Attachment 2 - Statement of Project Objectives - Template.docx
DOCX document 36 KB Posted
- Opportunity number
- DE-FOA-0003446
About this file
This is a Statement of Project Objectives (SOPO) template document provided as Attachment 2 for the HARMONY FOA (DE-FOA-0003446) from the Department of Energy's National Energy Technology Lab. The template outlines the required structure for applicants to detail their project execution plans, including objectives, scope of work, tasks, deliverables, and briefing requirements.
The template requires specific mandatory elements including Project Management (Task 1.0) with subtasks covering Project Management Plan, Data Management Plan, Cybersecurity Plan (due 30 days after award), and Technology Protection Plan (due 60 days after award). The SOPO must be organized into research/development (Phase 1) and field test/demonstration (Phase 2) sections, with clearly defined go/no-go decision points between phases. All work must support the HARMONY program's goal of enhancing grid reliability and resilience through human-centric analytics. The template specifies that the completed SOPO should be less than 5 pages and must not contain proprietary information since it may be publicly released by DOE after award.
Attachment 2 - Statement of Project Objectives - Template
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FundOpp_DE-FOA-0003446_Amd_000002.pdf | ||
| Budget-Justification-NETL-26-01.xlsx | XLSX spreadsheet | |
| Location(s)_of_Work.xlsx | XLSX spreadsheet | |
| NOFO 3446 Part 2 HARMONY 2026-01-14.pdf | ||
| FundOpp_DE-FOA-0003446_Amd_000001.pdf | ||
| Attachment 1 -NOFO Part 2_NETL.docx | DOCX document | |
| Attachment 3 - Project Management Plan Template.docx | DOCX document | |
| Attachment 5 - NOFO Technical Volume Cover Page.docx | DOCX document | |
| Attachment 4 - Budget-Justification-Worksheet-3-BPs.xlsx | XLSX spreadsheet | |
| FundOpp_DE-FOA-0003446.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 2 – SOPO TEMPLATE Modification 000001
Statement of Project Objectives (SOPO): The Project Narrative must include a detailed SOPO that addresses how the project objectives will be met. The SOPO must contain a clear, concise description of all activities that will be completed during project performance and follow the structure/format outlined below. Since the SOPO may be released (in whole or in part) to the public by DOE after award, it shall not contain proprietary or confidential business information.
The SOPO generally consists of less than five (5) pages to describe the proposed work. Since the SOPO is part of the Project Narrative, the number of pages must be included within the Project Narrative page limit. Applicants shall prepare the SOPO according to the following format.
Italicized text in the following template is provided as guidance and should be removed by the Applicant when preparing their SOPO. All other text is intended to be included in the Applicant’s proposed SOPO.
[*****BEGININNING OF SOPO TEMPLATE*****]
STATEMENT OF PROJECT OBJECTIVES (SOPO)
Insert Project Title
A. OBJECTIVES
Clearly and concisely describe the objective(s) of the project. If the project includes multiple phases of work, describe the objective(s) for each phase. This section should not exceed one-half page.
B. SCOPE OF WORK
Summarize the planned effort and approach to achieve the proposed objectives (including each phase if applicable). This section should not exceed one-half page.
C. TASKS TO BE PERFORMED
Include clear and concise tasks and subtasks (if needed) organized in a logical sequence. Group the tasks and subtasks into corresponding phases, if applicable. If the project contains any go/no-go decision points, define the criteria used to demonstrate meaningful and measurable technical progress and provide the data needed to justify continuing the project.
Task 1.0 - Project Management and Planning (Phases 1 and 2) (REQUIRED; APPLICANT INSERT TASK 1.0 AND ALL SUBTASKS)
Subtask 1.1 – Project Management Within 30 days of award, the Recipient shall revise the version of the Project Management Plan (PMP) that was submitted with their application by including details from the award negotiation process and through consultation with the Federal Project Officer (FPO). The PMP shall include all phases of the project. The Recipient shall not proceed beyond Task 1.0 until the updated PMP has been accepted by the FPO.
The PMP shall be revised and resubmitted as often as necessary to capture any major/significant changes to the planned approach, budget, key personnel, major resources, etc.
The Recipient shall manage and direct the project in accordance with the approved Project Management Plan to meet all technical, schedule and budget objectives and requirements. The Recipient will coordinate activities to effectively accomplish the work. The Recipient will ensure that project plans, results, and decisions are appropriately documented, and project reporting and briefing requirements are satisfied.
Subtask 1.2 – Data Management Plan The Recipient shall maintain the Data Management Plan (DMP) that was incorporated into the award during the negotiation process. The Recipient shall manage the generation/gathering, storage/preservation and sharing/dissemination of project data in accordance with the DMP. If needed, updates to the DMP must be negotiated and, if accepted, changes will be incorporated into the award/attachment.
Subtask 1.3 – Cybersecurity Plan The Recipient must submit a cybersecurity plan within 30 days of receiving the award. The plan is intended to foster a cybersecurity-by-design approach for DOE efforts. This plan to ensures effective integration and coordination across its research, development, and demonstration programs. If needed, updates to the Cybersecurity Plan must be negotiated and, if accepted, changes will be incorporated into the award/attachment.
Subtask 1.4 – Technology Protection Plan The Recipient must submit a Technology Protection Plan within 60 days of award setting out the Recipient’s policies and procedures for identifying, accessing, handling, controlling, and releasing the following: (1) Recipient’s proprietary information, including non-public technical information, trade secrets and other confidential business information, including but not limited to information, know-how, methods or processes that give the Recipient a competitive advantage in the marketplace; (2) information that is subject to U.S. export control laws or regulations; (3) information that has been designated as classified or controlled unclassified information (CUI) by DOE; (4) any other information designated by DOE as sensitive throughout the period of performance. The Recipient must meet the stated objectives set forth in its Technology Protection Plan and notify the Federal Project Officer of any revisions to the Technology Protection Plan or the proposed security approach.
Include additional tasks and subtasks as appropriate using the following format.
Research and Development (Phase 1)
Task 2.0 – (State title of task and provide description)
Subtask 2.1 - (State title of subtask and provide description)
Task 3.0 - (State title of task and provide description)
Task x.0 - (State title of task and provide description)
Go/No-Go Decision Point: The Go/No-Go Decision will be based on the completion of Phase 1 tasks and the submission of associated deliverables [Multiple Decision Points may be added as needed based on the completion of major tasks and/or project milestones]. The Recipient will not begin the next phase until receiving written authorization from the DOE Contracting Officer (CO) to proceed. Written authorization can be in the form of email or letter issued by the CO.
Field Test/Demonstration (Phase 2)
(PHASE 2 MUST INCLUDE TASKS FOR “DEVELOP TEST PLAN” AND “EXECUTE TEST PLAN”)
Task x.0 - (State title of task and provide description)
Task x.0 - Develop Test Plan – (provide description)
Task x.0 - Execute Test Plan – (provide description)
Task x.0 - (State title of task and provide description)
D. DELIVERABLES
The Recipient shall include a list of deliverables that will be submitted during the project.
Subtask 1.1 – Project Management Plan - Update due 30 days after award. Revisions to the PMP shall be submitted as needed or as requested by the NETL FPO.
Subtask 1.3 – Cybersecurity Plan - Due within 30 days after award.
Subtask 1.4 – Technology Protection Plan - Due within 60 days after award.
List additional deliverables as appropriate.
In addition to the deliverables listed above, the Recipient shall submit all periodic, topical, final, and other reports in accordance with the Federal Assistance Reporting Checklist and accompanying instructions.
E. BRIEFINGS/TECHNICAL PRESENTATIONS
The Recipient shall prepare, and present joint periodic briefings with the teams setup under the NOFO, technical presentations and demonstrations as requested by the Federal Project Officer, which may be held at a DOE or Recipient’s facility, other mutually agreeable location, or via webinar. These may include all or a combination of the following:
Kickoff Briefing - Not more than 30 days after submission of the updated Project Management Plan, the Recipient shall prepare and present a project summary briefing as part of a Project Kickoff Meeting.
Go/No-Go Decision Point Briefing - Not less than 90 days prior to the planned start of a new phase, the Recipient shall brief the DOE on the results to date, and their plans for the subsequent phase(s) of work. The DOE will consider the information from this briefing, as well as the content of deliverables submitted to date, prior to authorizing continuing the project.
Final Project Briefing - Not less than 30 days prior to the end of the project, the Recipient shall prepare and present a Final Project Briefing on the results and accomplishments of the entire project.
Other Briefings – The Recipient shall prepare and present technical, financial, and/or administrative briefings as requested by the DOE. Additionally, the DOE may require Recipients to make technical presentations at national and/or industry conferences.
[*****END OF SOPO TEMPLATE*****]