Attachment 2 Start Up Sheet.pdf
PDF 137 KB Posted
- Solicitation number
- 36C24423Q0072
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24423Q0072 0002.docx | DOCX document | |
| 36C24423Q0072 0002.pdf | ||
| Questions and Answers.pdf | ||
| 36C24423Q0072 0001.pdf | ||
| 36C24423Q0072 0001.docx | DOCX document | |
| 36C24423Q0072.docx | DOCX document | |
| Attachment 1 Pictures of Work Area.pdf | ||
| 36C24423Q0072_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
START-UP & SERVICE DATA INSTRUCTION
ROOFTOP UNIT # 3
START-UP CHECKLIST
Date:
Job Name:
Customer Name:
Address:
City: State: Zip:
Model Number: Serial Number:
Qualified Start-up Technician: Signature:
HVAC Contractor: Phone:
Address:
Contractor’s E-mail Address:
Electrical Contractor: Phone:
Distributor Name: Phone:
Design Supply Air CFM: Design Return Air CFM:
Design Outdoor Air CFM At Minimum Position:
Total External Static Pressure:
Supply Static Pressure:
Return Static Pressure:
Design Building Static Pressure:
Outside Air Dilution: Economizer Position Percentage: _ CFM:
REFERENCE
General Inspection Completed See Notes New steam and Chilled water coils inspected for shipping, storage, or rigging damage. Coil fins in good condition
New steam and Chilled water coils installed with proper clearances
Steam coil checked for gross leaks
Chilled water coil checked for gross leaks
Terminal screws and Piping connections checked for tightness
Filters installed correctly and clean
New dampers and actuators installed properly and fully functional
Condensate drain trapped properly, refer to Installation Manual
New dampers and actuators exercised from BAS system (CM3)
New Chilled water and Steam control valves installed and fully functional w/BAS
All field wiring (power and control) complete
Air Moving Inspection Completed See Notes
Alignment of drive components Correct rotation of motors, Return & Supply
Belt tension adjusted properly
Blower pulleys tight on shaft, bearing set screws tight, wheel tight to shaft
Pressure switch or transducer tubing installed properly
Operating Measurements - Air Flow
Fan operates with proper rotation ID Fans Exh. Fans Cond. Fans Pressure drop across dry Chilled water coil (At maximum design CFM) 1 IWC External Static Pressure IWC Return Static Pressure IWC Supply Static Pressure IWC Supply Air CFM Using Dry Coil Chart CFM Final Adjusted Supply Air CFM2 CFM
Verify Proper Operation of Heating/Cooling Staging Controls
Create a cooling demand at the Thermostat, BAS System (CM3) Verify that cooling is energized. Ensure new chilled water valve is modulating properly
Create a heating demand at the Thermostat, BAS System (CM3) Verify that heating stage is energized. Ensure new steam valve is modulating properly
Verify Proper Operation of the Variable Frequency Drive (If Required) Verify that motor speed modulates with duct pressure change.
FINAL - INSPECTION
Verify that all operational control set points have been set to desired value. Verify proper sequence of operation with BAS (CM3) controls.
Thermal Insulation properly installed according to specification. All areas around new coils and fan motors clean and free of installation debris.
Verify that all access panels have been closed and secured
OBSERVED PRODUCT DIFFICIENCIES & CONCERNS:
| REFERENCE |
| Operating Measurements - Air Flow |
| FINAL - INSPECTION |