This solicitation is for dock-side repair and maintenance services for USCGC BEAR from 15 May 2024 to 16 July 2024. The Coast Guard is seeking cleaning, inspection, testing and preservation services for tanks, voids, chain lockers and other spaces. Work items include cleaning and inspecting aviation fuel, diesel and potable water tanks; inspecting ballast and void spaces; testing electrical equipment; and surface preparation and coating application. The period of performance is from 15 May 2024 through 16 July 2024. The solicitation was released on 70Z08024QMECP0012. Responses are due by the date specified in the solicitation. The federal agency is the Department of Homeland Security, United States Coast Guard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A0001.pdf | ||
| Attachment 1 - USCGC BEAR FY24 DS2-AA Schedule of Services - Blank Price Schedule Rev 1.xls | XLS spreadsheet | |
| USCGC BEAR FY24 DS2-AA - 70Z08024QMECP0012 - Offeror Questions and Responses.pdf | ||
| Attachment 1 - USCGC BEAR FY24 DS2-AA Schedule of Services - Blank Price Schedule.xls | XLS spreadsheet | |
| 70Z08024QMECP0012.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC BEAR (WMEC 901)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2024
Developed By: Courtney K Brewbaker
(Rev-0, 8 November 2023)
USCGC BEAR (WMEC-270A) DOCKSIDE AVAILABILITY FY2024
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics ............................................................................................................................... xi General Requirements WORK ITEM 1: Tanks, Aviation Fuel Service, Clean And Inspect WORK ITEM 2: Tanks, Aviation Fuel Stowage And Overflow, Clean And Inspect WORK ITEM 3: Chain Lockers, Clean and Inspect WORK ITEM 4: Tanks, MP Fuel Stowage and Overflow, Clean and Inspect WORK ITEM 5: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 6: Tanks, Potable Water, Clean and Inspect WORK ITEM 7: Tanks, Ballast, Clean and Inspect WORK ITEM 8: Voids, Accessible, Clean and Inspect WORK ITEM 9: Tanks, Dirty Oil and Waste, Clean and Inspect WORK ITEM 10: Propulsion Shafting, Strain Gauge Alignment, Dockside, Check WORK ITEM 11: 28 Volt DC Helo Power Supply, Load Test WORK ITEM 12: 400 Hz Power Supply (FCX Systems Inc), Load Test WORK ITEM 13: Circuit Breakers (400 HZ), Inspect and Test WORK ITEM 14: Windspeed Transmitter, Anemometer, Renew WORK ITEM 15: Vent Ducts, Engine and Motor Room, All, Commercial Cleaning WORK ITEM 16: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning WORK ITEM 17: Vent Ducts, Laundry Exhaust, Commercial Cleaning WORK ITEM 18: Vent Ducts, All Other, Commercial Cleaning WORK ITEM 19: Commissary Hoist, Inspect and Service WORK ITEM 20: Anchor Chains and Ground Tackle, Inspect and Repair WORK ITEM 21: Anchor Windlass, Overhaul WORK ITEM 22: Towing Bitts, Chocks, and Fairleads; Inspect and Test WORK ITEM 23: Warping Capstan, Overhaul WORK ITEM 24: Helo Talon Grids, Inspect and Test WORK ITEM 25: Decks, Helicopter Operating Areas, Preserve WORK ITEM 26: Bulkhead and Overhead Sheathing and Insulation, Renew WORK ITEM 27: Deck Covering, Interior, Wet and Dry, Renew WORK ITEM 28: Helicopter Tie-Down Fittings, Renew WORK ITEM 29: Flight Deck Coaming, Remove WORK ITEM 30: Air Escape and Overflow Piping, Renew WORK ITEM 31: Vent Duct Insulation, Renew WORK ITEM 32: Fuel Oil Deck Connection, Renew WORK ITEM 33: Heating Coil, Renew WORK ITEM 34: Ventilation Fans and Ducting, Renew WORK ITEM 35: Chain Lockers, Preserve, Partial WORK ITEM 36: Tanks, Ballast, Preserve, Partial WORK ITEM 37: Tanks, Dirty Oil and Waste, Preserve, Partial WORK ITEM 38: Flow Meter (Aviation Fuel), Replace WORK ITEM 39: Point of Use Potable Water Filters, Install iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 111-002, Rev G, Shell Exp Aft 182
Coast Guard Drawing 901 WMEC 113-001, Rev E, Tank Top PL & FR Fwd FR 101
Coast Guard Drawing 901 WMEC 113-002, Rev A, Tank Top PL & FR Aft 182
Coast Guard Drawing 901 WMEC 113-003, Rev G, Tank Top PL & FR, FR 101-182
Coast Guard Drawing 901 WMEC 116-001, Rev D, CVK Fwd 101 & G Long 2
Coast Guard Drawing 901 WMEC 116-002, Rev E, CVK Aft 182
Coast Guard Drawing 901 WMEC 116-003, Rev E, CVK Fr 101-182 & G Long. 2&4
Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182
Coast Guard Drawing 901 WMEC 122-001, Rev H, Transv Bhds 12 & 26
Coast Guard Drawing 901 WMEC 122-002, Rev G, Transv Bhds 47, 78 & 82
Coast Guard Drawing 901 WMEC 122-003, Rev G, Transv Bhds 103, 117
Coast Guard Drawing 901 WMEC 122-004, Rev F, Transv. Bhds. 165, 169, 151.6
Coast Guard Drawing 901 WMEC 122-005, Rev F, Transv Bhds 186 & 190
Coast Guard Drawing 901 WMEC 122-006, Rev F, Transv Bhds 196, 207, 228 & 242
Coast Guard Drawing 901 WMEC 123-001, Rev C, Dumbwaiter TRK & FDN FR 165
Coast Guard Drawing 901 WMEC 123-002, Rev D, Chain Lkr Bhds & Details
Coast Guard Drawing 901 WMEC 123-007, Rev C, Tank (4-169-1-W) Modification Incidental to OWS
Installation
Coast Guard Drawing 901 WMEC 131-001, Rev H, Mn Dk Pl & Fr FWD 101
Coast Guard Drawing 901 WMEC 131-003, Rev H, Main Deck Plate & Frame 101-182
Coast Guard Drawing 901 WMEC 136-002, Rev F, 01 Level Pl & Fr Aft 182
Coast Guard Drawing 901 WMEC 141-001, Rev F, 1st Platform Plate & Frame FWD 103
Coast Guard Drawing 901 WMEC 141-003, Rev G, 1st Platform Plate & Frame 151-2/3 – 182
Coast Guard Drawing 901 WMEC 152-005, Rev J, 02 Level Plating & Framework
Coast Guard Drawing 901 WMEC 171-001, Rev J, Main Mast
Coast Guard Drawing 901 WMEC 185-003, Rev C, Capstan Foundation
Coast Guard Drawing 901 WMEC 185-004, Rev E, Anchor Windlass Fdn
Coast Guard Drawing 901 WMEC 185-005, Rev-, Installation of Jered Anchor Windlass & Warping
Capstan “A” Class MEP v (Rev-0)
Coast Guard Drawing 901 WMEC 186-003, Rev-, Talon Grid Foundation & Structural Mod 01 Level
Coast Guard Drawing 901 WMEC 233-005, Rev Z, Piping Schematic (Fuel Oil System)
Coast Guard Drawing 901 WMEC 243-001, Rev L, Shafting Arrangement
Coast Guard Drawing 901 WMEC 243-005, Rev D, Sftg Align Anal and Procs
Coast Guard Drawing 901 WMEC 262-001, Rev J, Lube Oil Sys Diag
Coast Guard Drawing 901 WMEC 314-002, Rev G, 400 Hz MG Wiring Diagram
Coast Guard Drawing 901 WMEC 314-003, Rev L, 400 Hz MG Schematic Diagram
Coast Guard Drawing 901 WMEC 314-005, Rev B, 28.5 VDC Hlcptr Start Rect Replacement Diagram
Coast Guard Drawing 901 WMEC 314-006, Rev D, 400Hz Hlcptr Svce Freqconv Installation Diagram
Coast Guard Drawing 901 WMEC 320-011, Rev N, 400 Hz Distr IWD
Coast Guard Drawing 901 WMEC 320-031, Rev B, 400 Hz Distr IWD
Coast Guard Drawing 901 WMEC 320-035, Rev AR, As Built Electrical One-Line Diagram
Coast Guard Drawing 901 WMEC 324-008, Rev J, 400Hz Switchboard Arrangement and Details
Coast Guard Drawing 901 WMEC 324-009, Rev G, 400Hz Swbd EWD
Coast Guard Drawing 901 WMEC 431-003, Rev G, Main IC Switchboard Arrangements, Elem Wrg Diag
& Dets
Coast Guard Drawing 901 WMEC 494-001, Rev T, Meteorological System Block & Isometric W.D.
Coast Guard Drawing 901 WMEC 505-008, Rev C, Bhd, Dk & Shell Piping Penetrations
Coast Guard Drawing 901 WMEC 506-001, Rev K, Ovfl AE & St Sys Diag
Coast Guard Drawing 901 WMEC 506-003, Rev K, Ovfl AE & St A&D Aft 103
Coast Guard Drawing 901 WMEC 513-005 Rev F, Vent, Engine Room & ECC Plan, Section & Elevation
A&D
Coast Guard Drawing 901 WMEC 514-001, Rev L, HVAC Sys Diag
Coast Guard Drawing 901 WMEC 514-002, Rev L, HVAC Equipment List
Coast Guard Drawing 901 WMEC 514-003, Rev D, HVAC Standard Details and General Instructions
Coast Guard Drawing 901 WMEC 514-005, Rev J, HVAC Fan Rooms Mn Dk A&D
Coast Guard Drawing 901 WMEC 514-006, Rev H, HVAC Fan Rm 02 Lvl A&D
Coast Guard Drawing 901 WMEC 514-020, Rev K, Chw & Hw System Diagram
Coast Guard Drawing 901 WMEC 529-001, Rev N, Ballasting & Emer Bilge Drainage Sys Diagram
Coast Guard Drawing 901 WMEC 533-003, Rev R, Potable Water Brominator System Diagram
Coast Guard Drawing 901 WMEC 533-005, Rev J, H&C Potable Water System Mn Dk - A & D
Coast Guard Drawing 901 WMEC 533-006, Rev H, H & C Potable Water System, 01 Lvl & Abv A&D
Coast Guard Drawing 901 WMEC 533-007, Rev J, H & C Potable Water Blw Mn Dk
Coast Guard Drawing 901 WMEC 541-001, Rev G, Fuel Oil Fill & Transfer System Diagram
Coast Guard Drawing 901 WMEC 541-002, Rev F, Fuel Oil Fill & Transfer IMS – A&D
Coast Guard Drawing 901 WMEC 541-003, Rev J, F.O. Fill & Xfr OMS – A&D
Coast Guard Drawing 901 WMEC 542-001, Rev J, JP-5 System Diagram
Coast Guard Drawing 901 WMEC 542-002, Rev H, JP-5 Sys - A&D
Coast Guard Drawing 901 WMEC 572-001, Rev G, Svce Hoist Instl A&D
Coast Guard Drawing 901 WMEC 581-001, Rev G, Anchor Handling A & D
Coast Guard Drawing 901 WMEC 581-002, Rev C, Hawse & Chain Pipes
Coast Guard Drawing 901 WMEC 581-004, Rev J, Anchor Windlass Arrangement and Details vi (Rev-0)
Coast Guard Drawing 901 WMEC 582-001, Rev F, Mooring & Towing Ftgs – A&D
Coast Guard Drawing 901 WMEC 582-002, Rev F, Capstan Arrangement and Details
Coast Guard Drawing 901 WMEC 588-001, Rev F, Helicopter Tie Down Fittings Arr & Dets
Coast Guard Drawing 901 WMEC 621-004, Rev N, Joiner Arr Main Deck FR 103-207
Coast Guard Drawing 901 WMEC 634-001, Rev G, Deck Covering Schedule
Coast Guard Drawing 901 WMEC 634-002, Rev-, 270 Ft WMEC C & A, Pnt, Dk Cov & Insul Mod Helo
Securing Grid Instl
Coast Guard Drawing 901 WMEC 635-001, Rev K, Hull Thermal & Acoustic Insulation A/D
Coast Guard Drawing 901 WMEC 651-001, Rev P, Galley and Scullery Arr and Det
Coast Guard Drawing 901 WMEC 801-004, Rev K, General Arrangement 01 Level
Coast Guard Drawing 901 WMEC 801-006 Rev M, General Arrangement 1st Platform
Coast Guard Drawing 901 WMEC 801-010, Rev C, Inboard Profile
Coast Guard Drawing 901 WMEC 801-018, Rev G, Booklet of Genl. Notes and Details
Coast Guard Drawing 901 WMEC 801-020, Rev G, Booklet of General Plans
Coast Guard Drawing FL 533-002, Rev A, Point of use Water Filter Install
Coast Guard Drawing FL-588-003, Rev -, Talon Grid, Supporting Skirt & Cover Fabrication & Instl
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual
Coast Guard Technical Publication (TP) 2711, SWBS 437, Jan 1992, Wind Transmitter
Coast Guard Technical Publication (TP) 2721, May 2016, SWBS 572, Dumbwaiter
Coast Guard Technical Publication (TP) 2721, May 2016, SWBS 581, Section A, Windlass, Anchor
Coast Guard Technical Publication (TP) 2721, May 2016, SWBS 582, Section A, Technical Manual for
Warping Capstan Model No. 3404-EC
Coast Guard Technical Publication (TP) 2823B, Manufacturer's Instruction Book-SWBS Group(s) 324-
426, Section A; Aug 2015; Switchboard, 400 Hz
Coast Guard Technical Publication (TP) 3368, Jun 2020, Talon Helicopter Landing Grid - Type 18-22-01
Multiple Class Cutters
Coast Guard Technical Publication (TP) 4931, Aug 2009, Section 321A, Precision Frequency Converters
Coast Guard Technical Publication (TP) 5461, SWBS 421, Nov 2012, Anemometer – Model 120 & 122
Coast Guard Technical Publication (TP) 7099, SWBS 314, Oct 2009, Rectifier Power Supply - 28 VDC, 300 A
Coast Guard Technical Publication (TP) 9146, SWBS 542, Jul 2022, Rotary Meter-Model Type 40 and
Register-Operating, Maintenance and Parts Manual
Coast Guard Technical Specification D-123-2048, Feb 2020, 270’ WMEC A Class Fluid Handling Plan for Tank Inspections
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 2351 (SFLC Std Spec 2351), 2022, Overhaul DC
Generators and Motors In-Shop vii (Rev-0)
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC
Electrical Motors In-Shop
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard
Electrical Cable Test
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean
Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior
Deck Covering Systems
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary
Hull Accesses
OTHER REFERENCES
American Bureau of Shipping (ABS) Approved Chain, Accessory and Bar Manufacturing Facilities List, Oct 2016
American National Standards Institute (ANSI) C37.50, 2018, Low Voltage AC Power Circuit Breakers
Used in Enclosures, Test Procedures
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities
American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System
Components - Health Effects
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component
Adhesives (AN)
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
Federal Specification (Fed Spec) QQ-N-281D (2), Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Federal Specification (Fed Spec) RR-C-271, Rev E, Mar 2016, Chains and Attachments, Carbon and
Alloy Steel
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe
Hangers and Supports - Materials, Design, Manufacture, Selection, Application and Installation
MIL-C-24633, Oct 2014, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded
MIL-DTL-23549, Sep 2016, Grease, General Purpose
MIL-PRF-16173, 2017, Corrosion Preventive Compound, Solvent Cutback, Cold-Application
MIL-PRF-24667C, March 2018, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering
Application
MIL-STD-1399 Section 300, Part 1, 25 September 2018, Low Voltage Electric Power, Alternating
Current
National Electrical Manufacturers Association (NEMA) Std, pub. No. AB4, 2017, Guidelines for
Inspection and Preventative Maintenance of Molded Case Circuit Breakers used in Commercial and
Industrial Application
NAVAIR SI-ACS-AFB-1P, 01 July 2020, Air Capable Ship Aviation Facilities Bulletin No. 1P viii (Rev-0)
Naval Air Warfare Center (NAVAIR) Drawing 621055, Rev G, Visual Landing Aids Installation
WMEC-270 Class Ships
NAVSEA Drawing 803-1385866, Rev E, Penetration, Bulkhead and Deck
NAVSEA Drawing 803-1916300, Rev N, Aircraft Securing and Engine Run Up
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation
Details
NAVSEA Drawing 804-5959214, Rev. -, Piping Insulation, Installation Details
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning
Underwriters Laboratories Inc. (UL) 1066, Apr 2012, Low-Voltage AC and DC Power Circuit Breakers
Used in Enclosures
Underwriters Laboratories Inc. (UL) 489, Oct 2016, Molded Case Circuit Breaker ix (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
14 Y Anemometer NSN: 6600-00-709-9947 2 ea. 5,316.00
23 N Kit, Overhaul, Warping
Capstan
NSN: 2030-01-F22-6596 1 ea. 3,400.00
24 N Screw, Cap, 5/8-11 UNC
2A x 3in.
NSN: 5305-01-393-1827 24 ea. 25.65
24 N Screw, Cap, M12-1.75 x
42 mm
NSN: 5305-01-584-6095 12 ea. 33.75
24 N **Talon Grid Stanchion
Bolt Assembly, Including
Locking Nut
NSN: 5340-01-481-3786 60 ea. 31.50
28 N Tie-down fitting, crossbar flush type
NSN: 5365-01-646-0939 P/N:
PH285N-14
2 ea.
381.19
33 N Marlo heating coil, 12-3/8 x 18 in
PN: 2W8-18-5608F-1.5-0.25S 1 ea.
3679.00
33 N Marlo heating coil, 33-3/8 x 30 in
PN: 2W22-30-5608F-6.95-1S 1 ea.
4826.00
38 N Meter, Impeller Type, Liquid
NSN: 6680-00-930-5955 1 ea. 4,126.41
N ASM Flange Assembly 1
½ inch Cast Iron, Oval
Buna
NSN: 4730-01-F22-6578
PN: 009805-014
1 kt. 167.83
39 N ***Water Filter
Assembly
PN: DWS160-L (3M)
NSN: 4330-01-F20-5959
11 ea. 172.44
39 N ***Water Filter Element PN: 56134-44 (3M)
NSN: 4330-01-F20-5960
11 ea. 139.00
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.
x (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4
(Inspection report particulars)):
Work
Item Title
19 Commissary Hoist, Inspect and Service
20 Anchor Chains and Ground Tackle, Inspect and Repair
21 Anchor Windlass, Overhaul
23 Warping Capstan, Overhaul
24 Helo Talon Grids, Inspect and Test xi (Rev-0)
PRINCIPAL CHARACTERISTICS
270' WMEC (A-CLASS)
PHYSICAL
Length overall 270' 0"
Length between perpendiculars 255' 0"
Beam molded 38' 0"
Depth molded, main deck amidships
01 level amidships
23' 6"
31' 4"
Full load displacement 1,902.2 long tons
Draft, full load to baseline amidships 14' 3"
Highest projection above baseline
*height approximated
≈ 110' 0"
Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase
Frame spacing 1' 0"
MACHINERY
Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,600 BHP each
Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-
1350 Generators. 475 KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4-
1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle
Number of propellers 2
Propeller diameter 9' 0"
Number of blades, Each 4
Pitch Controllable
Shaft RPM 260
Shaft diameter 10.55" at exit of hull
Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each
TANK CAPACITIES
Diesel fuel total (95%) 79,210 gal.
JP-5 total (95%) 25,890 gal.
Potable water total (100%) 8,553 gal.
Hydraulic & lube oil total (95%) 2,237 gal.
1 (Rev-0)
00000_0623_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast
Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must
3 (Rev-0) be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC
Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable
Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Large
Quantity Generator (LQG).
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an
NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’
Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
4 (Rev-0)
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental
Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For
Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.6.1 The Contractor must obtain RapidGate Credentials for access to Base Portsmouth.
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading
(mils)
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
11 (Rev-0)
4.2 Tank and Void Assessment form.
12 (Rev-0)
13 (Rev-0)
12300_ESD_1022_FLT
REC_12311_FLT_270’ WMEC ‘A’ Class (ALL) (0423)
WORK ITEM 1: Tanks, Aviation Fuel Service, Clean And Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TYPE OF
TANK
LOCATION
CAPACITY - 95%
(GALLONS)
LOW SUCTION
(GALLONS)
JP-5 Service 3-190-1-J 890 80
JP-5 Service 3-190-2-J 890 80
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 113-001, Rev E, Tank Top PL & FR Fwd FR 101
Coast Guard Drawing 901 WMEC 113-002, Rev A, Tank Top PL & FR Aft 182
Coast Guard Drawing 901 WMEC 113-003, Rev G, Tank Top PL & FR, FR 101-182
Coast Guard Drawing 901 WMEC 116-001, Rev D, CVK Fwd 101 & G Long 2
Coast Guard Drawing 901 WMEC 116-002, Rev E, CVK Aft 182
Coast Guard Drawing 901 WMEC 116-003, Rev E, CVKFr 101-182 & G Long. 2&4
Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182
Coast Guard Drawing 901 WMEC 122-001, Rev H, Transv Bhds 12 & 26
Coast Guard Drawing 901 WMEC 122-002, Rev G, Transv Bhds 47, 78 & 82
Coast Guard Drawing 901 WMEC 122-003, Rev G, Transv Bhds 103, 117
Coast Guard Drawing 901 WMEC 122-004, Rev F, Transv. Bhds. 165, 169, 151.6
Coast Guard Drawing 901 WMEC 122-005, Rev F, Transv Bhds 186 & 190
Coast Guard Drawing 901 WMEC 122-006, Rev F, Transv Bhds 196, 207, 228 & 242
COAST GUARD PUBLICATIONS
Coast Guard Technical Specification D-123-2048, Feb 2020, 270’ WMEC A Class Fluid
Handling Plan for Tank Inspections
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
14 (Rev-0)
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
Federal Specification (Fed Spec) QQ-N-281D(2), Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General. The Contractor must refer to the Coast Guard Drawings listed under Section 2 (References) for guidance in accomplishing this work.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• JP-5 Service Tank 3-190-1-J (890 gallon capacity)
• JP-5 Service Tank 3-190-2-J (890 gallon capacity)
NOTE
Vessel may come in with less tank fluid contents than specified above. The
Contractor is responsible for providing all materials, equipment and services necessary to comply with local environmental regulations.
3.1.4.1 The Contractor must follow the fluid handling plan in accordance with Coast Guard Technical
Spec D-123-2048 when moving fluid between tanks to ensure adequate stability of the vessel.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
15 (Rev-0)
3.3 Cleaning requirements. The Contractor must remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual water, sediment, sludge, rust, and bacterial growth, taking care not to damage the coating system (if applicable).
3.3.1 Remove cleaning media and residues continuously during the washing process. Wash the tank with high-pressure cold fresh water before it has a chance to dry after emptying. Do not use steam; it can damage the tank’s coating.
3.3.2 Drain and dry the tank using a portable air-driven pump. When dry, and after final visual inspection, close the tank. Submit a CFR.
WARNING
Do not use the Fuel Service or Transfer systems to drain water from the tank.
Excessive fuel contamination will result.
3.4 Tank content and waste disposal. The Contractor must dispose of tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.
3.5 Visual inspection. The Contractor must visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Complete the “Tank and Void Assessment Form” (found in the Work Item titled “General Requirements”) and submit via CFR. Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:
• Tank structural condition.
• Inaccessible areas.
• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
• Tank level indicator (TLI) and/or float switch condition.
• Sounding/vent tube and striker plate condition.
• Suction and discharge piping condition.
• Fastener material and condition.
3.6 Tank closing. The Contractor must ensure that the tank(s) remain open for approximately 24 hours after completion of any KO-authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast
Guard Inspector. After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.
Chase threads on studs to ensure even installation of the access covers. Renew any damaged or non-monel nuts with Nickel-Copper alloy (monel) nuts meeting QQ-N-281, Class A or B. The nuts and bolts must be of different classes to prevent galling. Contractor must renew 100% of existing fasteners.
Coast Guard personnel will operate all shipboard machinery and equipment.
16 (Rev-0)
3.7 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
4. NOTES
4.1 Tank content removal. The Ship’s force will pump down the tanks to the maximum extent possible with the installed pumping system.
4.2 Tank inspection. The Coast Guard Inspector will visually inspect the tank interior immediately prior to closing.
4.3 Refilling. After final visual inspection and tank closure, Ship’s force will refill tank with JP-5 fuel.
Recirculate the fuel until it is clear and bright and passes the MK I and MK III detector kit tests. Flush all lines, pipes, and fittings before placing the JP-5 system back in service.
17 (Rev-0)
WORK ITEM 2: Tanks, Aviation Fuel Stowage And Overflow, Clean And Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TYPE OF TANK LOCATION
CAPACITY - 95%
(GALLONS)
LOW SUCTION
(GALLONS)
JP-5 Drain 4-186-1-J 219 20
JP-5 Overflow 4-186-2-J 610 40
JP-5 Storage 4-190-1-J 8,928 300
JP-5 Storage 4-190-2-J 8,928 300
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 901 WMEC 113-001, Rev E, Tank Top PL & FR Fwd FR 101
Coast Guard Drawing 901 WMEC 113-002, Rev A, Tank Top PL & FR Aft 182
Coast Guard Drawing 901 WMEC 113-003, Rev G, Tank Top PL & FR, FR 101-182
Coast Guard Drawing 901 WMEC 116-001, Rev D, CVK Fwd 101 & G Long 2
Coast Guard Drawing 901 WMEC 116-002, Rev E, CVK Aft 182
Coast Guard Drawing 901 WMEC 116-003, Rev E, CVK Fr 101-182 & G Long. 2&4
Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182
Coast Guard Drawing 901 WMEC 122-001, Rev H, Transv Bhds 12 & 26
Coast Guard Drawing 901 WMEC 122-002, Rev G, Transv Bhds 47, 78 & 82
Coast Guard Drawing 901 WMEC 122-003, Rev G, Transv Bhds 103, 117
Coast Guard Drawing 901 WMEC 122-004, Rev F, Transv. Bhds. 165, 169, 151.6
Coast Guard Drawing 901 WMEC 122-005, Rev F, Transv Bhds 186 & 190
Coast Guard Drawing 901 WMEC 122-006, Rev F, Transv Bhds 196, 207, 228 & 242
18 (Rev-0)
COAST GUARD PUBLICATIONS
Coast Guard Technical Specification D-123-2048, Feb 2020, 270’ WMEC A Class Fluid
Handling Plan for Tank Inspections
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
Federal Specification (Fed Spec) QQ-N-281D (2), Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183A, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets
3. REQUIREMENTS
3.1 General. The Contractor must refer to the Coast Guard Drawings listed under Section 2 (References) for guidance in accomplishing this work.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
NOTE
Vessel may come in with less tank fluid contents than specified above. The
Contractor is responsible for providing all materials, equipment and services necessary to comply with local environmental regulations.
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, (Interferences). Known interferences include, but are not limited to the following:
• JP-5 Drain Tank 4-186-1-J (219 gallon capacity)
• JP-5 Overflow Tank 4-186-2-J (610 gallon capacity)
• JP-5 Storage Tank 4-190-1-J (8,928 gallon capacity)
• JP-5 Storage Tank 4-190-2-J (8,928 gallon capacity)
3.1.4.1 The Contractor must follow the fluid handling plan in accordance with Coast Guard Technical
Spec D-123-2048 when moving fluid between tanks to ensure adequate stability of the vessel.
19 (Rev-0)
3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard…