This document is a Statement of Work (SOW) for upgrading the VIA CONTROL software used on two 9.1 meter Viasat antennas operated by the 10th Space Operations Squadron (10 SOPS). The key requirements include:

The contractor shall develop a RHEL 8 version of the VIA CONTROL software that is compliant with DoD Information Assurance (IA) and NIST SP 800-53 security controls. The contractor shall install and test the RHEL 8 VIA CONTROL software on customer-provided HPE DL360 Gen10+ servers at the 10 SOPS locations in Point Mugu, CA and Prospect Harbor, ME. The software must undergo comprehensive testing against live satellite operations. The contractor shall also provide updated documentation, including system architecture, security controls, and operational procedures.

The related federal contract opportunity has a solicitation number of FA255024Q0037 and is being issued by the Department of the Air Force Space Command for the 10 SOPS VIA CONTROL software upgrade. The delivery date is 60 days after receipt of order.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work 10 SOPS Viasat VIA CONTROL Software Delivery

Current as of 13 August 2024

1.0 Background

10th Space Operations Squadron (10SOPS) operates 24x7x365 in support of Satellite Operations and is located at Point Mugu, CA and Prospect Harbor, ME. In support of Satellite control, 10SOPS uses SCN antennas along with two 9.1-meter Viasat antennas. They are critical in 10SOPS mission of operations.

The Viasat antennas collect telemetry data from various satellites and transmit commands to ensure satellite health and safety. The two Viasat 9.1 meter antennas were delivered in June of 2023 with a VIA CONTROL software using CentOS Linux 7 (CentOS 7). On June 30, 2024, CentOS 7 will reach End of Life (EOL) and will no longer be supported. Therefore, 10SOPS requires an updated version of the VIA CONTROL software using Red Hat Linux 8 (RHEL 8) operating system that is compliant with Department of Defense (DoD) Information Assurance (IA).

2.0 Requirements

2.1. Required Software: An updated version of VIA CONTROL using RHEL 8 is required. Specific requirements include:

- The contractor shall develop a RHEL 8 version of the VIA CONTROL software that is compliant with the DoD IA Software Technical Implementation Guide (STIG).

- The contractor shall install the DoD IA STIG compliant RHEL 8 and VIA CONTROL software on customer provided 4 (four) HPE DL360 Gen 10+ servers at the customer Headquarters site located at 661 13th Street Point Mugu, CA 90342.

- The contractor shall install and test 1 (one) HPE DL360 Gen10+ server into the Laguna Peak 9.1 m Viasat antenna with the updated RHEL 8 VIA CONTROL software and install and test 1 (one) HPE DL360 Gen10+ server into the Prospect Harbor 9.1m Viasat antenna with the updated RHEL8 VIA CONTROL software. The tests shall be conducted against live Ultra-High Frequency Follow-on (UFO) and Mobile User Objective System (MUOS) satellites operating in geosynchronous orbits. The tests shall include at a minimum:

• Viacontrol access and equipment interfaces are green

• Viacontrol configuration transferred and verified

• Viacontrol can schedule support

• ACU access permitted and can control antenna movement

• Unified S-Band (USB) uplink command test.

• S-Band uplink command test.

• S-Band downlink telemetry test.

• A demonstration of accurate ranging capabilities.

• A demonstration of auto tracking capabilities.

3.0 Information Assurance Requirements

3.1 The contractor shall provide IT products that adhere to the cybersecurity policies and guidelines specified in Department of Defense Directive 8500 and comply with the National Institute of Standards and Technology (NIST) Special Publication (SP) 800-53 controls. The objective is to ensure the highest level of security and compliance for the implemented solutions within the 10 SOPS environment.

3.2 Assess DoD Cybersecurity Requirements:

- Conduct a comprehensive assessment of the cybersecurity policies and guidelines outlined in DoD Directive 8500 and the NIST SP 800-53 controls.

- Identify specific compliance requirements from NIST SP 800-53 and document them for reference throughout the project.

3.3 Design and Development:

- Develop a detailed project plan outlining the approach, timelines, and resources required for the design and development of the IT products within the 10 SOPS environment.

- Implement robust cybersecurity measures and protocols in accordance with DoD Directive 8500 and the NIST SP 800-53 controls to ensure compliance.

- Incorporate the appropriate NIST SP 800-53 security controls, such as access controls, audit and accountability measures, system and information integrity, and incident response, into the design and development of the IT products.

- Employ encryption, access controls, and other industry-standard security measures as specified by the NIST SP 800-53 controls to safeguard sensitive data.

3.4 Testing and Quality Assurance:

- Perform thorough testing of the IT products to validate compliance with the cybersecurity policies and guidelines specified in DoD Directive 8500 and the NIST SP 800-53 controls.

3.5 Documentation and Reporting:

- Prepare comprehensive documentation, including system architecture, security controls, and operational procedures, in adherence to DoD Directive 8500 and the NIST SP 800-53 controls.

3.6 Deliverables:

-Design documents, including system architecture and security controls, aligned with the requirements of DoD Directive 8500 and the NIST SP 800-53 controls.

- Fully developed and tested IT products compliant with the cybersecurity policies and guidelines specified in DoD Directive 8500 and the NIST SP 800-53 controls.

- Comprehensive documentation, including operational procedures, user manuals, and security protocols, in accordance with DoD Directive 8500 and the NIST SP 800-53 controls.

3.7 Project Management:

- Provide a dedicated project manager responsible for overseeing the successful execution of the project within the 10 SOPS environment.

- Establish effective communication channels for timely updates, issue resolution, and decision-making.

3.8 Timeline and Milestones:

- Define specific timelines and milestones for each phase of the project, ensuring adherence to agreed-upon schedules within the 10 SOPS environment.

6. Compliance and Security:

- Ensure that all IT products meet or exceed the cybersecurity policies and guidelines specified in DoD Directive 8500 and the NIST SP 800-53 controls.

- Maintain compliance with relevant DoD standards, regulations, and guidelines, as well as the NIST SP 800-53 controls, throughout the project duration.

4.0 Documentation

4.1 Viasat shall provide an updated Computer Interface Control Documentation for the Antenna Control Unit (ACU) from the original document delivered in June 2023.

5.0 Government Furnished Equipment

5.1 Laguna Peak and Prospect Harbor Viasat 9.1m antenna system servers located at Point Mugu, CA.

5.2 (four) HPE ProLiant DL360 Gen 10 Plus Servers with the following specifications:

- Chassis: HPE DL360 Gen10+

- Processor: Intel Xeon Silver 4310, P/N P36921-B21

- Memory: 4x 16GB RDIMM, 3200MT/s, Dual Rank, P/N P06031-B21

- Storage: 2x 1.2TB 10K RPM SAS 12Gbps Self-Encrypting Hard Drives in RAID 1, P/N P28586-B21

- Network Card: Intel I350-T4 Ethernet 1Gb 4-port BASE-T OCP3, P/N P08449-B21 External USB DVD and Blu-ray drives are available.

6.0 Delivery

6.1 The contractor shall deliver RHEL 8 compatible VIA CONTROL software 60 days after receipt of order (ARO).

Delivery location is:

10 Space Operations Squadron 661 13th Street Bldg 375 Point Mugu, CA 93042

7.0 Installation

7.1 Laguna Peak 9.1m Viasat antenna located within the 10 SOPS Laguna Peak compound and on the Viasat 9.1m antenna located at Prospect Harbor, ME.

7.2 Installation locations are below:

Point Mugu: 10 SOPS 661 13th Street Bldg 375 Point Mugu, CA 93042

Prospect Harbor:

115 Lighthouse Point Rd Prospect Harbor, ME 04669

File details come from the government source that posted it. Updated .