., certain chlorinated cutting oils) and not from mixing with a listed hazardous waste.

3. If testing indicates PCBs at concentrations of 50 ppm or greater, the oil shall not be managed under 40 CFR Part 279 and must instead be handled and disposed of in accordance with applicable TSCA and hazardous waste requirements; the Contractor shall notify the VA Environmental staff within five (5) business days of such results and propose a compliant management plan.

4. The Contractor shall certify in writing, for each shipment of used oil and hazardous/universal waste, the analytical basis for classification, the regulatory status (used oil vs hazardous vs universal vs non-hazardous), and the approved method of treatment, recycling, or disposal; all supporting laboratory reports and chain-of-custody forms shall be provided to the VA and retained with the records described in the Document and Recordkeeping part of this section.

• Spill Prevention, Response, and Reporting:

1. The Contractor shall implement spill prevention and good housekeeping measures for used oil and associated wastes, including maintaining containers and transfer equipment in good condition, utilizing appropriate secondary containment where required or where reasonably necessary to prevent releases, and ensuring that spills and leaks are promptly stopped, contained, and cleaned up.

2. The Contractor shall develop and follow site-specific spill response procedures for work conducted at the VA facilities, including immediate notification of VA facility staff of any release of used oil or hazardous/universal waste and coordination with the VA’s existing Spill Prevention, Control, and Countermeasure (SPCC) and emergency response plans, where applicable.

3. The Contractor shall comply with all federal, Ohio, and Kentucky reporting requirements for releases of used oil or hazardous waste, including timely notification to appropriate regulatory agencies when release thresholds are met, and shall provide written incident reports to the VA within five (5) business days of any reportable release.

4. All spill cleanup materials (e.g., sorbents, rags, booms) that contain free-flowing or saturated oil and are generated by the Contractor’s activities shall be evaluated for hazardous waste characteristics and managed accordingly (either as hazardous waste, used oil-contaminated solids where acceptable, or non-hazardous waste) with appropriate documentation.

The Contractor shall be fully responsible for ensuring that all activities related to the generation, storage, handling, testing, transportation, recycling, and disposal of used oil and other wastes arising from this contract adhere to the requirements of Sections A through H, thereby supporting the VA facilities’ regulatory compliance, minimizing environmental liability, and protecting human health and the environment.

The Contractor shall indemnify and hold harmless the VA facilities from penalties, enforcement actions, or cleanup costs that result from the Contractor’s failure to comply with applicable waste management regulations or the requirements of this contract, to the extent permitted by federal procurement and VA policy.

G. Parking: Onsite parking is prohibited. Contractor shall secure offsite parking of all vehicles while performing any onsite service at the contractor’s expense. Contractor shall be permitted limited short term parking for loading/unloading of vehicles at approved locations.

H. Job Service Reports: Service personnel shall report to the CO/COR or authorized representative upon arrival at the facility and again upon completion of any required work. Service/work tickets shall be created for each task performed under this performance work statement. Service/work tickets shall identify equipment serviced, date and time of service, and all work performed. A copy of the work ticket containing a complete description of all work performed shall be given to the CO/COR or authorized representative.

4.3. SAFETY and Infection Control

4.3.1. INJURY and ACCIDENT REPORTS:

A. Contractor shall immediately report to the CO/COR in a manner and on the forms prescribed by the VAMC all accidents resulting in injury, trauma, death, hazardous exposures, and occupational disease.

B. Written reports for all incidents shall be provided within two (2) working days and include the cause, what, where, and when the incident occurred as well as repairs and tests performed to correct the cause having occurred under work covered by this contract.

4.3.2. General Safety:

A. The Contractor shall adhere to all OSHA, EPA, NFPA Life Safety Codes, and all other regulatory requirements.

B. In performance of this Contract, the Contractor shall follow VAMC safety policy and standards for safe work practices and take such safety precautions as the VAMC Safety Officer or designee or the CO/COR may determine to be reasonably necessary to protect the lives and health of occupants of the building. The

Contractor shall comply with VAMC tobacco policy, which designates all VA property as a NO-Tobacco area.

C. The Contractor is responsible for the supervision and management of all their employees while on government property and shall ensure compliance with the scope of work and all requirements referenced in this contract.

The provisions outlined in the scope of work do not relieve the Contractor of this responsibility. The Contractor shall ensure the safety and health of all patients, employees, visitors, and Contractor personnel at all times, and shall comply with all applicable OSHA safety and health standards. The selection, assignment, and management of Contractor employees are solely the responsibility of the Contractor. The Contractor shall not employ any individual identified as a potential threat to the health, safety, security, general well-being, or operation of the

VAMC facility or personnel. The Contractor is fully responsible for the performance and conduct of all employees at all times and shall not permit any employee to perform work under this Contract while under the influence of alcohol, drugs, or any other incapacitating agent.

D. The Contractor shall submit to the Contracting Officer, prior to the start of the Contract, the Safety Data Sheets

(SDS) for all potentially hazardous materials (lubricants, cleaners, fluids, etc.) to be used in the facility in performance of the Contract, and will not use, in the facility, such materials which have not been so cleared in advance with the VAMC. SDS for new chemicals shall be furnished prior to the arrival of the chemical on site.

The Contractor shall maintain copies of all SDS sheets to assure compliance with all laws and requirements regarding the “Right to Know” law.

E. Contractor is responsible to identify, provide and maintain all personal protective equipment (PPE) required to perform the duties outlined in the Contract. In addition, the Contractor is responsible for identifying and providing all applicable safety programs required to perform the work i.e., lockout/tag out, confined space entry, universal precautions, etc. Training required for safety programs and the proper use of PPE shall be provided by employer, and documentation maintained by the Contractor.

F. The Contractor shall obtain a Hot Work Permit from the Safety staff or the CO/COR in advance whenever soldering, welding, grinding, and using a cutting torch, or other open flame, spark or heat producing equipment is used. The Contractor is required to follow all requirements outlined for the issuance of the Hot Work Permit.

G. Contractor shall be notified of any non-compliance with safety regulations. The Contractor shall, after receipt of such notice, immediately correct the condition and notify the Contracting Officer in writing that the condition has been corrected. If, in the opinion of the CO/COR or the VAMC Safety Officer the condition is life threatening he/she shall instruct the Contractor to stop work until the condition has been corrected. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order halting all or any part of the work, and

Contractor may be held in default. The Contractor bears all costs of stop-work time and correcting safety hazards.

H. Contractor shall ensure all safety guards, equipment panels, doors, covers, devices, etc. are installed prior to placing equipment into normal operation. Any lost, damaged or missing guards, panels, doors, covers, devices are to be supplied or replaced by the contractor to ensure the safety of personnel.

4.3.3. Infectious Control:

A. To carry out its mission as a health care facility, the VAMC maintains the highest level of cleanliness as a part of its Infectious Control Program to ensure that patient health is not compromised. The Contractor shall maintain all equipment covered under the scope of work to these standards and comply with all other reasonable requests of the CO/COR related to Infectious Control measures.

B. Generator equipment, including control cabinets shall be wiped down with appropriate cleaning supplies to remove any dust or dirt accumulation. Before cleaning is performed ascertain if any build up indicates a problem with the equipment and requires service or repair.

C. Upon completion of daily work, contractor shall sweep all floors, remove all trash, rubbish, and waste materials.

CO/COR shall inspect equipment and equipment spaces for cleanliness. The inspection shall consist of a visual observation to detect any accumulation of dust, dirt or debris on any surface required to be kept clean under this Contract.

4.4. SPARE/REPLACEMENT PARTS

A. The Contractor shall be responsible for supplying all parts, materials, and consumables required to perform all scheduled preventive maintenance and testing described in this contract. This includes, but is not limited to:

OEM or approved equivalent filters, fluids, hoses, belts, batteries, cleaning supplies, and any other parts routinely replaced or consumed during preventive maintenance activities. All preventive maintenance parts and materials shall be of the original manufacturer’s design and specification, or equal thereto. Reverse engineered and/or refurbished parts shall not be utilized under the terms of this contract without explicit written permission from the Contracting Officer.

B. There shall be no borrowing of parts except in an emergency or with written consent from the VA.

5. REQUIREMENTS – Specific Tasks:

5.1. GENERAL (APPLICABLE TO ALL CONTRACT LINE ITEMS): The contractor shall perform major preventive maintenance service, load bank testing, battery replacements and major cooling service for emergency generator systems identified in Appendix A of this PWS. Contractor shall perform fuel quality analysis testing and maintenance for fuel storage tanks identified in Appendix B of this PWS.

A. Contractor shall verify proper equipment operation both prior to and immediately following performance of any maintenance or testing activities.

B. Annual load bank testing shall be performed upon completion of all preventive maintenance activities.

C. Base year testing, service and maintenance shall be performed within thirty (30) days of initial award. Option year testing, service and maintenance shall be performed mid-August of each contract option year.

D. Contractor shall provide advanced notification to the CO/COR no less than ten (10) business days prior to scheduled maintenance and service activity. Service must not interfere with needs or demands of the hospital.

The V.A. reserves the right to defer proposed service dates based upon the needs of the agency.

5.2. Task 1 - MAJOR PREVENTIVE MAINTENANCE SERVICE FOR EMERGENCY GENERATORS (CLINs-0001, 1001, 2001, 3001 and 4001):

A. Contractor shall annually perform major preventive maintenance service on all emergency generators listed in Appendix A. The contractor shall change the lube oil, primary and bypass lube filters, fuel filters, water separator filter, air filters and water filters. All filters shall be OEM. Contractor is responsible for removing and disposal of all used materials and waste. Maintenance shall include the following:

• Battery & Battery Charger System – Contractor shall clean and tighten all battery terminals and verify integrity of cables and connectors. Contractor shall load test battery; measure specific gravity and conductance of each battery cell; inspect electrolyte level and add fluid if necessary. Contractor shall verify proper operation and float voltage of external battery charger; and verify and record output of engine alternator. Battery racks shall be cleaned.

• Engine – Contractor shall verify and record oil pressure and coolant temperature. Contractor shall test all safety shutdown circuits and alarms including over speed, over crank, low oil pressure, high water temperature and low coolant level. Contractor shall clean and inspect air intake system including crankcase breather and turbocharger. Contractor shall inspect the muffler system and drain condensation trap (if applicable) and verify presence of bird screen and rain cap operation. Contractor shall inspect engine starting system, verify cable integrity and connections; inspect exhaust flex coupling and piping for leaks and proper connection. Contractor shall check for abnormal vibration or noise.

• Fuel System – Contractor shall inspect all fuel lines and hoses for visual leaks and general condition; inspect day tank and float assembly for proper operation and leaks; and inspect fuel pump for leaks. Contractor shall verify proper operation of governor, and governor linkage; and check level of fuel in primary supply tank. Contractor shall drain water and sediment from fuel filter and fuel supply tanks.

• Coolant System – Contractor shall inspect all clamps, verify condition of all hoses and identify any visual leaks. Contractor shall test the engine jacket water heater to verify proper and safe operation. The contractor shall also test coolant freeze point and verify coolant level; test coolant additive package (DCA) for proper corrosion inhibitors. Contractor shall inspect belt condition and tension, correct as required; engine belts shall be replaced as necessitated by inspection results. Contractor shall inspect radiator pressure cap, inspect radiator core for visual blockage, damage or obstructions; and inspect for proper operation of intake louvers, motorized or gravity. Contractor shall verify proper operation of remote radiator and belt condition.

• Controls – Contractor shall verify and record output voltage and adjust voltage regulator, if necessary;

calibrate control meters; and verify and record output frequency and adjust governor, if necessary.

Contractor shall verify operation of all lamps on control panel; and inspect for any loose connections, terminals or discoloration. Engine Start/Stop/Emergency Shutdown controls shall be tested to verify correct operation.

• Generator – Contractor shall inspect and lubricate generator end bell bearing. Inspect brushes, brush holders and commutator; inspect cooling screen and general condition of alternator. Contractor shall inspect for abnormal vibration. Contractor shall verify connections and insulation condition; and verify proper operation of shunt trip on mainline circuit breaker.

5.3. Task 2 - LOAD BANK TESTING FOR EMERGENCY GENERATORS (CLINs-0002, 1002, 2002, 3002 and 4002):

A. Contractor shall annually perform 4 hour Load Bank testing on all emergency generators listed in Appendix A.

Testing shall be performed solely utilizing supplemental loads under the following conditions:

• NOT LESS THAN 30 percent of the generator nameplate kW rating for NOT LESS THAN 60 continuous minutes.

• NOT LESS THAN 50 percent of the generator nameplate kW rating for NOT LESS THAN 120 continuous minutes.

• NOT LESS THAN 75 percent of the generator nameplate kW rating for NOT LESS THAN 60 continuous minutes.

• Total load test duration shall exceed four (4) continuous hours plus documented fifteen (15) minute warm up and cool down periods.

B. During testing the following measurements shall be recorded at intervals not exceeding thirty (30) minutes and documented in every test report:

• Time of day

• Generator Run Hours

• KW

• Load percentage

• Frequency

• Phase to phase AC voltage (measured across all phases)

• DC Voltage

• AC Amps (all phases)

• Oil Pressure

• Engine Temperature

• Engine revolutions per minute

C. Individual test reports shall be submitted for each emergency generator and shall document the following:

• Date and time of testing

• Total duration of testing time

• Testing location

• Name, physical address, email, and phone number of company conducting testing

• Name of technician conducting the test

• Generator Common Name

• Generator Manufacturer

• Generator Model number

• Generator Serial number

• Generator Nameplate KW

• Generator Nameplate Voltage

• Generator Nameplate Current

• Generator Current at Unity Power Factor (3 Phase)

• Generator Hour Meter Start/Stop times

• Ambient Air Temperature

• Technician Comments

5.4. Task 3 – UNDERGROUND FUEL STORAGE TANK TESTING AND MAINTENANCE (CLINs-0003, 1003, 2003, 3003 and

4003):

A. The contractor shall perform annual conditioning and polishing of stored fuel in all underground storage tanks (USTs) listed in Appendix B. This process shall include the removal of contaminants such as water, sediment, gums, microbes, and oxidized fuel to ensure the maintenance of fuel purity. Satisfactory completion of fuel conditioning and polishing (Requirement A) shall not be considered accomplished until after fuel quality analysis (Requirement B) has been performed on post-conditioning samples and the results confirm that all tested parameters meet acceptable standards for generator fuel purity as defined in Appendix C.

B. Annual fuel quality analysis shall be conducted for all underground storage tanks listed in Appendix B. Testing shall be performed for all properties listed in Appendix C and in accordance with ASTM methods and procedures. Fuel test samples shall be drawn only after completion of fuel conditioning and polishing. Fuel conditioning and polishing actions must be repeated if analysis results do not meet the standards specified in Appendix C, until satisfactory purity is achieved.

C. Biocides and or stabilizers shall be added to each fuel storage tank as indicated or recommended by the results of fuel quality analysis testing.

5.5. Task 4 – GENERATOR FUEL STORAGE DAY TANK MAINTENANCE (CLINs-0004, 1004, 2004, 3004 and 4004):

A. Contractor shall perform day tank maintenance and testing to include the following:

• Float Switch and Level Sensor Testing – Inspect, test, and verify operation of all float switches (high/low level, overfill alarms, pump start/stop control) and all electronic or mechanical level sensors for correct function, calibration, alarm annunciation, and local/remote signaling.

• Fuel Transfer Pump Testing - Inspect and test operation of day tank fill/transfer pumps under simulated or actual fill conditions. Verify correct pump start and stop by float control or PLC/system. Inspect pump for abnormal noise, vibration, leaks, or overheating.

• Control and Safety Device Verification - Test day tank control circuits, alarms, automatic shutdowns, and emergency stop features (including integration with generator controls where applicable). Simulate alarm and fail conditions to ensure reporting systems activate.

• Day Tank Components Inspection – Verify proper operation of each day tank and test the following items:

solenoid valves, strainers, hoses and fittings, fill pumps, and control devices.

5.6. Task 5 - MAJOR COOLING SYSTEM SERVICE FOR TWO (2) EMERGENCY GENERATORS (CLINs-0005):

A. Contractor shall perform major cooling system service for the following two (2) emergency generators during base year (2026).

• Building 1 – Kohler 1,500 KW Generator #1

• Building 1 – Kohler 1,500 KW Generator #2

Full service shall include:

• System drain, flush and fill with new extended life coolant.

• Replacement of all cooling system hoses, clamps, block heater hoses, belts, and miscellaneous parts.

5.7. Task 6 – FULL BATTERY REPLACEMENTS FOR EMERGENCY…