1282B123R0001_Amendment 0001_S.pdf
PDF 216 KB Posted
- Attached to
- Horse Creek Culvert Replacement Federal contract opportunity
- Solicitation number
- 1282B123R0001
- Issued by
- Department of Agriculture Forest Service
About this file
This document contains an amendment to a solicitation for a federal contract. The Forest Service is seeking to replace a reinforced concrete box culvert on Forest Service Road NFSR 779-1 at Horse Creek crossing in Slope County, North Dakota. Work will include demolishing an existing 4-sided box culvert, regrading road approaches, and installing a new 20-foot span and 7-foot rise precast reinforced concrete box culvert. The period of performance is November 15, 2022 through September 1, 2023. The amendment provides responses to contractor questions, schedules a mandatory site visit on October 18, 2022, and clarifies that structural backfill must meet the gradation specified in FP 14 specifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1282B123R0001_Amendment 0002_S.pdf | ||
| Attachment 1_SOW Horse Creek Culvert Replacement_v2.pdf | ||
| Attachment 5_Wage Determination.pdf | ||
| Attachment 2_Section B Schedule.pdf | ||
| Attachment 4_ Drawings_Horse Creek.pdf | ||
| Attachment 1_SOW Horse Creek Culvert Replacement.pdf | ||
| 1282B123R0001_Final.pdf | ||
| Attachment 6_PPQ.pdf | ||
| Attachment 3_Horse Cr-FSSS-Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1282B123R0001 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
82B1
WASHINGTON DC 20250-0001
1400 INDEPENDENCE AVE SW MS-1138
SPOC INTERMOUNTAIN
USDA FOREST SERVICE
62980510/12/20220001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
10/01/2022
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment is to:
1. Answer the questions posted to date. See Pages 2-3
2. Establish a Site Visit Date, Time, and Location. See Page 3
3. Update the SOW Period of Performance to match the dates identified in the Solicitation.
See Attachment 01
4. All other terms and conditions remain unchanged
Period of Performance: 11/15/2022 to 09/01/2023
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
LUCAS J. DAHLMAN
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
12 October 2022
1. Please confirm that all structural fill used outside of the culverts and wingwalls is to be imported.
Answer: Under general notes page 2 of 15 “specifications FP14.” Under section 208 eg structural backfill in FP 14 specifications page 128 208.02 structural backfill shall conform to
704.04. Yes, it is imported and has a gradation as specified in 704.04.
2. Please provide a gradation for all structural fill.
Answer: See question 1
3. Will excess onsite materials be allowed for use as roadway embankment or must this material be imported?
Answer: See “Notes” page 4 of 15
4. The included statement of work Attachment 1 lists a completion timeline of 335 days or
September 1, 2023 while the solicitation package lists 290 days or September 1, 2023. Please clarify which is correct.
Answer: The SOW has been updated to 290 or Sept 1, 2023 whichever comes first
5. Has the government set a predetermined area which can be used for material and equipment staging and if so what are the coordinates and size of the location?
Answer: There is plenty of area for staging areas for this project in close proximity to the site.
The road shall be closed during structure replacement so we can utilize the roadway and dependent on the contractor’s operation this can be verified in the field at the time of a prework or onsite visit prior to starting work.
6. Please confirm that this project has a minority participation goal of 1.3% and female participation goal of 6.9%.
Answer: Yes. Per the DOL, the goals apply as required. See https://www.dol.gov/sites/dolgov/files/ofccp/ParticipationGoals.pdf
7. We would like to request that a pre-proposal conference be scheduled for this project.
Answer: Site Visit – Tuesday October 18th, 2022 @ 900am MST – Location - On Site – See
Solicitation Documents and Email the Contracting Officer at lucas.dahlman@usda.gov to confirm attendance
8. We would like to make the government aware that several precast suppliers have informed us that the culvert required for this project will not be available until June/July of 2023 due to their https://www.dol.gov/sites/dolgov/files/ofccp/ParticipationGoals.pdf mailto:lucas.dahlman@usda.gov current order backlog, this can have a direct impact on the ability to complete this project within the allotted contractual timeline.
Answer: After award, invoices and documentation will have to be provided to show order and expected delivery. Time will be adjusted accordingly.
9. Will contractors be allowed to bill for material on hand or partial material costs associated with the design and construction of the box culvert and wingwalls as they are invoiced to the contractor due to the extended material lead times?
Answer: With proper invoicing and proof of contractor payment, the culvert and wingwalls are eligible for partial payment.
10. Will the contractor be required to provide field offices and technical equipment for the owner such as phone, computer and internet services at the project site?
Answer: No
11. Please provide a detail for the wood post item to be installed as part of this project
Answer:. Type 3 object marker detail listed on page 10 of 15
12. What is the typical flow rate in CFM of the Horse Creek during rain events?
Answer: 2 year event = 74 cfs, 25 year event = 537 cfs, 100 year event = 855 cfs.
13. Please provide gradation requirements for the foundation fill.
Answer: See Page 664 of FP 14, section 701.01
14. Please provide a list of the pre-approved geotextile fabrics.
Answer: Class one geotextile as called out for on plan sheet 8 of 15, 9 of 15, 10 of 15. It is a
Separation and stabilization fabric, woven or non-woven meeting the specifications/properties listed on page 698, table 714-1. The supplier should be able to provide a list of fabrics that would meet this requirement. That is the preapproved list.
SITE VISIT:
Date: Tuesday, October 18th, 2022
Time: 0900am MST
Location - On Site – See Solicitation Documents
Contact: Email the Contracting Officer at lucas.dahlman@usda.gov to confirm attendance mailto:lucas.dahlman@usda.gov