Attachment 3. FJXT240014 Bid Schedule.xlsx
XLSX spreadsheet 545 KB Posted
- Attached to
- Solicitation FA449724R0018 Federal contract opportunity
- Solicitation number
- FA449724R0018
About this file
This document appears to be an attachment to a federal solicitation (FA449724R0018) for architect and engineering (A/E) design services to repair transformers and lighting for the main aircraft parking apron at Dover Air Force Base, Delaware. The design work must adhere to various Air Force and installation-specific standards and guidelines. The attachment provides a template for contractors to submit a construction cost estimate in the Construction Specifications Institute (CSI) format, with prefilled division sheets and instructions for completing the estimate. Contractors are required to fill in certain areas of the estimate, including overhead and profit percentages. The solicitation is being issued by the Department of the Air Force Air Mobility Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SOW Attachment 2 - DAFB Local Design Guide (9 Apr 18) 1.pdf | ||
| Attachment 2. Repair Main Parking Apron 35 Design Drawings.pdf | ||
| Solicitation - FA449724R0018.pdf | ||
| Attachment 1. SOW Repair Main Parking Apron Transformers and Lighting.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions Use the information from the prefilled division sheets below to complete the 50 Divisions Cost Estimate CSI* Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab. Please note that on the summary page there is a place to fill in overhead and profit percentages for both the prime and the subcontractor that will self-populate the summary page and all the division tabs.
Exceptions:
(1) if each subcontractor has a different overhead and profit rates than the percentage placed on the summary page, an adjustment will have to be made to that specific division page. The spreadsheet will still calculate correctly.
(2) If the prime is self-performing the work for that division then the profit and overhead will need to be zeroed for that particular division, because the primes overhead and profit is already captured on the summary page.
The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs except for the few exceptions listed above.
Divisions 1, 2, and 3 show sample inputs to illustrate how the spreadsheet works.
* CSI = Construction Specifications Institute
&"Verdana,Bold"Construction Cost Estimate
&P of &N
Summary CONSTRUCTION BID SCHEDULE Date:
COMPANY
| PROJECT | |||
| DSN Airfield Ramp Lighting | |||
| LOCATION | PROJECT NO. | ||
| DOVER AIR FORCE BASE, DOVER DE | FJXT240014 | ||
| DIVISION | DESCRIPTION | % by | |
| Division | Division Total |
| DIVISION 01 | GENERAL REQUIREMENTS | - 0 | ||
| DIVISION 02 | EXISTING CONDITIONS | ERROR:#DIV/0! | - 0 | |
| DIVISION 03 | CONCRETE WORK | FILL IN AS REQUIRED (this will link to the entire document) |
davisjam: davisjam:
Percentages listed are place fillers. Please complete as required
| DIVISION 04 | MASONRY | ERROR:#DIV/0! | - 0 | ||
| DIVISION 05 | METALS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 06 | WOOD, PLASTICS AND COMPOSITES | ERROR:#DIV/0! | - 0 | GC Overhead | |
| DIVISION 07 | THERMAL AND MOISTURE PROTECTION | ERROR:#DIV/0! | - 0 | GC Profit | |
| DIVISION 08 | OPENINGS | ERROR:#DIV/0! | - 0 | Sub Overhead | |
| DIVISION 09 | FINISHES | ERROR:#DIV/0! | - 0 | Sub Profit | |
| DIVISION 10 | SPECIALTIES | ERROR:#DIV/0! | - 0 | Sales Tax | 0.00% |
| DIVISION 11 | EQUIPMENT | ERROR:#DIV/0! | - 0 | Risk/Bonding | 0.00% |
| DIVISION 12 | FURNISHINGS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 13 | SPECIAL CONSTRUCTION | ERROR:#DIV/0! | - 0 | This spreadsheet contains many formulas... please save a copy prior to editting in case you make a mistake. All shaded areas are either linked or contain formulas | |
| DIVISION 14 | CONVEYING EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 15 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 16 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 20 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 21 | FIRE SUPRESSION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 22 | PLUMBING | ERROR:#DIV/0! | - 0 | ||
| DIVISION 23 | HEATING, VENTILATING AND A/C | ERROR:#DIV/0! | - 0 | ||
| DIVISION 24 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 25 | INTEGRATED AUTOMATION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 26 | ELECTRICAL | ERROR:#DIV/0! | - 0 | ||
| DIVISION 27 | COMMUNICATIONS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 28 | ELECTRONIC SAFETY AND SECURITY | ERROR:#DIV/0! | - 0 | ||
| DIVISION 29 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 30 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 31 | EARTHWORK | ERROR:#DIV/0! | - 0 | ||
| DIVISION 32 | EXTERIOR IMPROVEMENTS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 33 | UTILITIES | ERROR:#DIV/0! | - 0 | ||
| DIVISION 34 | TRANSPORTATION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 35 | WATERWAYS AND MARINE CONSTRUCTION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 36 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 37 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 38 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 39 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 40 | PROCESS INTEGRATION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 41 | MATERIAL PROCESING AND HANDLING EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 42 | PROCESS HEATING, COOLING AND DRYING EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 43 | PROCESS GAS & LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 44 | POLLUTION CONTROL EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 45 | INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 46 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 47 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 48 | ELECTRICAL POWER GENERATION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 49 | RESERVED | ERROR:#DIV/0! | - 0 |
HARD COST TOTAL ERROR:#DIV/0! - 0
| PRIME GENERAL CONTRACT OFFICE OVERHEAD (Fill in%) | 0% | - 0 |
| SUBTOTAL | - 0 | |
| PRIME GENERAL CONTRACTOR'S PROFIT(Fill in%) | 0% | - 0 |
| SUBTOTAL | - 0 | |
| BUILDER'S RISK / PERFORMANCE BONDS (Fill in%) | 0% | - 0 |
| CONTRACT TOTAL | $ - 0 |
Div1
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| GENERAL REQUIREMENTS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | - 0 | ||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div2
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| CODE A (No design completed) | ||||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | ||||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXISTING CONDITIONS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | |||||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | - 0 | ||||||
| Sub-Contractor's Profit | - 0 | ||||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div3
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONCRETE WORK | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 10.00% | - 0 | |||||
| Sub-Contractor's Profit | 15.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div4
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| CODE A (No design completed) | ||||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | ||||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| MASONRY | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div5
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXISTING CONDITIONS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div6
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| WOOD, PLASTICS AND COMPOSITES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div7
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| THERMAL AND MOISTURE PROTECTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div8
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| OPENINGS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div9
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FINISHES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div10
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIALTIES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div11
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div12
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FURNISHINGS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div13
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIAL CONSTRUCTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div14
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONVEYING EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div15
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div16
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div20
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div21
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FIRE SUPRESSION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div22
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PLUMBING | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div23
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| HEATING, VENTILATING AND A/C | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div24
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div25
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| INTEGRATED AUTOMATION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div26
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRICAL | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div27
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| COMMUNICATIONS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div28
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRONIC SAFETY AND SECURITY | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div29
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div30
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div31
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EARTHWORK | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div32
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXTERIOR IMPROVEMENTS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div33
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| UTILITIES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div34
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| TRANSPORTATION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div35
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| WATERWAYS AND MARINE CONSTRUCTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| RESERVED | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div36
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div37
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div38
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div39
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div40
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PROCESS INTEGRATION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div41
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| MATERIAL PROCESING AND HANDLING EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div42
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PROCESS HEATING, COOLING AND DRYING EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div43
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PROCESS GAS & LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | $ - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div44
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| POLLUTION CONTROL EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| Sub-Contractor's Overhead | 0.00% | - 0 | |||||
| Sub-Contractor's Profit | 0.00% | - 0 | |||||
| State Sales Tax | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div45
| CONSTRUCTION COST ESTIMATE | DATE | |||
| - 0 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| DSN Airfield Ramp Lighting | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DOVER DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 0 | 0 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .