Attachment 3 - Product Version Configurations.pdf
PDF 13 MB Posted
- Attached to
- Streetlight Replacement Project
- Solicitation number
- 61899
- Issued by
- Fairfax County, Falls Church City, Virginia
About this file
This document is an attachment related to a streetlight replacement project in the City of Fairfax, Virginia. The City of Fairfax, located in Fairfax County, has a multi-year project to replace the existing gas-powered streetlights with new LED streetlights. The second phase of the project will replace 45 streetlights on North Street, Chain Bridge Road, University Drive, Blenhiem Boulevard, Main Street, and East Street. The City will not guarantee any specific amount of business to the awarded contractor after the initial phase.
The document does not provide pricing terms, set-asides, information on incumbents, funding requirements, or other salient details. The focus is on the project overview, locations, and quantities for the second phase of the streetlight replacement initiative in the City of Fairfax.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Bid Submission Form.docx | DOCX document | |
| Attachment 2 - Price Document 3.18.24.xlsx | XLSX spreadsheet | |
| IFB 61899 - Streetlight Replacement Project.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF FAIRFAX - North St Phase
PLAN FOR BID SOLICITATION
1of 5
NTS
12/12/23
R&A R&A
(Not For Construction)
NOTIFY "MISS UTILITY" AT 1-800-552-7001
72 HOURS IN ADVANCE OF ANY
CONSTRUCTION IN THESE LOCATIONS
15865 Crabbs Branch Way Rockville, MD 20855
PROJECT MANAGEMENT
UTILITY ENGINEERING &
(301) 548-7475 (Office)
(301) 548-7478 (Fax)
Gas Lamp-to-LED Streetlight Conversions
Poles and Conduit Alignment and Design
HISTORIC DISTRICT STREETLIGHT LAMP/POLE CONFIGURATIONS
CONCRETE FOUNDATIONS - "VERSION A" & "VERSION B"
City of Fairfax - Gas Lamp Conversions
North St / Phase 2 - Streetlight Configurations
Streetlight
Version
Label
A
B
C
PTUE3
Historic
LED Lamp
X
X
X
12-foot pole concrete base
X
X
X
12-foot pole
Direct-Bury
Banner
Accessories
X
X
X
CF-19
19-in diameter
12-foot pole concrete base
CF-16
16-in diameter
DB
WFCL3
Cutoff Acorn
LED Lamp
ARDCL
Cutoff Colnl
LED Lamp
D
E
X
X
X X
X
LED STREETLIGHT INFRASTRUCTURE LEGEND
NEW: 1way, 2-inch PVC for new streetlight connections (Phase 2)
NEW: 12' x 12' Electric Splice Box (Phase 2)
NEW: Electric circuit feed path (Phase 2)
EXISTING: 1way, 2-inch PVC for streetlight connections (Phase 1)
EXISTING: Electric circuit feed path (Phase 1)
Transition Residential
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text No.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
DESIGNED
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
CITY
AutoCAD SHX Text
STLT
NTS12/12/23
R&A R&A
(Not For Construction)
NOTIFY "MISS UTILITY" AT 1-800-552-7001
72 HOURS IN ADVANCE OF ANY
CONSTRUCTION IN THESE LOCATIONS
15865 Crabbs Branch Way Rockville, MD 20855
PROJECT MANAGEMENT
UTILITY ENGINEERING &
(301) 548-7475 (Office)
(301) 548-7478 (Fax)
Gas Lamp-to-LED Streetlight Conversions
Poles and Conduit Alignment and Design
HISTORIC DISTRICT STREETLIGHT LAMP/POLE CONFIGURATIONS
DIRECT BURY FOUNDATIONS - "VERSION C"
City of Fairfax - Gas Lamp Conversions
North St / Phase 2 - Streetlight Configurations
Streetlight
Version
Label
A
B
C
PTUE3
Historic
LED Lamp
X
X
X
12-foot pole concrete base
X
X
X
12-foot pole
Direct-Bury
Banner
Accessories
X
X
X
CF-19
19-in diameter
12-foot pole concrete base
CF-16
16-in diameter
DB
WFCL3
Cutoff Acorn
LED Lamp
ARDCL
Cutoff Colnl
LED Lamp
D
E
X
X
X X
X
LED STREETLIGHT INFRASTRUCTURE LEGEND
NEW: 1way, 2-inch PVC for new streetlight connections (Phase 2)
NEW: 12' x 12' Electric Splice Box (Phase 2)
NEW: Electric circuit feed path (Phase 2)
EXISTING: 1way, 2-inch PVC for streetlight connections (Phase 1)
EXISTING: Electric circuit feed path (Phase 1)
Transition Residential
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text No.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
DESIGNED
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
CITY
NTS
12/12/23
R&A R&A
(Not For Construction)
NOTIFY "MISS UTILITY" AT 1-800-552-7001
72 HOURS IN ADVANCE OF ANY
CONSTRUCTION IN THESE LOCATIONS
15865 Crabbs Branch Way Rockville, MD 20855
PROJECT MANAGEMENT
UTILITY ENGINEERING &
(301) 548-7475 (Office)
(301) 548-7478 (Fax)
Gas Lamp-to-LED Streetlight Conversions
Poles and Conduit Alignment and Design
PRIMARY ROAD CUTOFF ACORN STREETLIGHT LAMP/POLE CONFIGURATION
CONCRETE FOUNDATION - "VERSION D"
City of Fairfax - Gas Lamp Conversions
North St / Phase 2 - Streetlight Configurations
Streetlight
Version
Label
A
B
C
PTUE3
Historic
LED Lamp
X
X
X
12-foot pole concrete base
X
X
X
12-foot pole
Direct-Bury
Banner
Accessories
X
X
X
CF-19
19-in diameter
12-foot pole concrete base
CF-16
16-in diameter
DB
WFCL3
Cutoff Acorn
LED Lamp
ARDCL
Cutoff Colnl
LED Lamp
D
E
X
X
X X
X
LED STREETLIGHT INFRASTRUCTURE LEGEND
NEW: 1way, 2-inch PVC for new streetlight connections (Phase 2)
NEW: 12' x 12' Electric Splice Box (Phase 2)
NEW: Electric circuit feed path (Phase 2)
EXISTING: 1way, 2-inch PVC for streetlight connections (Phase 1)
EXISTING: Electric circuit feed path (Phase 1)
Transition Residential
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text No.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
DESIGNED
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
CITY
NTS12/12/23
R&A R&A
(Not For Construction)
NOTIFY "MISS UTILITY" AT 1-800-552-7001
72 HOURS IN ADVANCE OF ANY
CONSTRUCTION IN THESE LOCATIONS
15865 Crabbs Branch Way Rockville, MD 20855
PROJECT MANAGEMENT
UTILITY ENGINEERING &
(301) 548-7475 (Office)
(301) 548-7478 (Fax)
Gas Lamp-to-LED Streetlight Conversions
Poles and Conduit Alignment and Design
RESIDENTIAL CUTOFF COLONIAL STREETLIGHT LAMP/POLE CONFIGURATION
DIRECT BURY FOUNDATION - "VERSION E"
City of Fairfax - Gas Lamp Conversions
North St / Phase 2 - Streetlight Configurations
Streetlight
Version
Label
A
B
C
PTUE3
Historic
LED Lamp
X
X
X
12-foot pole concrete base
X
X
X
12-foot pole
Direct-Bury
Banner
Accessories
X
X
X
CF-19
19-in diameter
12-foot pole concrete base
CF-16
16-in diameter
DB
WFCL3
Cutoff Acorn
LED Lamp
ARDCL
Cutoff Colnl
LED Lamp
D
E
X
X
X X
X
LED STREETLIGHT INFRASTRUCTURE LEGEND
NEW: 1way, 2-inch PVC for new streetlight connections (Phase 2)
NEW: 12' x 12' Electric Splice Box (Phase 2)
NEW: Electric circuit feed path (Phase 2)
EXISTING: 1way, 2-inch PVC for streetlight connections (Phase 1)
EXISTING: Electric circuit feed path (Phase 1)
Transition Residential
AutoCAD SHX Text
REVISIONS
AutoCAD SHX Text No.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
DESIGNED
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
DATE
AutoCAD SHX Text
SCALE
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
CITY
| Sheets and Views |
| GAS-LED North - S1 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S2.pdf |
| Sheets and Views |
| GAS-LED North - S2 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S3.pdf |
| Sheets and Views |
| GAS-LED North - S3 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S4.pdf |
| Sheets and Views |
| GAS-LED North - S4 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S5.pdf |
| Sheets and Views |
| GAS-LED North - S5 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S6.pdf |
| Sheets and Views |
| GAS-LED North - S6 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S7.pdf |
| Sheets and Views |
| North - Hist CF Specs - S7 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S8.pdf |
| Sheets and Views |
| North Hist - DB Specs - S8 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S9.pdf |
| Sheets and Views |
| Cutoff Acorn CF Specs - S9 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S10.pdf |
| Sheets and Views |
| Cutoff Colonial DB Specs-S10 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S11 foundation.pdf |
| Sheets and Views |
| GAS-LED North - S1 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S2.pdf |
| Sheets and Views |
| GAS-LED North - S2 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S3.pdf |
| Sheets and Views |
| GAS-LED North - S3 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S4.pdf |
| Sheets and Views |
| GAS-LED North - S4 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S5.pdf |
| Sheets and Views |
| GAS-LED North - S5 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S6.pdf |
| Sheets and Views |
| GAS-LED North - S6 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S7.pdf |
| Sheets and Views |
| North - Hist CF Specs - S7 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S8.pdf |
| Sheets and Views |
| North Hist - DB Specs - S8 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S9.pdf |
| Sheets and Views |
| Cutoff Acorn CF Specs - S9 |
| COF - Gas Lamp-LED Plan - 2023 10 12 North St Phase - PRELIM REVIEW - S10.pdf |
| Sheets and Views |
| Cutoff Colonial DB Specs-S10 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S6.pdf |
| Sheets and Views |
| GAS-LED North - S6 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S4.pdf |
| Sheets and Views |
| GAS-LED North - S4 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S1 A.pdf |
| Sheets and Views |
| GAS-LED North - S1 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S2 A.pdf |
| Sheets and Views |
| GAS-LED North - S2 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S3 A.pdf |
| Sheets and Views |
| GAS-LED North - S3 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S4 A.pdf |
| Sheets and Views |
| GAS-LED North - S4 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S5 A.pdf |
| Sheets and Views |
| GAS-LED North - S5 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S6 A.pdf |
| Sheets and Views |
| GAS-LED North - S6 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S9 A.pdf |
| Sheets and Views |
| Cutoff Acorn CF Specs - S9 |
| COF - Gas Lamp-LED Plan - 2023 12 12 North St Phase 2 - ISSUE FOR IFB - S10 A.pdf |
| Sheets and Views |
| Cutoff Colonial DB Specs-S10 |
File details come from the government source that posted it. Updated .