This bid schedule outlines the requirements for a federal construction contract to provide EHRM Administrative and Training Space Support at the VA Illiana Healthcare System campus in Danville, Illinois. The contract involves three phases of work to renovations and alterations for buildings 99, 22 and other site areas over a 540 day performance period. Phase One work is to be completed within 120 days of award, Phase Two within 180 days after Phase One is finished, and Phase Three within 240 days after Phase Two. A single award will be made for the base bid, which includes all labor, materials and equipment to complete the work shown in the construction plans.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

550-21-703; EHRM Training and Administrative Space Support

STATEMENT OF BID ITEM(S)

NOTE: A SINGLE AWARD WILL BE MADE ON BID ITEM A (BASE BID)

Work location is on the campus of the VA Illiana Healthcare System located at 1900 East Main Street, Danville, IL 61832.

A. BASE BID: Furnish all labor, materials, equipment, tools, supervision, and all other necessary resources required for Project #550-21-703 “EHRM Administrative and Training Space Support” as required by the three phases detailed in the drawings and specifications. Phasing work is to be coordinated with the COR (Contracting Officer’s Representative.)

Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction and certain other items. All work shown on the accompanying Construction Plans is included in the base bid. This includes work at Buildings 99, 22, and site south of Lot N.

PHASE ONE: PERFORMANCE PERIOD OF 120 DAYS AFTER AWARD

PHASE TW0: PERFORMANCE PERIOD OF 180 DAYS AFTER PHASE ONE IS COMPLETED AND TRAILERS ARE INSTALLED BY OTHERS PHASE THREE: PERFORMACE PERIOD OF 240 DAYS AFTER PHASE TWO IS COMPLETED AND TRAILERS ARE REMOVED BY OTHERS.

TOTAL CONTRACT PERFORMANCE PERIOD: 540 DAYS AFTER AWARD