This is a combined synopsis/solicitation for unplanned dock-side repairs to the USCGC Paul Clark (WPC 1006). The solicitation is issued by the United States Coast Guard as a request for quotations, with a 100% total small business set-aside. The contractor shall provide all labor, materials, and services to meet the requirements specified in the statement of work, which include renewing both main diesel engines, preserving ship structures, and conducting operational tests. The North American Industry Classification System code applicable is 336611, with a small business size standard of 1,250 employees. Quotations must be submitted in response to solicitation number 70Z080-21-Q-P4504900 by the specified deadline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC PAUL CLARK (WPC 1006)
SPECIFICATION FOR UNPLANNED DOCKSIDE REPAIRS
FY2021
Developed By: Joel J. Geist
(Rev-0, 29 September 2020)
Solicitation 70Z080-21-Q-P4504900Attachment 2
USCGC PAUL CLARK (WPC-154) UNPLANNED DOCKSIDE AVAILABILITY FY2021
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .................................................................................. v Consolidated List of Critical Inspection Items ............................................................................................. vi Principal Characteristics ............................................................................................................................. vii General Requirements WORK ITEM 1: Main Diesel Engine(s), Renew iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 154WPC 085-201 Rev A, Propulsion System, SSDG, EDG Installation Drawings Coast Guard Drawing 154WPC 151-301 Rev E, Scantlings Superstructure Coast Guard Drawing 154WPC 200-301 Rev -, Machinery Arrangement Drawings Coast Guard Drawing 154WPC 204-301 Rev F, Equipment Removal Plan
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors
Manual Coast Guard Technical Publication (TP) 8019A, SWBS 233, Aug 2019, Main Propulsion Diesel Engine
(MDE), MTU 20V4000M93L (154 WPC A & B-Class Cutters) Coast Guard Technical Publication (TP) 8902B, SWBS 233, Oct 2019, Technical Repair Standard For
Use On Fast Response Cutters (FRC-B) Main Propulsion Diesel Engine Model MTU 20V4000M93L (154 WPC A & B-Class Cutters)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None v (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
1 Y FRC MDE NIIN: 0C 2815-12-392-7931 2 $1,861,153.95
1 N FRC MDE Container NIIN: 8145-01-F13-3476 2 $47,857.63 1 Y Spreader Bar, Main
Engine
NIIN: 01-F18-5444 1 $50,000.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter
USCGC PAUL CLARK (WPC-154) UNPLANNED DOCKSIDE AVAILABILITY FY2020
vi (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
This section is not applicable to this package.
vii (Rev-0)
PRINCIPAL CHARACTERISTICS
154' WPC (SENTINEL CLASS)
PHYSICAL
Anchor ROCNA, anchor, 150 KG/ 331 LB, Stainless Steel Bulkheads (7), Watertight Bulkheads located below the Main Deck Displacement, delivery, light ship 302 Metric Tons Draft, full load 2.58 Meters (8.46 Feet) End of service life displacement 353 Metric Tons Framing Longitudinal Full load displacement 353 Metric Tons Height of highest projection 17.22 Meters (56.5 Feet) Length overall (loa) 46.80 Meters (153.5 Feet) Maximum beam 7.75 Meters (25.43 Feet) Minimum operating displacement 314 Metric Tons Waterline length (lwl) 44.35 Meters (145.5 Feet)
HULL
Hull/main weatherdeck material AH-36 Steel Superstructure 5456-H1111 Aluminum
MACHINERY
Bow thruster Schottel STT 60 LK Diameter of propeller 1900 mm Emergency service generator (edg) Cummins 6BTA5.9-DM Diesel with Stanford 93KW Generator Fin stabilizer (2), Quantum QC1500 Main propulsion (2), MTU 20V4000 M93L, Sequential Turbo-Charged Diesels Number of blades 6 Number of propellers (2) Michigan Wheel Marine Propeller pitch capability Fixed Propulsion shafts (2), Electralloy Nitronic 50HS (9430mm) Shafts Reduction gears (2), ZF 23560C/D Series Rudders (2), 316L Stainless Steel Shaft rotations per minute 478 Shaft(s) bearing, aft (2), Duramax Bearings Shaft(s) bearing, intermediate (2), Duramax Bearings Shaft(s) diameter 8 Inches Shaft(s) Seal (2), Wartsila Mechanical Seals Ship service generators (2), Cummins QSM11-DM Diesels with Stanford 317KW Generator
TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)
Fresh water tank, port (3-38-2-w) 708 gal Fresh water tank, stbd (3-38-1-w) 756 gal Fuel oil edg day tank (1-10-1-f) 134 gal Fuel oil gen. ovrflw tnk, ctr. (3-40-0-f) 1,159 gal Fuel oil overflow tank, center (3-10-0-f)
616 gal
Fuel oil service tank, #1 port (3-17-2-f) 1,750 gal Fuel oil service tank, #1 stbd (3-17-1-f) 1,750 gal Fuel oil service tank, #2 port (3-40-2-f) 890 gal Fuel oil service tank, #2 stbd (3-40-1-f) 890 gal Fuel oil storage tank, #1 center (3-11-0- 5,040 gal viii (Rev-0)
f) Fuel oil storage tank, #2 center (3-23-0-f)
5,350 gal
TANK CAPACITIES AT 95% LIQUID LOAD (22,958 TOTAL GALLONS)
Grey water tank, (3-17-0-w) 2,668 gal.
Lube oil storage tank, (2-35-2-f) 146 gal.
Oily water tank, (3-34-1-w) 336 gal.
Sewage collection tank, (3-6-0-w) 429 gal.
Waste oil tank, (3-34-2-f) 336 gal.
1 (Rev-0)
00000_0220_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2018, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.
3.2 Contractor-provided fire extinguishers. The Contractor shall provide portable fire extinguishers.
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3 (Rev-0)
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;
ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. None.
3.7 SFLC Standard Specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2018 Edition Standard Specifications and supersede published content:
None.
4 (Rev-0)
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
7 (Rev-0)
QA-3A - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
8 (Rev-0)
QA-3B - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-1/NACE WJ-1
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP WJ-3/NACE WJ-3
SSPC-SP WJ-4/NACE WJ-4
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading (mils)
Mean Reading (mils) IAW ASTM DD4417).
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
COATING MFG PRODUCT NAME BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
1 AVG. BMR DEVIATION
1 AVG. BMR DEVIATION
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
20000_JLW_0818_154WPC
WORK ITEM 1: Main Diesel Engine(s), Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew both Main Diesel Engines.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN
QTY ESTIMATED
COST
($/UNIT)
Y FRC MDE NIIN: 0C 2815-12-392-7931 2 $1,861,153.95
N FRC MDE Container NIIN: 8145-01-F13-3476 2 $47,857.63 Y Spreader Bar, Main Engine NIIN: 01-F18-5444 1 $50,000.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 154WPC 085-201 Rev A, Propulsion System, SSDG, EDG Installation
Drawings Coast Guard Drawing 154WPC 151-301 Rev E, Scantlings Superstructure Coast Guard Drawing 154WPC 200-301 Rev -, Machinery Arrangement Drawings Coast Guard Drawing 154WPC 204-301 Rev F, Equipment Removal Plan
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 8019A, SWBS 233, Aug 2019, Main Propulsion Diesel
Engine (MDE), MTU 20V4000M93L (154 WPC A & B-Class Cutters) Coast Guard Technical Publication (TP) 8902B, SWBS 233, Oct 2019, Technical Repair
Standard For Use On Fast Response Cutters (FRC-B) Main Propulsion Diesel Engine Model MTU 20V4000M93L (154 WPC A & B-Class Cutters)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2018, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2018, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor shall refer to TP-8019A, TP-8902B and Coast Guard Drawings 154WPC 085-201, 154WPC 200-301, 154WPC 204-301 to accomplish the following tasks.
3.1.1 CIR.
None.
3.1.2 Tech Rep. The Contractor shall provide onsite at least one QL3 certified technician on MTU4000 series engines. The technician shall possess a 1B dongle, have certification on ECU-7 series governors, and the Contractor shall have 20V4000 engine maintenance experience.
3.1.2.1 Most current technical documentation. Prior to starting work, the QL3 certified technician shall obtain from the OEM (MTU) the most current versions of the MTU documents contained within TP- 8019A (e.g. service manuals, bulletins, etc.) and abide by requirements in those current documents. After the overhauled/repaired engines have been accepted satisfactory by the Coast Guard, turn over all new versions of documents to the Coast Guard.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.1.5 Removal and Reinstallation Plan. In conjunction with, and incorporated into, the submission of the PD per paragraph 3.5.2 of SFLC STD SPEC 0000, prepare and submit detailed removal and reinstallation plans that contain the following. After the final version of the PD is approved by the Coast Guard work may commence.
• An “Interference Removal/Reinstallation and Access Cut Plan” containing a list of items that will be removed as interferences. Describe measures that will be taken to prevent contamination/water/etc. from entering the cutter, and measures that will ensure ship’s structure will not deform after removal of the WERP plates. Describe the control welding techniques that will be used to ensure the WERP plates and adjacent structure will not be warped or damaged, and that final weldment will not crack.
• A “Cutter Stability Plan” containing a description of measures that will be taken to ensure the stability characteristics described below in para 3.5.3.1 Maintain cutter stability parameters are maintained.
• A “Rigging Plan” containing type and rating of crane and a step-by-step description of the rigging evolution. Describe all lifting appliances (e.g. strong-backs, jigs, etc.) that will be used.
• An “Engine Installation and Alignment Plan” containing a brief description of how the new engines will be reconnected to all disturbed interfaces and how the new engines will be aligned/connected to all hard-points (e.g. reduction-gear flange, inlet/exhaust ppg, water ppg, etc.). Describe how engine feet will be removed and reinstalled onto rails, and to what extent Chock-fast liners will be disturbed and why. Describe what types of alignment jigs, instruments, and tools will be used (e.g. laser, dial indicator, etc.)
• An “Operational Test Plan” containing an outline of all of the procedural steps required to fully prove a satisfactory install of the two new engines.
• A “Preservation Plan for F-Condition Engines” that outlines the steps that will be taken to package, preserve, and seal-off the removed engines
3.1.6 Operational test - initial. Prior to commencement of work, witness Coast Guard personnel perform an operational pre-test of all items and shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Inspect engine room bilge areas to determine extent of failed coatings. Prior to engine renewal submit a CFR that details any required growth repairs identified during the operational test based on the observed condition of the systems.
3.1.7 Inspection/Verification Sign-off Sheet. The Contractor shall print off and maintain the sign-off sheet shown beneath paragraph 4.1 titled “FRC Engine Change Out Inspection/Verification Form” (or create and maintain an equivalent sheet). Immediately after completion of the predecessor task notify the COR/PE of the pending inspection, show and describe to the COR/PE the items requiring inspection and approval, then pending satisfactory inspection by the COR/PE, have the COR/PE sign the sheet to certify satisfactory completion of the task. Proceed with follow-on tasks only after receiving COR/PE witness, approval, and signature. Submit the filled-out sign-off sheet with the final testing CFR (described beneath paragraph 3.2.8) as certification that a Government representative was present for all listed inspections.
3.1.8 Coordinate with MTU Tech Rep funded by other Coast Guard contract. The Coast Guard will provide an MTU tech rep that will assist in the installation of any pending retrofits, be available for start-up, and sea-trials. The Contractor shall coordinate with this tech rep prior to the start of the availability to determine scheduling of engine uncrating, engine rigging date, sea trials, and all other project details.
3.2.1 Base Miami-specific Requirements and Restrictions.
3.2.1.1 Potential Transport of GFP. GFP (e.g. engines, containers, etc.) may require additional handling (e.g. transport from a barge to pier, from elsewhere on the base to the worksite, etc.). If the GFP is not in close proximity to the work site at the start of the availability, the Contractor shall submit a CFR requesting contract modification and additional funding. The KO will release a CR to have the Contractor move the GFP into close proximity of the worksite.
3.2.1.2 Pier and Causeway Weight Restrictions. Loading any one section (ie. bridge section between two caissons) of the causeway leading to Base Miami shall not exceed 64,000 lbs at any one instance, and no single axle shall exceed 32,000 lbs at any one instance (see image below). Base Miami Beach bulkheads are subject to the loading restrictions detailed in the 'waterfront loading' drawing imbedded below. The crane lift of the engines shall be conducted in either Zone 1 or Zone 2. Prior to bringing equipment (e.g.
crane, trucks, etc.) submit a report to the COR listing the weights of the various items/vehicles and do not load the causeway or the piers with equipment without prior approval from the COR.
� g i � � � -� -� � i )s• )\• � .... j ,9 s! ? � � � j i � g * !ii C C z o, I
� • • ., N
�5 i ,::� �� � , -<) " OlN
�o
I o;!;
ll E n � g � ;
C C •
:. •I •
C
�,i§§§
H�-!�
.J T t .J .. ., .: ,l;,f'
��O<">�
��ESS
ll'<llllll �w�rw lHH i :� .
0 {, - I��,,�
0 " ol ·•
N
0 (, �
0 z 6
- ·--1�
;i .� 2; �
I
C
C ll
E ll
I N
;,�n
��2 §! - C t: � �
�-o�B or. c.., !� g� � ,= 0
-r7 a a ., _C3 10-0·
7J ', �
CJ �
' ct:::::IJ 7'f ?
'.b·w0:u �
0 .. ' �
✓'jti � x
• 0�
Jr, .o· -;, c-, SC , ,,,y, z
��8 �::::li'!i - ::u -< z C, C,C
C: ?o zo a t, n
�p o
3.2.1.3 Rotation of vessel to accommodate engine removal. If rotating the vessel is required to facilitate rigging evolutions, the Contractor shall not block the channel leading to the pier, or any other marked waterways, during rotation evolutions. The Contractor shall tow the vessel out to open water to perform the rotation maneuver, spending as little time in any channel as practicable.
3.3 Engine Renewal Requirements. The Contractor shall renew both MDEs by performing and abiding by the following. Refer to TP-8902A, Chapter 2 and Chapter 40 for Shipboard Removal and Installation Requirements.
NOTE
Ship’s Force will perform electrical isolation, tag-out procedures, etc.
Coordinate with Ship’s Force and ensure all of this work is complete prior to performing any maintenance.
Coordinate with Ship’s Force and the COR/PE to schedule pre-engine-removal sea trials for collecting preliminary test data on.
3.3.1 Conduct preliminary inspections and tests. Conduct the preliminary tests specified in TP-8902A, Chapter 2.
3.3.2 Remove interferences and prepare for engine rigging evolution. While removing all interferences, and in conjunction with engine removal/reinstallation, perform the following.
3.3.2.1 Take all necessary precautions to prevent all environmental elements (e.g. rain, birds, dirt, etc.)
from entering the skin of the cutter while the WERP deck plates are removed. This may involve temporary installation of cofferdams around accesses openings, tents/shelters, etc. or other equivalent methods.
3.3.2.2 Maintain cutter stability parameters. Throughout the entire contract 1) maintain, at a minimum, lightship stability conditions, and 2) maintain a list small enough to allow direct vertical rigging of engines out of the ship with no need to apply a significant horizontal force to guide the engines in/out (e.g. pulling/guiding engine with tag lines, pushing engine, etc), refer to TP-8902A, Chapter 2. This will involve installation and adjustment of shoring and weights, or an equivalent method. Main deck loading shall not exceed 1000 lbs per sqft.
3.3.2.3 WERP removal and reinstallation requirements. Maintain the dimensions of the clear opening created after WERPs are removed by install temporary structural members that will prevent all deformation of the superstructure that may occur after removing WERP plates in accordance with the approved “Removal and Reinstallation Plan” (NOTE: Post WERP removal expansion of the clear opening has been noted in the past and shall be prevented.). Coordinate with the COR/PE 24 hours in advance of inspection of the installed temporary structural members and prior to removal of any WERP plate weld joint material, proceed with WERP removal after satisfactory COR/PE inspection of temporary structure. Minimize damage to WERP plate and surrounding structure by only removing existing weld joint material that attaches the WERP plate to the 01 LVL Deck. First saw/grind down into the weld joint approximately 1/8”, then carefully sever the remaining weld (approx 1/16”) using a chisel or equivalent method/tool to release the WERP plate from the 01 LVL Deck. Inspect WERP foundation bar for any damage that will require repairs before final WERP installation. Submit CFR. At reinstallation employ control welding to the greatest practicable extent to ensure no latent defects (e.g. cracks, warping, etc. at a later date).
FIGURE 1. TITLE
3.3.3 Prepare installed intake/exhaust ducts and engines for removal. Prior to disturbing engine intake and exhaust ducts, secure (i.e. “cage”) all spring-loaded expansion joints (e.g. clamp together with turn buckles, etc. or equivalent method) to prevent release from their pre-disassembly dimensions/adjustment and label their locations. Measure and record all exhaust hanger distances prior to disassembly to aid in efficient reassembly and exhaust alignment.
3.3.4 Inspect engine intake ducts and exhaust ducts. Coordinate with the COR/PE 24 hours in advance of the inspection. In the presence of the COR/PE, wipe-down and visually inspect all accessible interior surfaces of all intake and exhaust piping and mufflers. Inspect soot trap. Determine if further disassembly and cleaning is required. Submit a CFR describing findings and any recommended additional cleaning.
3.3.5 Remove old engines, install new engines. Perform the following.
3.3.5.1 Preservation of Removed Engines. Prior to engine removal, both main diesel engines shall be preserved IAW TP-8019A chapter 5.3.2 (Service Interruption of more than 3 months), MTU Preservation and Re-preservation Specifications, A001070/00E. Submit a CFR containing all preservation documentation described in chapter 2.2 (Check sheet for preservation and re-preservation). Ensure all coolant drain lines are opened and all coolant drained from engine.
3.3.5.2 Mark existing alignment adjustments, transfer adjustments to new engines. Coordinate with the COR/PE 24 hours in advance of the inspection. In the presence of the COR/PE, and prior to engine removal, perform the following for efficient install of the new engines:
• Scribe/mark/trace on each existing engine foot liner plate where the engine foot currently rests, then later, at install, place new engines as close as practicable to the marked location.
• Measure and record the “Adjustment Nut Height” of each installed engine foot, then transfer those adjustment dimensions to the feet on the new engines prior to install (ideally while suspended from the crane and immediately after lifting off of shipping crate).
FIGURE 2. TITLE
3.3.5.3 Inspect CHOCKFAST liners for damage (e.g. cracks, deformation, etc.). Coordinate with the COR/PE 24 hours in advance of the inspection. Immediately after the existing engines are removed, and in the presence of the COR/PE, conduct a thorough visual inspection of all 12 CHOCKFAST poured liners installed on the engine bed rails. Verify they have no damage, were originally poured correctly, and can be reused. Submit a CFR detailing the inspection results and describe any additional recommended repairs.
3.3.5.3.1 Determine the flatness of the CHOCKFAST/liner assemblies, relative to one another.
Determine how closely the combination of all of the liners emulates a perfectly flat surface for the engines to rest upon. After each engine has been removed, and using a proper planar “datum feature” (e.g. 3 points on one of the liners defining a plane, etc.), determine 4 offset dimensions from that plane for each liner. Each offset dimension shall be measured from a points within 1” of a different corner on the liner (4 offset dimensions per liner). Submit a CFR detailing the inspection results and describe any additional recommended repairs.
3.3.5.4 Record existing engine flange to RG flange alignment readings. Coordinate with the COR/PE 24 hours in advance of the inspection, and after removing engine to RG coupling and obtaining alignment instrument readings, show those instrument readings to the COR/PE. Submit CFR.
NOTE
As of this writing, bilge coating condition does not warrant mandatory QP1 Certification or Independent NACE inspector. If, at the start of the contract performance period, bilge coating condition deteriorates past the thresholds specified in SFLC STD SPEC 6310 and SFLC STD SPEC 0000, these requirements will be invoked and additional associated preservation costs will be compensated by contract mod if necessary.
3.3.5.5 Clean and touch-up preserve bilges beneath engines. Clean and pressure wash all engine room bilge surfaces to remove all loose contaminates and dirt. Submit a CFR describing the condition of bilge coatings and all discrepancies (e.g. failed coatings, rust, etc.), note all coating discrepancies in excess of 20 sqft total. Coordinate with the COR/PE 24 hours in advance of the inspection, and have the COR/PE inspect all preparation work prior to coating application. Touch-up preserve up to 10 sqft of failed or damaged bilge coating beneath the STBD engine and up to 10 sqft of failed or damaged bilge coating beneath the PORT engine (i.e. include in pre-award quote), and apply one topcoat, up to 5mils, over all intact bilge surfaces. Additional coatings repairs will be authorized/funded by CR/mod to the contract.
See paragraph 3.2.11.1 below for coatings requirements.
3.3.5.6 Renewals. In addition to the Government-furnished engines, renew the following components
• All disturbed soft parts (e.g. seals, gaskets, o-rings, etc.).
• All engine fluids (e.g. jacket water, oil, etc.)
• All exhaust hanger rubber grommets.
• Insulation Blankets covering the Exhaust Silencer only (do not renew blankets covering the exhaust pipe leading to and from the Exhaust Silencer, retain and reuse those blankets).
• All disturbed hardware and fasteners (e.g. nuts, bolts, washers, studs, etc.).
• All flex hoses and expansion joints leading to and from each engine.
• The ASW expansion joint leading to the RG.
• The ASW hose leading to R/G from the jacket water cooler.
• All exhaust pipe gaskets.
3.3.5.7 Align new engines to existing reduction gearboxes. Align the engine output flanges to the reduction gear flanges in accordance with Coast Guard Drawing 154WPC 085-201. Coordinate with the COR/PE 24 hours in advance of the inspection, and after completing the final alignment adjustments and obtaining satisfactory alignment instrument readings, show those instrument readings to the COR/PE.
Submit CFR.
3.3.6 Repackage and ship removed engines. Place the preserved F-condition MDEs into the new Government-furnished MDE containers reusing the foil bag from the “A” condition engine and accomplish the following:
3.3.6.1 Ensure all preserved F-condition MDE valves are closed.
3.3.6.2 Seal off all electrical sockets with a waterproof adhesive tape. Blank all openings and flanged connections over 3 inches diameter with wooden flanges, sealed with adhesive tape. All other openings (e.g. tapped holes, etc.) shall be blanked with plastic or metal caps and waterproof adhesive tape.
3.3.6.3 Install all retained engine support components to facilitate safe engines transport. Renew all disturbed fasteners.
3.3.6.4 Return the crankshaft locking devices (provided on "A" condition engine) with the F-condition engines.
3.3.6.5 Install shipping blanks from A-condition engines (turbos, water inlets/outlets, etc) on F-condition engines.
NOTE
Ensure any parts /assemblies removed for trouble shooting or failure analysis are reinstalled on F-condition engines.
3.3.6.6 Mark the serial numbers on the new Government-furnished containers to reflect the appropriate "F" condition engine serial numbers. Mark the containers condition codes to “F”. Ensure the F-condition engines and containers are protected from weather if left outside.
3.3.6.7 Attach the following labels to the removed engines, ensuring that they are in a prominent position, stating:
• “NO OIL OR WATER, DO NOT TURN!”
• “ENGINE REMOVED FROM SERVICE – Date__________”.
3.3.6.8 Notify the COR/PE at least 24 hours prior to closing shipping containers, then show the COR/PE that all paragraph 3.2.6 requirements have been met, then close the containers. Turn over crated engines as MTI items. Dispose of the old shipping crates.
3.3.7 Restore interferences, remove all temporary installations. Restore all interferences, repair all damage incurred in conjunction with maintenance actions performed during this contract. Perform and/or abide by the following:
3.3.7.1 WERP Reinstallation and testing. Notify the COR/PE at least 24 hours prior to weld joint inspections and tests. After WERPs are reinstalled, in the presence of the COR/PE, perform weld joint testing in accordance with SFLC STD SPEC 0740 on 100% of the weld joint areas that seal the WERP plate to the 01 LVL deck. Submit CFR with NDT results.
3.3.7.2 Touch-up preservation requirements. Prepare and coat exterior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems) or Appendix B (Cutter and Boat Interior Painting Systems), and SFLC Std Spec 0000.
Abide by the exception cited below.
3.3.7.3 Insulation repairs. In conjunction with reinstallation, repair all damage to disturbed bulkhead insulation (e.g. damaged perforated sheathing pieces, damaged insulation, etc.) by renewing appropriate sectional areas.
3.3.8 Conduct final grooming, inspections, and tests.
3.3.8.1 Engine Sea-Trial Testing. Perform all testing specified in TP-8902A Volume 2 and record all associated data. Perform a minimum 4-hour long sea trial and download ECU7 sea trail data, run for a minimum of 3 hours at full speed. Take post-sea-trial, lube oil, coolant, and fuel oil samples and obtain lab test results for submission.
3.3.8.2 Exhaust blanket thermograph survey. During the sea trial, after the engines and exhaust reach a maximum and steady state temperature (after the full-speed/full-power run), conduct an infrared thermographic survey of the entire exhaust blanket assembly on both engines in the presence of the COR/PE. Use an instrument that captures digital thermographic images, and ensure that images of all blanket surfaces have been recorded. Submit these digital images of all surfaces at steady-state temp with the final report. Ensure that no exhaust blanket areas/seams exceed 550 deg F and that all gaps between blanket seams are covered.
3.3.8.3 Final Report. Submit final CFR containing all test results/data and the “FRC Engine Change-out Inspection/Verification Form” below with all completed signatures.
4. NOTES
4.1 Inspection forms.
FRC ENGINE CHANGE-OUT INSPECTION/VERIFICATION FORM
1A. PARAGRAPH 3.2.2.3: TEMP STRUCTURE INSTALLED SATISFACTORILY, REMOVAL OF PORT WERP
PLATE MAY COMMENCE.
Contractor Name Signature Date COR/PE Name Signature Date
1B. PARAGRAPH 3.2.2.3: TEMP STRUCTURE INSTALLED SATISFACTORILY, REMOVAL OF STBD WERP
PLATE MAY COMMENCE.
Contractor Name Signature Date COR/PE Name Signature Date
2A. PARAGRAPH 3.2.4: PORT INTAKE/EXHAUST DUCT AND MUFFLER INSPECTION COMPLETED,
ASSOCIATED CFR ACCURATE.
Contractor Name Signature Date COR/PE Name Signature Date
2B. PARAGRAPH 3.2.4: STBD INTAKE/EXHAUST DUCT AND MUFFLER INSPECTION COMPLETED,
ASSOCIATED CFR ACCURATE.
Contractor Name Signature Date COR/PE Name Signature Date 3A. PARAGRAPH 3.2.5.1: PORT LINER/FEET MARKING, ADJUSTMENT MEASUREMENTS, AND TRANSFER
OF ADJUSTMENT TO NEW ENGINE FEET SATISFACTORILY COMPLETED.
Contractor Name Signature Date COR/PE Name Signature Date 3B. PARAGRAPH 3.2.5.1: STBD LINER/FEET MARKING, ADJUSTMENT MEASUREMENTS, AND TRANSFER
OF ADJUSTMENT TO NEW ENGINE FEET SATISFACTORILY COMPLETED.
Contractor Name Signature Date COR/PE Name Signature Date
4A. PARAGRAPH 3.2.5.2: PORT CHOCKFAST LINERS EITHER SAT, OR RENEWAL PLAN ACCURATELY
DESCRIBED AND APPROVED BY CFR.
Contractor Name Signature Date COR/PE Name Signature Date
4B. PARAGRAPH 3.2.5.2: STBD CHOCKFAST LINERS EITHER SAT, OR RENEWAL PLAN ACCURATELY
DESCRIBED AND APPROVED BY CFR.
Contractor Name Signature Date COR/PE Name Signature Date
5A. PARAGRAPH 3.2.5.3: PORT ENGINE EXISTING ALIGNMENT READINGS, RECORD DIMENSIONS
BELOW.
Actual Flange-to-Flange Dimension: Actual Radial Dimension: Actual Face Dimension Contractor Name Signature Date COR/PE Name Signature Date
5B. PARAGRAPH 3.2.5.3: STBD ENGINE EXISTING ALIGNMENT READINGS, RECORD DIMENSIONS
BELOW.
Actual Flange-to-Flange Dimension: Actual Radial Dimension: Actual Face Dimension Contractor Name Signature Date COR/PE Name Signature Date
6A. PARAGRAPH 3.2.5.4: SAT INSPECTION OF PORT BILGE PREP WORK PRIOR TO COATINGS
APPLICATION.
Contractor Name Signature Date COR/PE Name Signature Date
6B. PARAGRAPH 3.2.5.4: SAT INSPECTION OF STBD BILGE PREP WORK PRIOR TO COATINGS
APPLICATION.
Contractor Name Signature Date COR/PE Name Signature Date 7A. PARAGRAPH 3.2.5.6: PORT ENGINE ALIGNMENT READINGS ARE SAT, RECORD DIMENSIONS BELOW.
Actual Flange-to-Flange Dimension: Actual Radial Dimension: Actual Face Dimension Contractor Name Signature Date
COR/PE Name Signature Date 7B. PARAGRAPH 3.2.5.6: STBD ENGINE ALIGNMENT READINGS ARE SAT, RECORD DIMENSIONS BELOW.
Actual Flange-to-Flange Dimension: Actual Radial Dimension: Actual Face Dimension Contractor Name Signature Date COR/PE Name Signature Date
8. PARAGRAPH 3.2.6.9: BOTH F-CONDITION ENGINES HAVE CRATED IN ACCORDANCE WITH ALL
PACKAGING REQUIREMENTS.
Contractor Name Signature Date COR/PE Name Signature Date
9. PARAGRAPH 3.2.7.1: 100% OF WELD JOINT CONNECTING WERP PLATES TO THE 01 LVL DECK
VISUALLY INSPECTED AND NDTED SAT.
Contractor Name Signature Date COR/PE Name Signature Date
10. PARAGRAPH 3.2.8.1: EXHAUST BLANKETS INSTALLED PROPERLY AND SATISFACTORILY, JOINTS
BETWEEN BLANKET SECTIONS DO NOT LEAK HEAT…