This document includes a maintenance task list for Trane cooling and heating units and Tracer 100 control panels. The maintenance task list outlines 18 specific inspection and maintenance tasks for cooling units, 11 tasks for heating units, and 7 tasks for Tracer 100 control panels. Tasks include cleaning, lubrication, inspection, adjustment, filter replacement and recording operational measurements.
The related federal contract opportunity is solicitation number SP330023Q0188 for preventative and corrective maintenance of Trane cooling and heating units and Bry-Air dehumidifier units at the Defense Logistics Agency distribution center in Albany, Georgia. The solicitation seeks maintenance services on the equipment listed in the task list documentation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP3300-17-P-1059
Attachment 2 – Maintenance Task List
MAINTENANCE TASK LIST
OPERATING INSPECTION-COOLING
Cleaning, Lubrication, Inspection, Adjustment & Operation
1. Record operating log of temperatures, pressures, voltages, amperages, etc.
2. Check and calibrate unit safety and operating controls
3. Record megohm reading for evaporator fan, condenser fan, return air fan, and compressor motors
4. Check main starter, tighten all starter bolts and terminals, and check contacts for wear
(where applicable)
5. Check oil level in compressor (where applicable)
6. Tighten terminals on motor and control panel
7. Check crankcase heater
8. Check internal interlocks (where applicable)
9. Check oil sample for acid (where applicable)
10. Check damper operation.
11. Lubricate and adjust as required
12. Inspect evaporator and condenser coils
13. Inspect evaporator, condenser, and return air fans
14. Lubricate fan bearings (where applicable)
15. Inspect and adjust belt alignment and tension (replace if required)
16. Inspect and change filters as required Report to operator any uncorrected deficiencies noted
OPERATING INSPECTION-HEATING SECTION
Cleaning, Lubrication, Inspection, Adjustment, & Operation
1. Check unit safety and operating controls
2. Tighten terminals on motor and control panel
3. Check crankcase heater
4. Check external interlocks (where applicable)
5. Check damper operation.
6. Lubricate and adjust as required
7. Inspect and change filters as required
8. Inspect heat element
9. Inspect heating control wiring
10. Clean and tighten terminal block wiring connections
11. OPERATING INSPECTIONS-TRACER 100
12. Clean Tracer control panel interior.
13. Tighten all panel terminators.
14. Check for loose or damaged parts.
15. Check and record panel transformer primary and secondary voltages.
16. View the even log and status displays to verify all inputs are reading properly.
17. Verify manual override switches are in the proper positions.
18. Check physical condition of all hardware listed on "equipment covered" list.
OPERATING INSPECTIONS-TRACER 100
Cleaning, Lubrication, Inspection, Adjustment, & Operation
1. Clean Tracer control panel interior.
2. Tighten all panel terminators.
3. Check for loose or damaged parts.
4. Check and record panel transformer primary and secondary voltages.
5. View the even log and status displays to verify all inputs are reading properly.
6. Verify manual override switches are in the proper positions.
7. Check physical condition of all hardware listed on "equipment covered" list.