Attachment 2 Statement of Work - 1240LU23R0018 Forest-wide toilet decommission.doc

DOC document 66 KB Posted

Attached to
Forest-wide toilet decommission Federal contract opportunity
Solicitation number
1240LU23R0018
Issued by
Department of Agriculture Forest Service

About this file

This statement of work outlines a forest-wide toilet decommissioning and installation project for the Department of Agriculture Forest Service. The project involves replacing nine existing toilets with five accessible concrete vaults and four wood frame vault toilets, and decommissioning three existing wood frame vault toilets, across twelve sites. Work will include removing existing toilet structures, filling pits, installing new toilets, and site restoration. Prices range from $250,000 to $500,000 and work is estimated to begin on September 18, 2023 through October 31, 2024. The statement of work provides detailed requirements for removal and installation work at each site location.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

PROJECT:

FORESTWIDE TOILET DECOMMISSIONING AND INSTALLATION PROJECT

C-1 - PROJECT DESCRIPTION AND LOCATION

DESCRIPTION OF WORK.

A. General

Project work will vary site by site, but the following work items will be included in the overall project: Replace (9) existing toilets with (5) accessible concrete vaults and (4) wood frame vault toilets. Decommission (3) existing wood frame vault toilets.

SITE #
SITE NAME
REMOVAL TYPE
REPLACEMENT TYPE
PUMPING REQUIRED
1
Tukaytespe Picnic Area
Concrete Vault
Concrete Vault
Yes
2
Coolwater Ridge
Wood Vault
Concrete Vault
Yes
3
Lookout Butte
Wood Pit
Wood Vault
No
4
Castle Butte
Wood Pit
Wood Vault
No
5
Weitas Meadow Camp
Wood Pit
Decom only
No
6
Elk Mountain Trailhead
Wood Pit
Decom only
No
7
Pete Forks Junction
Wood Pit
Decom only
No
8
Five Mile Pond
Wood Vault
Concrete Vault
Yes
9
Weitas Guard Station
Wood Pit
Wood Vault
No
10
Sherman Creek
Wood Pit
Concrete Vault
No
11
Split Creek
Wood Pit
Concrete Vault
No
12
Tom Beal
Wood Pit
Wood Vault
No

Work Description by Site:

1. Tukaytespe Picnic Area - Work includes removal of the existing concrete vault toilet structure, removal of any concrete materials, cutting the edge of the asphalt pavement and removal of any other materials so a new toilet can be delivered and placed in the same location. Work would include pumping the existing toilet unit of any waste materials prior to removing the vault; dismantling and removing the concrete single vault toilet unit; installing erosion control, preparing the excavation area for the new vault toilet including a level subgrade; supplying the new concrete vault toilet and finally backfilling and finishing site work after the new concrete vault toilet is delivered to the site. Final vault installation work shall include any required excavation work to accommodate the new unit, setting the new unit, backfilling after the unit is set, and construction of gravel apron and concrete entrance pad. When all installation work is complete, remove erosion control, repair or replace asphalt transition and final dressing of site to remove evidence of excavation work.

2. Coolwater Ridge - Work includes removal of the existing wood frame toilet structure and any other materials so a new toilet can be placed. Work would include pumping the existing toilet unit of any waste materials prior to removing the vault; dismantling and removing the wooden single vault toilet unit; preparing the excavation area for the new concrete vault toilet; supplying the new concrete vault toilet; and finally backfilling and finishing site work after the vault toilet is delivered to the site. Final vault installation work shall include any required excavation work to accommodate the new unit, setting the new concrete vault toilet, backfilling after the unit is set, and construction of gravel apron and concrete entrance pad. When all installation work is complete, final dressing of site to remove evidence of excavation work must be completed.

3. Lookout Butte - Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a legal manner off Forest Service lands. The pit shall be filled with soil that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final dressing of site to remove evidence of excavation work must be completed. New wood frame toilet installation would include preparing the excavation area for the new wood frame vault toilet; constructing the new wood frame vault toilet; and finally backfilling and finishing site work after the vault toilet is constructed on the site. Final vault installation work shall include any required excavation work to accommodate the new unit, construction of new wood frame vault toilet, backfilling, and construction of gravel apron and concrete entrance pad. When all installation work is complete, final dressing of site to remove evidence of excavation work must be completed.

4. Castle Butte - Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a legal manner off of Forest Service lands. The pit shall be filled with soil that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final dressing of site to remove evidence of excavation work must be completed. New wood frame toilet installation would include preparing the excavation area for the new wood frame vault toilet; constructing the new wood frame vault toilet; and finally backfilling and finishing site work after the vault toilet is constructed on the site. Final vault installation work shall include any required excavation work to accommodate the new unit, construction of new wood frame vault toilet, backfilling, and construction of gravel apron and concrete entrance pad. When all installation work is complete, final dressing of site to remove evidence of excavation work must be completed.

5. Weitas Meadow Camp -Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a legal manner off or Forest Service lands. The pit shall be filled with imported fill that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final hand dressing of site to remove evidence of excavation work must be completed.

6. Elk Mountain Trailhead - Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a landfill. The pit shall be filled with imported soil that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final hand dressing of site to remove evidence of excavation work must be completed.

7. Pete Forks Junction - Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a Legal manner off of Forest Service lands. The pit shall be filled with imported material that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final hand dressing of site to remove evidence of excavation work must be completed.

8. Five Mile Pond (Optional Item) - Work includes removal of the existing wood frame vault toilet structure and any other materials so a new toilet can be delivered and placed in the hole. Work would include dismantling and removing the wooden single vault toilet unit; installing erosion control, preparing the excavation area for the new concrete vault toilet; setting the new concrete vault toilet, and finally backfilling and finishing site work after the new concrete vault toilet is delivered to the site. Final vault installation work shall include any required excavation work to accommodate the new unit, setting the new concrete vault, backfilling after the unit is set, and construction of gravel apron and concrete entrance pad. When all installation work is complete, remove erosion control, complete final dressing of site to remove evidence of excavation work must be completed.

9. Weitas Guard Station (Optional Item) - Work includes removal of the existing wood frame vault toilet structure and any other materials and filling of the existing hole. The new toilet will be placed in a new location. Work would include dismantling and removing the wooden single vault toilet unit; preparing the excavation area for the new wood frame vault toilet; constructing the new wood frame vault toilet; and finally backfilling and finishing site work after the vault toilet is constructed on the site. Final vault installation work shall include any required excavation work to accommodate the new unit, construction of new wood frame vault toilet, backfilling, and construction of gravel apron and concrete entrance pad. When all installation work is complete, final dressing of site to remove evidence of excavation work must be completed.

10. Sherman Creek (Optional Item) - Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a legal manner off of Forest Service lands. The pit shall be filled with soil that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final dressing of site to remove evidence of excavation work must be completed. Preparing the excavation area for the new vault toilet including a level subgrade; installing erosion control, supplying the new concrete vault toilet and finally backfilling and finishing site work after the concrete vault toilet is delivered to the site. Final vault installation work shall include any required excavation work to accommodate the new unit, setting the new unit, backfilling after the unit is set, and construction of gravel apron and concrete entrance pad. When all installation work is complete, remove erosion control, and complete final dressing of site to remove evidence of excavation work.

11. Split Creek (Optional Item) - Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a legal manner off of Forest Service lands. The pit shall be filled with soil that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final dressing of site to remove evidence of excavation work must be completed. Preparing the excavation area for the new vault toilet including a level subgrade; installing erosion control, supplying the new concrete vault toilet and finally backfilling and finishing site work after the concrete vault toilet is delivered to the site. Final vault installation work shall include any required excavation work to accommodate the new unit, setting the new unit, backfilling after the unit is set, and construction of gravel apron and concrete entrance pad. When all installation work is complete, remove erosion control, and complete final dressing of site to remove evidence of excavation work.

12. Tom Beal (Optional Item) - Work includes removal of the existing wood frame pit toilet structure and any other materials associated with the existing toilet. The privy building should be dismantled and the portions of the building that may have come into contact with human sewage should be disposed of in a legal manner off of Forest Service lands. The pit shall be filled with soil that is free of rock and graded to allow for about 12 inches of settling. The site should be marked and protected from traffic or excavation activities. When all decommission work is complete, final dressing of site to remove evidence of excavation work must be completed. New wood frame toilet installation would include preparing the excavation area for the new wood frame vault toilet; constructing the new wood frame vault toilet; and finally backfilling and finishing site work after the vault toilet is constructed on the site. Final vault installation work shall include any required excavation work to accommodate the new unit, construction of new wood frame vault toilet, backfilling, and construction of gravel apron and concrete entrance pad. When all installation work is complete, final dressing of site to remove evidence of excavation work must be completed.

Price Range. $250,000 - $500,000 Site Tour. No site tour is planned.

Start Work. It is estimated that work will begin on September 18, 2023.

Period of Performance. September 18, 2023 – October 31, 2024

C-2 - GOVERNMENT FURNISHED PROPERTY

a. No Government furnished property is provided for this project.

File details come from the government source that posted it. Updated .