Attachment 2 - Specification_Tiger Shark.pdf
PDF 3 MB Posted
- Attached to
- DRYDOCK: USCGC TIGER SHARK DD FY2027
- Solicitation number
- 70Z08026QPBPL0040
About this file
This is a detailed specification for drydock repairs to the USCGC Tiger Shark (WPB-87359), a Coast Guard patrol vessel, scheduled for FY2027 (November 17, 2026 through February 16, 2027). The specification document encompasses 48 work items organized into comprehensive maintenance and preservation tasks required during the vessel's drydock availability.
The work scope includes critical structural and mechanical repairs: hull plating ultrasonic testing and thickness measurements (Work Items 1-2), comprehensive preservation of underwater body surfaces and freeboard at 100 percent coverage (Work Items 3-4), cleaning and inspection of fuel service tanks, dirty oil tanks, and oily water tanks (Work Items 5-7), and deck preservation on main decks and associated equipment foundations (Work Item 8). Additional work items address propulsion system overhauls including main engine realignment, renewal of water-lubricated shaft bearings and bearing carriers, complete propulsion shaft renewal, rudder assembly renewal, and propeller renewal (Work Items 13-20). The specification also requires electrical system upgrades including thermographic inspection of power distribution systems, 24VDC distribution system upgrades, intrusion detection system replacement, and various ventilation, hydraulic, and auxiliary system modifications. Specialized tasks include sea trial performance support, cathodic protection anode renewal, drydocking services, and temporary services provision. Government-furnished property includes specialized components such as Thordon bearings, propeller shafts, rudder assemblies, electrical panels and alternators, and intrusion detection system components, with estimated costs ranging from hundreds to over $14,000 per unit for major items. Quality assurance requirements mandate preservation of critical-coated surfaces with comprehensive documentation through provided QA inspection forms addressing coating system compliance, surface preparation standards, and coating thickness measurements, with seven work items identified as critical inspection items requiring completion within the first 25 percent of the contract period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Blank SOS_Tiger Shark.xlsx | XLSX spreadsheet | |
| 70Z08026QPBPL0040_SOL.pdf | ||
| Attachment 3 - SOW Addendum.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC TIGER SHARK (WPB 87359)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2027
Developed By: Aries T Knoll
(Rev-0, 3 April 2026)
USCGC TIGER SHARK (WPB-87) DRYDOCK AVAILABILITY FY2027
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record .......................................................................................................................................... iv Consolidated List of References .................................................................................................................... v Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items ........................................................................................... xii Principal Characteristics ............................................................................................................................ xiii General Requirements WORK ITEM 1: Hull Plating (Side Scan), Ultrasonic Testing WORK ITEM 2: Ultrasonic Thickness Measurements, Perform WORK ITEM 3: U/W Body, Preserve, 100 percent WORK ITEM 4: Hull Plating Freeboard, Preserve, 100 Percent WORK ITEM 5: Tank, Dirty Oil, Clean and Inspect WORK ITEM 6: Tank, Oily Water, Clean and Inspect WORK ITEM 7: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 8: Decks, Exterior (Main Deck), Preserve WORK ITEM 9: Superstructure, Preserve, 100% WORK ITEM 10: Capastic Fairing, Depth Sounder, Renew WORK ITEM 11: Watertight Closures, Assess WORK ITEM 12: Mast, Preserve (“100%”) – Contractor Interference Removal WORK ITEM 13: Main Engine/Reduction Gear, Realign WORK ITEM 14: Intermediate Water-Lubricated Propulsion Shaft Bearings, Renew WORK ITEM 15: Aft Water-Lubricated Propulsion Shaft Bearings, Renew WORK ITEM 16: Intermediate Bearing Carriers, Renew WORK ITEM 17: Aft Bearing Carriers, Renew WORK ITEM 18: Propulsion Shafts, Renew WORK ITEM 19: Stern Tube Interior Surfaces, Preserve, 100 Percent WORK ITEM 20: Propellers, Renew WORK ITEM 21: Electrical Power Distribution System, Thermographic Inspection, 450 VAC And
Below WORK ITEM 22: Fathometer Transducer, Renew WORK ITEM 23: Speed Log, Skin Valve, Renew WORK ITEM 24: Ventilation System, Engine Room Supply and Exhaust Fan Assemblies, Clean and
Inspect WORK ITEM 25: Ducting, HVAC System, Clean WORK ITEM 26: Sea Water System, Perform Maintenance WORK ITEM 27: Rudder Assemblies, Renew WORK ITEM 28: Stern Launch Door, Remove, Inspect and Reinstall WORK ITEM 29: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 30: Sewage Holding Tanks, Clean and Inspect WORK ITEM 31: Grey Water Piping, Clean and Flush WORK ITEM 32: Sewage Piping, Clean and Flush WORK ITEM 33: Cathodic Protection/Zinc Anodes, Renew WORK ITEM 34: Drydock WORK ITEM 35: Temporary Services, Provide - Cutter WORK ITEM 36: Sea Trial Performance, Support, Provide WORK ITEM 37: Auxiliary Foundation(s), Renew WORK ITEM 38: Seawater Cooling Piping/Valves, Renew WORK ITEM 39: Critical Coated Surface(s), Preserve WORK ITEM 40: Carpeting, Renew iii (Rev-0)
WORK ITEM 41: Mooring Bits, Renew WORK ITEM 42: Flood Lights, Modify WORK ITEM 43: 24VDC Distribution System, Upgrade WORK ITEM 44: Intrusion Detection System, Replace WORK ITEM 45: Unmanned Space Ventilation Modify WORK ITEM 46: Cathodic Protection/Zinc Anode(s), Remove WORK ITEM 47: Fire Main Bleed Line, Modify WORK ITEM 48: Sewage Air Compressor, Remove iv (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
v (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-001, Rev -, Tank Capacity Curves Coast Guard Drawing 87 WPB 085-011, Rev D, Lifting Slings Coast Guard Drawing 87 WPB 085-012, Rev A, Lifting Cradle Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion Coast Guard Drawing 87 WPB 111-050, Rev A, Updates to DWG 87-WPB-111-001 Exhaust Port Insert
Plate Installation and Details Coast Guard Drawing 87 WPB 113-001, Rev G, Platform Plating & Framing Coast Guard Drawing 87 WPB 116-001, Rev -, Longitudinal Girders & BHD’s Coast Guard Drawing 87 WPB 117-001, Rev G, Transverse Sections Coast Guard Drawing 87 WPB 122-001, Rev C, Watertight Bulkheads Coast Guard Drawing 87 WPB 131-001, Rev J, Deck Construction Plan Coast Guard Drawing 87 WPB 151-001, Rev M, Superstructure Details Coast Guard Drawing 87 WPB 163-001, Rev H, Sea Chest Details Coast Guard Drawing 87 WPB 165-001, Rev F, Transducer Details Coast Guard Drawing 87 WPB 167-002, Rev C, CG Schedule of Doors, Manholes, Windows & Hatches Coast Guard Drawing 87 WPB 167-003, Rev -, Weather Tight Door for Fuel Station Access Coast Guard Drawing 87 WPB 167-004, Rev H, W.T. Doors and Hatches Coast Guard Drawing 87 WPB 171-001, Rev Y, Mast Details Coast Guard Drawing 87 WPB 182-001, Rev C, Main Engine & Generator Foundations Coast Guard Drawing 87 WPB 184-002, Rev A, Foundation Mods Incidental to LED Floodlight Install Coast Guard Drawing 87 WPB 185-001, Rev AP, Auxiliary Foundation Booklet Coast Guard Drawing 87 WPB 243-003, Rev -, Propulsion Shaft Details Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details Coast Guard Drawing 87 WPB 256-001, Rev AC, Seawater Cooling Piping Coast Guard Drawing 87 WPB 302-001, Rev AF, Misc. Controls Wiring Diagram Coast Guard Drawing 87 WPB 310-001, Rev J, Ship’s Service One-Line Diagram Coast Guard Drawing 87 WPB 310-007, Rev A, Unmanned Spaces Ventilation modification Electrical Coast Guard Drawing 87 WPB 313-001, Rev R, DC System vi (Rev-0)
Coast Guard Drawing 87 WPB 321-001, Rev L, Power System Deck Plan Coast Guard Drawing 87 WPB 321-002, Rev AV, Power & Lighting Circuit Details & V.D. Calculations Coast Guard Drawing 87 WPB 330-002, Rev -, Pilothouse LED Floodlight Modifications Electrical Coast Guard Drawing 87 WPB 331-001, Rev R, Lighting System Deck Plan Coast Guard Drawing 87 WPB 423-001, Rev Y, Speed Log & Depth Sounder System Coast Guard Drawing 87 WPB 433-001, Rev M, General Announcing & Alarm Sys Wiring Diagram Coast Guard Drawing 87 WPB 436-001, Rev H, Fire Detection System Coast Guard Drawing 87 WPB 514-001, Rev M, HVAC Duct & Piping System Coast Guard Drawing 87 WPB 514-005, Rev E, Ventilation Mods to Unmanned Spaces Coast Guard Drawing 87 WPB 521-002, Rev -, Fire Main Bleed Line Mod Coast Guard Drawing 87 WPB 526-001, Rev J, Scuppers & Deck Drains Piping Coast Guard Drawing 87 WPB 561-001, Rev M, Steering System Details Coast Guard Drawing 87 WPB 562-001, Rev A, Rudder Details Coast Guard Drawing 87 WPB 582-001, Rev J, Mooring and Towing Coast Guard Drawing 87 WPB 583-001, Rev Y, RIB Deployment Structure Coast Guard Drawing 87 WPB 593-001, Rev L, Sewage Piping Coast Guard Drawing 87 WPB 593-005, Rev -, Air Compressor, Removal Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements Coast Guard Drawing 87 WPB 602-001, Rev F, Visual ID and Draft Mark Plan Coast Guard Drawing 87 WPB 621-001, Rev K, Joiner Work Details Coast Guard Drawing 87 WPB 631-001, Rev P, Ship’s Painting Schedule Coast Guard Drawing 87 WPB 633-001, Rev A, Cathodic Protection Coast Guard Drawing 87 WPB 634-001, Rev G, Deck Covering and Details Coast Guard Drawing 87 WPB 635-001, Rev C, Linings and Insulation Coast Guard Drawing 87 WPB 640-001, Rev P, Interior Furnishings Coast Guard Drawing 87 WPB 995-001, Rev -, Jigs and Fixtures for Shaft Installation Coast Guard Drawing 87WPB 431-001, Rev U, IC Panel Board Wiring Diagram Coast Guard Drawing 87WPB 432-001, Rev L, Dial Telephone Wiring Diagram Coast Guard Drawing 87WPB 436-002, Rev C, Intrusion Detection System, Replace Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem Coast Guard Fleet Drawing FL 2804-22, Rev B, Consolidated Visual ID for Cutters
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3D, Coatings and Color Manual Coast Guard Commandant Instruction (COMDTINST) M5530.1C, Physical Security and Force
Protection Program Coast Guard Technical Publication (TP) 4499, Jun 2018, SWBS 243, Stern Tube Seal-Model 442C Coast Guard Technical Publication (TP) 4500, Sep 2017, SWBS 233, Engine Change-Out Guide -
Waterborne Main Diesel Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock
Seal Type EL Coast Guard Technical Publication (TP) 4511, SWBS 430, Jun 2019, Alarm Panel & Tank Level
Indication (TLI) System vii (Rev-0)
Coast Guard Technical Publication (TP) 4525, SWBS 202, 2003, Main Diesel Engine Control System Schematics
Coast Guard Technical Publication (TP) 4533, SWBS 233, 2002, Propulsion Internal Combustion Engines, Maintenance Manual
Coast Guard Technical Publication (TP) 4559, SWBS 513, Oct 2019, Ventilation System, Engine Room Coast Guard Technical Publication (TP) 4564A, Electronic Steering System Coast Guard Technical Publication (TP) E-424-013, SWBS 424, July 2007, CDOH-EML500 Speedlog
User’s Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard
Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean
Shipboard Ventilation Systems Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire
Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std. Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior
Deck Covering Systems Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary
Services
OTHER REFERENCES
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2016, Recommended Practice for
Personal Qualification and Certification in Nondestructive Testing American Society for Nondestructive Testing, SNT-TC-1A: Personnel Qualification and Certification in
Nondestructive Testing, 2016 AN/SPS-73V Surface Search Radar (SSR), Sep 1998, Operation, Maintenance, and Installation Manual ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-
Petrolatum Commercial Item Descriptions (CID) A-A-59316, Nov 2016 Abrasive Materials for Blasting Federal Standard (FED-STD) 595, 2008, Colors Used in Government Procurement viii (Rev-0)
MIL-A-18001, Dec 2015, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418) MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning MIL-A-46106b, Jun 1992, Adhesive-Sealants, Silicone, RTV, One-Component MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Non-ionic) MIL-HDBK-299, Oct 1991, Cable Comparison Handbook – Data Pertaining to Electric Shipboard Cable MIL-PRF-24139, Mar 1987, Grease, Multipurpose, Water Resistant.
MIL-PRF-24613A, Nov 2007, Deck Covering Materials, Interior, Cosmetic Polymeric MIL-PRF-24635, 2009, Coating Systems, Weather-Resistant, Exterior Use MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull MIL-STD-2003, Sep 2009, Electrical Plant Installation Standard Methods for Surface Ships &
Submarines Raytheon Marine Company, Jan 1992, Technical Manual, Radar Set Model R40X/R41X, AN/SPS-69, RMC Document Number G261404 Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and
Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and
Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power-Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning ix (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
8 N Slip Resistant Sheets NSN: 7220-01-F11-2238 1 KT 5,352.24 13 Y *Alignment jig N/A 1 ea. ---- 14 N Thordon bearing, Grade Orange (5.5" OD x 4" ID x 7.87"
(200mm) LG)
PN: F54615-02-8-1 NSN:
3120-21-914-2012
2 ea. 525.03
15 N Thordon bearing, Grade Orange (5.5" OD x 4" ID x 11.41"
(290mm) LG)
PN: F54615-02-8-0 NSN:
3120-21-914-2011
2 ea. 558.05
16 N **Intermediate bearing carrier
NSN: 3130-01-F11-2388 P/N:
87 WPB 243-001, Item 17
2 ea. 591.86
17 N **Aft bearing carrier NSN: 3130-01-F11-2200 PN:
87 WPB 243-001, Item 14
2 ea. 1931.31
18 Y Propeller Shaft NSN: 2010-01-458-9175 2 ea. 10,195.95 18 N Seal Assembly, Shaft NSN: 4320-01-670-5724 PN:
388725 2 ea. 6801.00
18 N Kit Rebuild, Inflatable Seal
NSN: 5330-01-F18-5385 PN:
390831
2 ea. 1381.00
18 Y *Alignment Kit N/A 1 set 5000.00 20 Y Starboard Propeller
(RH)
PN: 706-3351.00 RH NSN:
2010-01-457-0573 1 ea. 9153.07
20 Y Port Propeller (LH) PN: 706-3350.00 LH NSN:
2010-01-459-0421
1 ea. 9542.05
20 N *Propeller Nut Wrench N/A 1 ea. 200.00 20 N Propeller Nut PN: 5317350 NSN: 2010-01-
458-9217 2 ea. 322.07
20 N Propeller Nut, Locking PN: 5317355 NSN: 5310-01- 458-9125
2 ea. 285.10
20 N Anode, Propeller Nut PN: 87WPB243001ITEM39
NSN: 5342-01-481-8403
2 ea. 153.06
22 N Transducer, sonar PN: A80214 NSN: 5845-01- 668-2181
1 ea. 328.72
23 N 3" Ball Valve NSN: 4810-01-517-8110 PN:
LV071A
1 ea. 5625.00
23 N **Doppler Speed Log Measurement Rod
NSN: 6605-01-470-1266 1 ea. 4984.63
24 N **Fan, Tube Axial NSN: 4140-01-598-0425 1 ea. 2,223.72 24 N **Fan, Tube Axial NSN: 4140-01-598-1549 1 ea. 3,091.15 26 N Iron body/ Stainless steel stem/ bronze disk (flanged) 8 inch
PN: J022929-512431A NSN:
4820-01-613-5021
2 ea. 563.25 x (Rev-0)
26 N Iron body/ Stainless steel stem/ bronze disk
(wafer) 8 inch
PN: 22929-112431A NSN:
4820-01-615-9571
2 ea. 521.46
26 N Iron body/ Stainless steel stem/ bronze disk
(flanged) 3 inch
PN: 22925-5124 NSN: 4820-
01-650-0975
2 ea. 226.51
26 N Iron body/ Stainless steel stem/ bronze disk
(wafer) 3 inch
PN: 22925-1124316 NSN:
4820-01-332-6811
2 ea. 214.14
27 Y Rudder Assembly, port NSN: 2040-01-461-1944 1 ea. 6113.36 27 Y Rudder Assembly, starboard NSN: 2040-01-461-1943 1 ea. 5971.93
27 N Upper Roller Bearing NSN: 3110-01-512-5534 2 ea. 287.43 27 N Wartsila EL Seals Kit PN: H75492-01 NSN: 2040-01-
565-9776 2 ea. 7243.42
27 N Lower Bearing PN: TBF113090 NSN: 3120- 20-000-7677
2 ea. 405.81
28 N **Valve, Counterbalance
PN: CBCA-LAN/AP NSN:
4820-01-687-1295
4 ea. 291.50
28 N **Manifold, Valve PN: YVY NSN: 4730-01-687-
2 ea. 134.30
33 N Anode, corrosion preventive
PN: 899Y105 NSN: 5342-00-
813-6058
15 ea 57.37
33 N Anode, corrosion preventive
PN: Z0220205F3REV1 NSN:
5340-01-644-5457
2 ea 111.95
34 Y *Transducer Cover Plate
N/A 2 ea. 50.00
42 N Phoenix SturdiLED White
NSN: 6230-01-696-1316 2 ea. $784.33
42 N Phoenix SturdiLED Red
NSN: 6210-01-696-0472 2 ea. $784.33
43 N Panel Bridge 24 V NSN: 6110-01-F18-5605 1 ea. 2,548.00 43 N Alternator NSN: 6125-01-020-2950 2 ea. 14,668.79 43 N Regulator Voltage NSN: 5963-01-623-3549 2 ea. 350.00 43 N Resistor Thermal NSN: 5905-01-662-5504 2 ea. 35.00 43 N Harness, Wiring NSN: 5995-01-661-5659 2 ea. 75.00 43 N Seal Plain NSN: 5330-12-314-3403 2 ea. 56.32 43 N Coupling Half NSN: 4730-12-408-7920 2 ea. 1,572.87 43 N Coupling, Flex NSN: 3010-01-255-4200 2 ea. 480.44 43 N Insert, Flexible
Coupling NSN: 3010-12-332-3557 2 ea. 830.23
43 N Screw Machine NSN: 5305-01-384-3454 12 ea. 3.71 43 N Washer, Spring
Tension NSN: 5310-12-125-7798 12 ea. 2.44
43 N Nut, Plain Hexagon NSN: 5310-12-156-4982 12 ea. 2.33 43 N Guard Plate NSN: 2920-12-408-7817 2 ea. 941.45 43 N Plate, Mounting NSN: 5340-12-333-7085 2 ea. 75.00 43 N Screw, Cap, Hexagon NSN: 5305-01-240-1274 14 ea. 4.53 43 N Washer, Spring NSN: 5310-01-195-9000 14 ea. 1.81 xi (Rev-0)
Tension 43 N Screw Cap Hexagon NSN: 5305-12-142-8243 4 ea. 7.92 43 N Screw, Cap NSN: 5305-12-142-8236 4 ea. 3.64 43 N Washer, Flat NSN: 5310-12-149-4352 8 ea. 2.35 43 N Bracket NSN: 2815-12-408-5547 4 ea. 130.18 44 N Sensaphone Eapress II ACN: 6320-01-F21-6407 1 $1300 44 N IDS Relay Panel ACN: 6320-01-F21-6406 1 $1400 44 N Switch, 3 position, Key Lock, ACN: 6320-01-F21-6408 1 $13.00
44 N Holder, switch ACN: 6320-01-F21-6409 1 $2.00 44 N Contact Block, NC ACN: 6320-01-F21-6410 2 $5.00 44 N Sensor, Optical ACN: 6320-01-F21-6411 6 $44.00 44 N Mounting Bracket, 90 deg
ACN: 5340-01-F21-6412 2 $7.00
44 N Mounting Bracket, straight
ACN: 5340-01-F21-6413 4 $7.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xii (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
3 U/W Body, Preserve, 100 percent
18 Propulsion Shafts, Renew
26 Sea Water System, Perform Maintenance
27 Rudder Assemblies, Renew
28 Stern Launch Door, Remove, Inspect and Reinstall
34 Drydock
39 Critical Coated Surface(s), Preserve xiii (Rev-0)
PRINCIPAL CHARACTERISTICS
87' WPB
PHYSICAL
Length overall 87' Length between perpendiculars 81' 7" Depth 10' 11" Maximum beam 19.4' Draft, mean to design waterline 5' 9" Height of highest projection 50.2' Full load displacement 93.5 long tons Minimum operating displacement 83.9 long tons Displacement, light ship 77.9 long tons Framing Longitudinal Bulkheads Four watertight bulkheads located below the Main Deck Anchor 40 lb Fortress with 480 ft. 3 strand 5/8" dia. Line stayset
HULL
Hull/main weatherdeck material ABS Grade AH 36 Superstructure 5086 Aluminum
MACHINERY
Main propulsion Two MTU 8V396TE94, sequential turbo-charged diesels Reduction gears Two ZF Type BW 255 Propulsion shaft Two AQUAMET 22, 101.6mm Shaft diameter 4" Shaft seal Two John Crane mechanical seals Shaft bearing, intermediate Thordon Elastomeric Bearing Shaft bearing, aft Thordon Elastomeric Bearing Number of propellers 2 Number of blades 5 Diameter of propeller 1040mm Pitch 1230 mm fixed Shaft RPM 828 Rudders Two 316L Stainless Steel Ship's service generators Two Man Model D08241F01 diesel with Stanford 60KW Generator
TANK CAPACITIES
3-9-1-f (fuel oil) 1402 gal 3-9-2-f (fuel oil) 1402 gal 3-12-2-f (waste oil) 86 gal 3-12-1-f (oily water) 86 gal 3-7-0-q (sewage collection) 352 gal 3-7-1-q (grey water) 52 gal 3-12-1-w (fresh water) 200 gal 3-12-2-w (fresh water) 200 gal
1 (Rev-0)
00000_0226_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3D, Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire
Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under
2 (Rev-0) the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70
3 (Rev-0) microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and
4 (Rev-0) storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK
ITEM #
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL # WORK
ITEM # WORK ITEM TITLE
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER
COAT, BARRIER COAT, TOP
COAT, ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFAC
E
AMBIEN
T
ΔT
| DP -
SURFACE |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK
ITEM #
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL # WORK ITEM
# WORK ITEM TITLE
COATING MFG PRODUCT NAME BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5 AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
11 (Rev-0)
4.2 Tank and Void Assessment form.
12 (Rev-0)
13 (Rev-0)
11000_NET_0523_87WPB
WORK ITEM 1: Hull Plating (Side Scan), Ultrasonic Testing
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform thickness measurements of the underwater (u/w) body and freeboard by ultrasonic side scan method.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion Coast Guard Drawing 87 WPB 111-050, Rev A, Updates to DWG 87-WPB-111-001 Exhaust
Port Insert Plate Installation and Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
OTHER REFERENCES
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2016, Recommended
Practice for Personal Qualification and Certification in Nondestructive Testing
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
14 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
• Hull zinc anode system
• Docking blocks
3.2 Work coordination and preparation. The Contractor must plan all specified vessel work detailed in this specification package to ensure the side scan survey does not necessitate a work stoppage. The Contractor must abide by the following guidance, to facilitate the ultrasonic survey:
• Ensure that all freeboard and u/w body surface preparation and primer coat application tasks are completed within ten days of lifting the vessel.
• Prior to side-scan survey, inspect interior and bilge plating for the presence of bubbles of rusted metal. Break up and remove all rust bubbles to ensure accurate survey results.
• Provide a continuous supply of fresh water at .50 gpm within 50 feet of the vessel with standard hose bib fitting.
• Provide 110 VAC electrical power, and scaffolding or other suitable means of access to bring inspection personnel within one foot of all the hull surface inspection areas that are five feet above ground level.
• After completion of the hull survey, and authorized hull repairs, resume/complete freeboard and u/w body preservation process.
• Pay close attention to manufacturer’s recommended practices in regard to paint system overcoat time limitations and required degree of surface cleanliness prior to resuming coating operations.
3.3 Side scan requirements and procedures. The Contractor must ensure the following referring to Coast Guard Drawings 87 WPB 085-13, 87 WPB 111-001, and 87 WPB 111-050 as guidance during the performance of the tasks specified below.
3.3.1 Testing company and personnel. Provide the services of a qualified ultrasonic testing company, with suitable side scan equipment, to conduct a “Scanning Crawler Automated Test” of the vessel’s freeboard and u/w hull plating for the presence of metal corrosion and deterioration. Ensure the following:
• All scanning operations are completed by personnel meeting the personnel qualification and certification, as required by contractor process. This contractor-developed personnel qualification and certification process must meet, at a minimum, ASNT Recommended Practice No. SNT-TC-1A.
• An ASNT Level III Analyst is on site, to oversee the project and evaluate the collected data.
• An ASNT Level III or II Analyst is on site, to verify with a hand held gauge all areas on the hull identified as thinner than the specified criteria, in order to expedite all repair procedures.
• Qualified personnel are provided to complete all on-site inspections.
3.3.2 Coast Guard notification.
3.3.2.1 Provide a daily update to the COR on all areas inspected and potential issues or schedule changes.
15 (Rev-0)
3.3.2.2 Notify the COR at least 3 days prior to completion for an onsite review of readings and repair areas.
3.3.3 Scanning parameters. Use the following parameters during the course of this inspection:
• Automated scanning resolution must be set to 0.5” x 0.5”
• Plates where scan data indicating wastage greater than or equal to 25% nominal plate thickness must be highlighted in “RED” and designated “repair areas”.
• Plates where scan data indicating wastage greater than or equal to 15% to 24% of nominal plate thickness must be highlighted in “YELLOW”.
• Plates where scan data indicating wastage greater than or equal to 10% to 14% of nominal plate thickness must be highlighted in DARK GREEN.
• Hand held UT readings must be taken to verify bad metal areas found with the side scan equipment. All readings must be provided to the COR and the lowest reading marked on the hull at the bad metal location.
• Areas that are accessible but cannot be reached by the automated scanner must be scanned with a hand-held meter at a resolution of 2” x 2”. Any repair areas found during the hand scan must be marked on the ships hull and their approximate positions recorded on the plate drawings and report summary.
3.3.3.1 Any scanning parameter or scope of work changes must be approved by the KO.
3.3.3.2 The echo to echo transducer is not authorized due to inconsistent readings and technical difficulties.
3.3.3.3 There must be no deviation from the color scheme specified above.
3.3.4 Ensure that the side scan inspection area includes the Port, Starboard, and Transom exterior shell plating, but must exclude the following list.
• Areas under and within 6-inches of blocks and side blocks (areas that are accessible 6 inches from blocks and side blocks must be hand scanned.)
• Areas up to 6-inches around any obstacle on the hull including sea suctions, discharges, rudderposts, anodes, stern tubes, and docking blocks.
• Any areas blocked by immovable scaffolding or shipyard activity.
3.4 Side scan reports. The Contractor must submit a CFR containing the final report within three working days after the side scan inspection is completed. A copy of all repair areas must be clearly marked, in yellow or white, on the provided shell plate drawing(s), and provide a summary document of same areas.
Submit two hard copies of the report with two CD’s containing the electronic (raw) data prior to departing the job site. Ensure the reports include:
• Inspection overview.
• Data sheets for each plate with designated repair areas outlined in blue.
• Mosaic of scanned data overlaid on Coast Guard Drawing 87 WPB 111-001.
16 (Rev-0)
NOTE
Where hull repairs are required in the vicinity of the exhaust teardrops, use Coast Guard Drawing 87 WPB 111-050 for guidance on location of stainless steel hull inserts and when planning for plating renewal.
3.4.1 Photos. Provide digital photos of all designated repair areas.
3.4.2 Electronic files. Ensure CD’s contain a complete copy of the report, interactive data files, and digital pictures. All electronic files must be compatible with standard USCG workstation operating software.
Electronic files format must be such that the CG has the capability to change the percent of wastage (format conditioning) per plate. Electronic files must be capable of being opened using MS Word, MS Excel, or PDF software. Digital pictures must be recorded in JPEG format.
3.5 Touch-up preservation. The Contractor must prepare and coat all disturbed interior bilge surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)
4. NOTES
This section is not applicable to this work item.
17 (Rev-0)
11000_NET_0523_87WPB
WORK ITEM 2: Ultrasonic Thickness Measurements, Perform
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform up to 250 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion Coast Guard Drawing 87 WPB 111-050, Rev A, Updates to DWG 87-WPB-111-001 Exhaust
Port Insert Plate Installation and Details Coast Guard Drawing 87 WPB 163-001, Rev H, Sea Chest Details
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
18 (Rev-0)
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
• Sea chest grates
• Tight interior spaces
3.2 UT measurements. Using Coast Guard Drawings 87 WPB 085-013, 87 WPB 111-001, and 87 WPB 111-050 as guidance, the Contractor must perform up to 250 UT measurements in locations designated by the Coast Guard Inspector in accordance with SFLC Std Spec 0740, Appendix C. Submit a CFR.
3.2.1 The Contractor must conduct 50 of the 250 UT shots over the 1/4” sea chest plating in both sea…