This document contains specifications for a federal construction contract solicitation to replace a culvert on a forest service road. The contractor will demolish an existing 4-sided concrete box culvert, regrade road approaches, and install a new 20-foot span, 7-foot rise precast concrete box culvert. The work also includes erosion control, backfilling, seeding, and traffic control. The solicitation is issued by the US Department of Agriculture Forest Service for a project located on the Medora Ranger District in North Dakota. The specifications provide requirements for materials, construction methods, submittals, and measurement and payment for various line items.

View the file

Other files for this federal contract opportunity

Other files attached to Horse Creek Culvert Replacement, newest first.
File Type Posted
1282B123R0001_Amendment 0002_S.pdf PDF
Attachment 1_SOW Horse Creek Culvert Replacement_v2.pdf PDF
1282B123R0001_Amendment 0001_S.pdf PDF
Attachment 5_Wage Determination.pdf PDF
Attachment 2_Section B Schedule.pdf PDF
1282B123R0001_Final.pdf PDF
Attachment 6_PPQ.pdf PDF
Attachment 4_ Drawings_Horse Creek.pdf PDF
Attachment 1_SOW Horse Creek Culvert Replacement.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents Preface

101 - Terms¸ Format¸ and Definitions

102 - Bid¸ Award¸ and Execution of Contract

103 - Scope of Work

104 - Control of Work

105 - Control of Material

106 - Acceptance of Work

107 - Legal Relations and Responsibility to the Public

108 - Prosecution and Progress

109 - Measurement and Payment

153 – Contractor Quality Control

155 – Schedules for Construction Contracts

156 - Public Traffic

157 - Soil Erosion and Sediment Control

203 - Removal of Structures and Obstructions

204 - Excavation and Embankment

208 - Structure Excavation and Backfill for Selected Major Structures

251 - Riprap

302 - Minor Crushed Aggregate

553A – Precast Concrete Structures

625 - Turf Establishment

725 - Miscellaneous Material

Preface Preface_wo_07_11_2017

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest

System Roads.

101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016

Add the following paragraph to Subsection 101.01:

101.01 Meaning of Terms.

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_National_11_9_2016

Add the following to Subsection 101.03:

101.03 Abbreviations.

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations

AFPA — American Forest and Paper Association

FSAR — Forest Service Acquisition Regulations

MSHA — Mine Safety and Health Administration

NESC — National Electrical Safety Code

WCLIB — West Coast Lumber Inspection Bureau

(f) Miscellaneous unit abbreviations.

MP — milepost location ppm — parts per million volume

STA station location

101.04_National_11_9_2016

Make the following changes to Subsection 101.04:

101.04 Definitions.

Delete the definitions and replace with the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line

(including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2)

Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of

Agriculture.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road

Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.

Utilization Standards — The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016

Delete Section 102 in its entirety.

Delete Section 102. Refer to Solicitation for RFP requirement

103 - Scope of Work 103.00_National_11_9_2016

Delete Section 103.04 and 103.05

104 - Control of Work 104.00_National_11_9_2016

Delete Subsections 104.02, and 104.04.

104.06_National_11_9_2016

Add the following to Subsection 104.06:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road

Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.02_National_11_1_2016

Add the following to Subsection 105.02c:

105.02(c) Contractor-located sources.

All material (e.g., soil, gravel, sand, borrow, aggregate, etc.) transported onto National Forest System land or incorporated into the work shall be weed-free. The Contracting Officer may request written documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor. Contractor-provided expertise and methods to establish weed-free status must be appropriate for the weeds of concern in the local area. The following applies to this contract:

A Forest Service weed specialist will inspect proposed sources to determine weed-free status. Provide the Contracting Officer written notification of proposed material sources 14 days prior to use. Written approval of the specific source will be provided to the contractor by the CO. If weed species are present in the proposed source, appropriate mitigation measures may allow conditional use of the source as required by the Contracting Officer.

106 - Acceptance of Work 106.01_National_11_9_2016

Delete Subsection 106.01 and replace with the following:

106.01 Conformity with Contract Requirements.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project.

When the Government tests work, copies of test reports are furnished to the Contractor upon request.

Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive.

The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work;

providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

1. Sampling method;

2. Number of samples;

3. Sample transport;

4. Test procedures;

5. Testing laboratories;

6. Reporting;

7. Estimated time and costs; and

8. Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the

Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

1. Have the work accepted at a reduced price; or

2. Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.02_National_11_9_2016

Delete Subsection 106.02 and replace with the following:

106.02 Visual Inspection.

Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.

107 - Legal Relations and Responsibility to the Public

107.05_National_11_9_2016

Delete Subsection 107.05 Responsibility for Damage Claims.

108 - Prosecution and Progress 108.00_National_11_9_2016

Delete Section 108 in its entirety.

Delete Section 108.

109 - Measurement and Payment

Add the following sentence to Subsection 109.02(b):

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

109.10_Project_8_15_2018

Add the following Subsection 109.10:

109.10 Methods of Measurement.

One of the following methods of measurement for determining final payment is DESIGNATED IN THE

SCHEDULE OF ITEMS for each PAY ITEM:

(a) Actual Quantities (AQ). These quantities are determined from measurements of completed work.

(b) Contract Quantities (CQ). As defined in 109.02 (b) and supplemented above.

(c) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

153 – Contractor Quality Control 153.07_Project_8_3_2018

Add the following.

153.07. Project Submittals

At a minimum the contractor shall provide project submittals as shown on the Submittal Log below. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Drawings.

Submittal Log

Log

No.

Incidental to Pay

Item(s) Description of Submittal

Type of

Submittal

Requirement found in

Specification No.

/Drawings

Additional

Specification

References

1 151 Submittal Schedule Schedule

2 151 Weed Free Material Source

Certification

Material

Certification FSSS 105.02(b)

3 151 Hazardous Spill Plan Plan FSSS 107.10

4 151 Contractor Quality Control Plan Plan 153.02 552.09

5 151 Material Storage/Staging Plan Plan and

Description FSSS 151 Drawings

6 151 Bridge Removal Plan Plan and

Description Drawings

7 152 Surveyor Credentials Certification FSSS 152

8 157 Soil Erosion and Pollution Control

Plan Plan FSSS 157.03

9 157 Stream Diversion & Dewatering Plan Plan Drawings

FSSS 157.03

157.09

10 208 Excavation and Backfill Plan &

Methods Plan Drawings

11 208 Structural Backfill Proctor Test Results 208.11 Drawings, FSSS

12 208 Structural Backfill Density Testing Test Results 208.11

13 208 Foundation Fill Proctor Test Results 208.11 Drawings, FSSS

14 208 Foundation Fill Density Testing Test Results 208.11

15 251 Type II Geotextile Material

Certification 714.01

Submittal Log

Log

No.

Incidental to Pay

Item(s) Description of Submittal

Type of

Submittal

Requirement found in

Specification No.

/Drawings

Additional

Specification

References

16 251 Riprap Material

Certification 705.02

17 302 Aggregate Surface Course Material

Certification

FSSS 302

18 553A Precast Concrete Structures:

Concrete Box, Wingwalls/Footings Shop Drawing FSSS 553A.03 104, 552, 553, 19 553A Precast Concrete: PCI/NPCA

Certification

Fabrication

Certification

FSSS 553.02

20 553A Precast Concrete Structures: Testing Test Results FSSS 553A.06 106, 554, 562

21 553A Reinforcing Steel Order List 554.03 553, 553A, 709, Drawings

22 553A Miscellaneous Material: Grout Material Certification

FSSS 725.40 Drawings

23 553A Miscellaneous Material: Grout Product Approval FSSS 725.40 Drawings

24 553A Installation Plan Plan Drawings

25 625 Seed Mix Material

Certification

625.10 106, FSSS 625,

26 633 Object Markers & Posts Material

Certification 633 Drawings

27 635 Traffic Control Plan Plan FSSS 156, 635

155 – Schedules for Construction Contracts Refer to FHWA FP-14 Standard Specifications for construction of roads and bridges on federal highway projects

156 - Public Traffic 156.00_Project_8_31_2018

Delete Section 156 in its entirety and replace with the following:

Section 156. – Public Traffic Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Temporary Traffic Control 635

Construction Requirements

156.03 General. The Contractor will be allowed to close Road No. 779-1 at the culvert site, to through traffic. Road No. 779 must be kept open to through traffic until traffic can be routed over the new culvert. The Contractor will be responsible for providing, installing, maintaining, and removing of the road closure and detour signs during the construction period. The Contractor shall be responsible for providing, installing, maintaining, and removal of type 3 barricades at the project site for the road closure period.

The Contractor shall submit a traffic control plan to the C.O. 14 days prior to road closure.

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM

7100-15. All required signs will be in place and approved prior to beginning work on project.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the

National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Payment for this item shall be incidental to

Mobilization.

157 - Soil Erosion and Sediment Control 157.04_Project_8_15_2018

Delete the second and third paragraph in Subsection 157.04 and replace with the following:

157.04 General.

Submit a Dewatering and Soil Erosion and Pollution Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction in accordance with the plans. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the CO for approval.

Reflect in the Dewatering and Soil Erosion and Pollution Control Plan special concerns and measures necessary to protect resources and government improvements. Include:

(a) The construction activities and sequence of implementation relating to specific erosion control measures.

(b) The location and type of temporary controls to be implemented during construction.

The following pollution prevention measures are a requirement for endangered species protection:

i. All equipment will be inspected for leaks prior to commencing work each day and any identified problems corrected before equipment is allowed to operate.

ii. Fueling, maintenance and staging of equipment will occur in designated areas away from water bodies

iii. A spill containment kit will be available onsite at all times during construction, and proper notification procures will be in place in the event of a hazardous release.

iv. Absorbent pads will be placed beneath fuel tanks during fueling and maintenance. Pads will also be placed under any pumps while operating.

(c) For work in stream channels with running water a detailed dewatering plan is required.

The following dewatering, fish salvage, and turbidity control measures are a requirement for endangered species protection:

i. All instream work must be completed during the designated instream fisheries work window.

ii. The CO shall be notified at least 48 hours in advance of commencing dewatering and re-watering activities.

iii. Flows will be completely diverted around the in-stream work site through a combination of pumping, piping, openchannel, and/or pre-approved, alternative methods and returned to the channel below the project area. Pump screen openings shall not exceed 3/32 or 0.0938 inches (2.38 mm). If the diversion inlet is not screened, the diversion outlet will be placed in a location that facilitates safe reentry of fish into the stream channel.

iv. Flow diversion structures will be constructed with sand bags covered with plastic sheeting. Cofferdams, portable bladder dams, or other technologies constructed of non-erodible material may also be used to contain stream flow.

(d) Description of the monitoring plan.

When erosion control measures are not functioning as intended, take corrective action to eliminate or minimize pollutants in storm water discharges from the project.

Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property and reclaim all disturbed areas.

203 - Removal of Structures and Obstructions 203.04_National_11_2_2016

Make the following changes to Section 203. Removal of Structures and Obstructions -

Subsection 203.04(b):

203.04 (b) General.

Delete the fifth paragraph of Subsection 203.04(b) and replace with the following:

Remove structures and obstructions in the roadbed to 12 inches (300 millimeters) below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches (300 millimeters) below finished ground or to the natural stream bottom.

Delete the seventh paragraph of Subsection 203.04(b) and replace with the following:

When abandoning an existing culvert pipe, remove the upstream and downstream portion of the culvert to within 12 inches (300 millimeters) of the subgrade or embankment slope. Ensure the abandoned pipe is at least 48 inches (1200 millimeters) from a new culvert or structure. Seal the abandoned culvert ends with a tight-fitting plug of concrete at least 6 inches (150 millimeters) thick. Ensure the structure does not entrap water.

203.05_Project_8_15_2018

Update the following in Subsection 203.05:

203.05 Disposing of Material.

(a) Remove from project. All materials designated for removal become property of the Contractor and are to be disposed of by removing off of National Forest Lands in accordance with all local, state, and federal requirements.

(b) Burn. Delete this section.

(c) Bury. Delete this section.

(e) Scatter. Slash material from clearing and grubbing shall be scattered on roadway embankment slopes and disturbed areas per the direction of the C.O.

204 - Excavation and Embankment 204.00_Project_8_15_2018

Delete Subsection 204.11 and replace with the following:

Section 204.11 Compaction.

204.11 Compaction. Compact the embankment using one of the following methods as specified.

(a) Placement Method 1. Use AASHTO T 27 to determine the quantity of material retained on a No. 4

(4.75-millimeter) sieve. Compact as follows:

(1) More than 80 percent retained on a No. 4 (4.75-millimeter) sieve. Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second. Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation:

(a) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds (180 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute;

(b) Eight roller passes of a 20-ton (20-metric ton) compression-type roller; or

(c) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration and a minimum frequency of 1000 vibrations per minute.

Increase the compactive effort for layers deeper than 12 inches (300 millimeters) as follows:

• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 204.11(a)(1)(a), by four passes; or

• For each additional 6 inches (150 millimeters) or fraction thereof, increase the number of roller passes in Subsection 204.11(a)(1)(b) and (c), by eight passes.

(2) 50 to 80 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145. Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content. Use AASHTO T 99 to determine the optimum moisture content of the portion of the material passing a No. 4 (4.75-millimeter) sieve.

Multiply this number by the percentage of material passing a No. 4 (4.75-millimeter) sieve, and add 2 percent to determine the optimum moisture content of the material.

Use nonvibratory rollers at speeds less than 6 feet (1.8 meters) per second and vibratory rollers at speeds less than 3 feet(1 meter) per second. Compact each layer of material full width according to Subsection 204.11(a)(1).

(3) Less than 50 percent retained on a No. 4 (4.75-millimeter) sieve. Classify the material according to AASHTO M 145. For material classified A-1 or A-2-4, determine the maximum density according to AASHTO T 99, Method C.

Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.

Use compression-type or vibratory rollers. Compact each layer of material full width to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures. When required, use AASHTO T 224 to correct for coarse particles.

(b) Placement Method 2. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical.

Operate roller compaction equipment over the full width of each layer until there is no visible evidence of further consolidation or, if when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes. Use compression-type rollers at speeds less than 6 feet

(1.8 meters) per second and vibratory rollers at speeds less than 3 feet (1 meter) per second.

Ensure rollers meet the following requirements:

(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch (4.5 kilogram/millimeter) of width of the compression roll or rolls.

(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum dynamic force of 30,000 pounds (130 kilonewtons) impact per vibration, specifically designed to compact the material on which it is used.

(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi (550 Kilopascals).

(4) Sheepsfoot, tamping, or grid rollers capable of exerting a force of 250 pounds per inch (4.5 kilogram/millimeter) of width of roller drum.

(c) Placement Method 3. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical.

Operate hauling and spreading equipment uniformly over the full width of each layer until there is no visible evidence of further consolidation. Make at least three complete passes.

(d) Placement Method 4. Adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical.

Operate hauling and spreading equipment uniformly over the full width of each layer.

(e) Placement Method 5. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact the complete surface with a bucket of an excavator larger than 39,000 pounds (18 metric ton) Gross Vehicle Weight using a minimum of three blows. Overlap compaction by ½ width of bucket.

(f) Placement Method 6. Adjust the moisture content of the material to a moisture content suitable for compaction. Compact using an approved mechanical tamper for a minimum of three complete passes.

When compacting with rollers or hauling and spreading equipment is not practical, use approved mechanical tampers for a minimum of three complete passes.

208 - Structure Excavation and Backfill for Selected Major

Structures

208.03_Project_8_15_2018

Add the following to Subsection 208.03:

208.03 General.

Submit four sets of the excavation plan to the CO for approval a minimum of 21 days before the start of construction:

Use all suitable material from structure excavation for road embankment and native channel material.

Field drain and dry excessively wet material that is otherwise suitable for embankment before placement. Place and shape unsuitable or excess material in the designated sites or as directed by the

CO.

208.07_National_11_8_2016

Add the following to Subsection 208.07:

208.07 Dewatering.

Construct diversions according to Subsection 157.10 Diversions. Submit dewatering plans according to

Subsection 104.03.

208.12_Project_8_15_2018

Delete Subsection 208.12 and add the following:

208.12 Measurement.

Measure the Section 208 items listed in the bid schedule according to Subsection 109.02 and the following:

Measure structural excavation by the cubic yard to the neat lines shown on the plans or the contractor’s approved excavation plan. Do not include the following volumes in structure excavation:

(a) Material excavated outside of the neat lines shown in the plans or approved in the contractors excavation plan;

(b) Any material included within the staked limits of the excavation, such as continuous channel changes and ditches, for which measurement is covered under other sections;

(c) Water or other liquid material;

(d) Material excavated before measurements of the original ground; or

(e) Material rehandled, except when the contract specifically requires excavation after embankment placement.

Measure foundation fill and structural backfill by the cubic yard in place for the volume placed to the neat lines and grades shown on the plans or the contractor’s approved excavation plan.

251 - Riprap 251.07_Project_8_15_2018

Delete the last sentence of Subsection 251.07 and add the following:

251.07 Acceptance

Structure excavation and backfill will be evaluated under Section 208.

302 - Minor Crushed Aggregate 302.04_Project_8_31_2018

Delete Subsection 302.02 and replace with the following:

302.02 Material

Conform to the following Subsections:

Water…………………………………………………………………..……725.01(c)

NDDOT Modified Class 5 Specification

Sieve Size Percent Passing

1” 100

¾” 90-100

No. 4 35-70

No. 200 10-17

Contractor may also supply material meeting the requirements of NDDOT Class 13 or Section 703.06- Crushed Aggregate.

Aggregate must be certified erionite free and certification must be submitted to C.O. 14 days prior to placement for approval.

302.04_National_7_10_2017

Add the following to Subsection 302.04

302.04 Placing Crushed Aggregate

Written approval of the surfacing is required before placing aggregate.

553A – Precast Concrete Structures 553.00_Project_8_15_2018

Add Section 553A:

Section 553A. — Precast Concrete Structures Description

553A.01 Work. Construct precast concrete members. In addition, manufacture, test materials for, transport, store, and install all precast concrete portions except piling, and perform all necessary grouting, welding, or other connections. Furnish precast concrete members complete and in place, including all concrete reinforcing steel and incidentals connected therewith.

Materials

553A.02 Requirements. Provide materials that meet the requirements specified in the following subsections:

High-Strength Nonshrink Grout ………………………………. 725.40

Mortar ……………………………………………………………………. 725.41

Reinforcing Steel …………………………………………………….. 709.01

Sealants, Fillers, and Seals …………………………………….... 712.01

Structural Concrete …………………………………………………. 552

Structural Steel ……………………………………………………….. 717.01

Provide precast concrete members of the size, shape, strength, air content, and finish that are SHOWN

ON THE DRAWINGS. Precast concrete members must be manufactured by a plant with one of the following certifications:

• Precast / Prestressed Concrete Institute (PCI) o Bridge 1, Precast Bridge Products (no prestressed reinforcing).

o Commercial 1, Precast Concrete Products (no prestressed reinforcing).

• National Precast Concrete Association (NPCA) o Precast

• American Concrete Pipe Association (ACPA) o QCast

Submit a copy of the transmittal letter of the latest PCI, NPCA or ACPA inspection/certification with the shop drawings.

In lieu of the industry certifications shown above, Contractor shall retain a professional engineer to provide quality assurance for the work by inspecting and certifying in writing the concrete members are constructed in accordance to the specification and shall include but not limited to:

a) Shop drawing review.

b) Concrete member dimensions.

c) Concrete mix design.

d) Aggregate sources and test results.

e) Steel reinforcing placement.

f) Concrete curing and strength test results.

g) Concrete material certifications.

h) Placement mixing, delivery and sampling.

Certification of the above shall be received by the CO prior to shipment and installation at the job site.

Perform all sampling, testing, and inspection necessary to ensure quality control of the component materials and the concrete. Sample and test for quality control and acceptance testing in accordance with the AASHTO or ASTM test methods prescribed in Section 552.

Maintain adequate records of all inspections and tests. Keep records that indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and the nature of any corrective action taken.

Construction

553A.03 Performance. Construct precast concrete structural members in accordance with the following sections and subsections, as applicable:

Reinforcing Steel ………………………………………………

Storing, Transporting, & Erecting ………………………... 553.09

Structural Concrete ……………………………………………… 552

Submit four sets of shop drawings to the CO for approval, including the concrete mix design for each class of concrete proposed for use, a minimum of 21 days before fabrication of the precast member(s).

553A.05 Handling, Transporting, & Erecting. Provide additional reinforcement, as needed, to meet the requirements of handling, transporting, and erecting precast members.

553A.06 Acceptance. Reinforcing steel, anchor devices, elastomeric bearings, and material for concrete and grout will be evaluated under Subsection 106.03. Furnish production certifications for hydraulic cement and reinforcing steel.

Concrete for precast concrete members will be evaluated under Subsections 106.02, 106.03, and 106.04.

Construction of precast concrete members will be evaluated under Subsections 106.02 and 106.04.

Reinforcing steel will be evaluated under Section 554.

Falsework and forms will be evaluated under Section 562.

Measurement

553A.07 Measure the Section 553A items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Do not measure reinforcing steel, concrete, anchorages, plates, nuts, and other material contained within or attached to the unit for precast concrete structural members.

Payment

553A.08 The accepted quantities will be paid at the contract price per unit of measurement for the

Section 553A pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

625 - Turf Establishment 625.00_Project_8_15_2018

Delete Section 625 in its entirety and replace with the following:

Section 625. — Turf Establishment Description

625.01 This work consists of soil preparation, watering, fertilizing, seeding, and mulching. Seeding and mulching methods are designated as dry or hydraulic.

Material

625.02 Conform to the following Subsections:

Seed 713.04

Construction Requirements

625.03 General. Apply turf establishment to prepared ground or any disturbed area.

Seeded areas damaged by construction activities shall be reseeded within 10 days of the damage. Do not seed during windy weather or when the ground is excessively wet, frozen, or snow covered.

Assure that all seed and mulch used in the work conforms to the weed free requirements of Section 713.

625.04 Preparing Seedbed. Ensure that the surface soil is in a roughened condition favorable for germination and growth.

625.05 Seeding. Apply seed by the following methods:

(a) Dry Method. Apply the seed with approved power driven seeders, drills, or other mechanical equipment. Hand-operated seeding methods are satisfactory on areas inaccessible to mechanical equipment.

Furnish and apply the following kinds and amounts of pure live seed:

Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.

625.06 Acceptance. Material for turf establishment will be evaluated under Subsections 106.02 and

106.03.

Placing of turf establishment will be evaluated under Subsections 106.02 and 106.04.

Measurement

625.07 Measure the Section 625 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:

When measuring turf establishment and supplemental applications by the acre (hectare), measure on the ground surface.

When measuring water by volume or mass, measure in the hauling vehicle or by metering.

Payment

625.08 The accepted quantities will be paid for at the contract price per unit of measurement for the

Section 157 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Species Preferred

Cultivar, Ecotype, or Germplasm

Common Name % of Mix

Cool Season Grasses:

Elymus canadensis Nassella viridula Pascopyrum smithii

Mandan Lodorm Rodan

Canada wildrye Green needlegrass Western wheatgrass

0.15 0.20 0.25

Warm Season Grasses

Bouteloua gracilis Calamovilfa longifolia Schizachyrium scoparium

Alternate Warm Season

(for one of above species) Bouteloua curtipendula

Bad River Goshen

Badlands

Pierre

Blue grama Prairie sandreed Little bluestem

Sideoats grama

0.10

Forbs Dalea purpurea

OR

Dalea candida

Local1

Antelope1

Purple prairieclover

White prairieclover

0.04

0.04

Helianthus pauciflorus

OR

Solidago rigida

Bismarck1

Stiff sunflower

Stiff goldenrod

0.03

Echinacea angustifolia

OR

Ratibida columnifera

Bismarck1

Purple coneflower

Prairie coneflower

Totals 100%

725 - Miscellaneous Material

725.40_Project_8_15_2018

Add the following Subsection 725.19.

725.19 High-Strength Non-shrink Grout.

Furnish grout that is packaged and ready for use with the addition of water at the construction site.

Ensure that each bag is stamped to show the last date on which it may be used. Use grout that consists of a hydraulic cementitious system, graded and processed natural fine aggregate, and additional technical components such that the product meets the following conditions:

(a) Free of inorganic accelerators, including chlorides.

(b) Free of oxidizing catalysts.

(c) Free of gas-producing agents.

(d) When mixed to 130 percent flow on flow table (ASTM C 230 at 10 drops), it does not reduce in linear dimension when tested in accordance with ASTM C157. Take measurements at 72 hours and 7 days.

(e) Produces no bleeding for the first 2 hours after mixing when mixed to 130 percent flow on flow table (ASTM C 230 at 10 drops), as tested in accordance with ASTM C232.

(f) Has a minimum strength as follows when tested in accordance with ASTM C 109:

(1) After 72 hours, 25 MPa (3500 psi).

(2) At 7 days, 40 MPa (6000 psi).

(3) After 28 days, 50 MPa (7200 psi).

Provide performance characteristics at 115 to 120 percent flow on flow table (ASTM C

230 at 10 drops).

(g) It must be designed, as stated by the manufacturer, to be mixed, placed, and cured at atmospheric temperatures of 5O C to 30O C (40O F to 85O F). Submit products proposed for use for approval by the CO and accompany them with manufacturer’s submittals substantiating all requirements in this subsection, including graphs or charts showing the time, temperature, and humidity requirements for curing to achieve the specified grout strengths; and recommendations for storage, mixing, application, and curing procedures.

As specified as grout on the contract plans, the following products meet the above requirements.

1. MASTERFLOW 928 GROUT, manufactured by Chemrex.

2. CRYSTEX GROUT, manufactured by L&M Construction Chemicals, Inc.

3. CEMENT ALL, manufactured by CTS Cement Manufacturing Co.

4. SURE-GRIP HIGH PERFORMANCE GROUT manufactured by Dayton Superior.

725.41_Project_8_15_2018

Add the following Subsection 725.20.

725.20 Mortar.

Furnish mortar that is packaged and ready for use with the addition of water at the construction site.

Ensure that each bag is stamped to show the latest date on which it may be used. Use mortar that consists of a cementitious system made up of:

(a) Natural aggregate, 3/8” maximum size, that meets the requirements specified in ASTM C 33 except for grading. Accomplish grading by blending sieve sizes to obtain the optimum density.

(b) Metallic aggregate free from nonferrous material, soluble alkaline compounds, and visible rust.

(c) Water reducers, workability agents, air-entraining agents, and catalysts.

Blend the materials to minimize bleeding, increase workability, resist exposure to freeze-thaw cycles and deicing salts, and prevent shrinkage within and at the perimeter of the patch, keyway, or other area to be filled.

Ensure that the minimum compressive strength of the mortar, as tested by ASTM C 109 for a 3” slump, is:

• 24-hour..........................................................................................35MPa (5000 psi)

• 7-day.............................................................................................60 MPa (8500 psi)

• 28-day........................................................................................70 MPa (10,000 psi)

Ensure that the durability of the products when tested at 300 cycles, ASTM C 666, procedure A is:

Submerged in: DF (%)

Water 98

5% CaCl2 solution 95

5% NaCL solution 85

Ensure that the scaling resistance has a rating of 3, Moderate Scaling, after 50 cycles when tested in accordance with ASTM C 672.

Provide certification from the manufacturer that the product is compatible for work that is 1” or more in depth and more than 1” in width; and where the mixing, placing, and curing temperatures may range from 5O C to 30O C (40O F to 85O F).

Submit products proposed for use to the CO for approval, and accompany them with the manufacturer’s submittals substantiating all requirements in this section, including (1) graphs or charts showing the time, temperature, humidity, and curing requirements to achieve mortar strengths equal to the adjacent concrete; and (2) complete recommendations for storage, mixing, application, and curing procedures.

As specified as mortar on the contract plans, the following products meet the above requirements.

1. EMACO T425 or T430, manufactured by Chemrex.

2. RAPID SET DOT REPAIR MIX manufactured by CTS Cement Manufacturing Co.

SURE-GRIP HIGH PERFORMANCE GROUT (when extended with pea gravel) manufactured by

Dayton Superior.