Attachment 2 – Statement of Work (SOW) Supply and Delivery of #2 crushed run gravel for the Montezuma National Wildlife Refuge
1.0 Background
The U.S. Fish and Wildlife Service Montezuma National Wildlife Refuge (Refuge) located at 3395 US Route 20 East, Seneca Falls, NY 13148 has a 3.5 mile Wildlife Drive that is the main roadway through the Refuge. The Refuge is in the process of rebuilding the Wildlife Drive to comply with our CCP determinations, as well as accomplishing the normal annual maintenance needed before the Wildlife Drive is open for the season.
2.0 Scope
The Refuge expects to use approximately 1,800 tons of material for our Wildlife Drive Rehab Project. The Contractor shall deliver to the Refuge #2 Crusher Run gravel on an as-needed basis. The Contractor shall supply and deliver the crusher run gravel and supply all labor including CDL drivers, transport vehicles, and vehicle permits as may be required.
3.0 Period of Performance
The Performance Period of this BPA shall be as follows:
Performance Period
Year 1: Date of award through 05/02/2022
Year 2: 05/03/2022 through 05/02/2023
Year 3: 05/03/2023 through 05/02/2024
Year 4: 05/03/2024 through 05/02/2025
Year 5: 05/03/2025 through 05/02/2026
3.1 Hours of Operations
Delivery shall be during regular business hours which are as 7:00 a.m. to 5:30 p.m. Monday thru Friday except recognized Federal holidays.