This is a Specification for Drydock Repairs document for the USCGC BARBARA MABRITY (WLM-559), a 175-foot Coast Guard buoy tender, detailing comprehensive maintenance and repair work for fiscal year 2027. The vessel is homeported in Mobile, Alabama, and the drydock availability will be conducted at a contractor's facility.

The specification encompasses 100 work items covering hull preservation and structural repairs, machinery overhauls, tank cleaning and inspection, propulsion system maintenance, electrical system testing, and preservation of ship structures. Major work categories include hull plating renewal and preservation (Items 1-78), tank cleaning and inspection for fuel, water, ballast, and waste systems (Items 17-23, 55-70), Z-drive propulsion unit overhaul and alignment (Items 25-34), sea valve and strainer maintenance (Items 38-41), thruster and anchor handling system service (Items 45-54), and specialized preservation tasks for decks, superstructure, and masts (Items 71-87). Critical inspection items must be completed within the first 25 percent of the contract period. The specification references numerous Coast Guard drawings, SFLC Standard Specifications, AWS welding standards, SSPC surface preparation standards, and other industry standards. Government-furnished property includes engine mounts, coupling elements, seal kits, bearings, transducers, hydraulic components, and various windows and doors. The quotation due date is November 6, 2026, at 1:00 PM Eastern Time, with quotes valid for 120 days, and submissions should be sent via email to Sandy.M.Reed Robinson and Sandra.A. Martinez at the USCG.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC BARBARA MABRITY (WLM 559)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2027

Developed By: Robert J Stankovich

(Rev-0, 16 July 2026)

USCGC BARBARA MABRITY (WLM-175) DRYDOCK AVAILABILITY FY2027

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ........................................................................................................................................... v Consolidated List of References ................................................................................................................... vi Consolidated List of Government-furnished Property ............................................................................... xiv Consolidated List of Critical Inspection Items ......................................................................................... xvii Principal Characteristics - TENDER .......................................................................................................... xix General Requirements WORK ITEM 1: Fire Prevention Requirements WORK ITEM 2: Hull Plating, Side Scan, Ultrasonic Testing WORK ITEM 3: U/W Body, Preserve, 100 percent WORK ITEM 4: Hull Plating Freeboard, Preserve, Partial WORK ITEM 5: Hull Plating Freeboard, Preserve, 100 Percent WORK ITEM 6: Hull and Structural Plating, General, 10.2 lbs. Steel, Renew WORK ITEM 7: Hull and Structural Plating, General, 12.75 lbs. Steel Plate, Renew WORK ITEM 8: Hull and Structural Plating, General, 15.3 lbs. Steel Plate, Renew WORK ITEM 9: Hull And Structural Plating, General, 20.4 lbs. Steel Plate, Renew WORK ITEM 10: Hull and Structural Plating, General, 7.5 lbs., 3/16 in. Steel Plate, Renew WORK ITEM 11: Hull and Structural Plating, General, 7.65 lbs. Steel Plate, Renew WORK ITEM 12: Hull And Structural Plating, General, Cracked Steel Welds, Repairs WORK ITEM 13: Hull and Structural Plating, General, Degraded Weld, Steel, Repair WORK ITEM 14: Appendages, U/W, Leak Test WORK ITEM 15: Appendages, U/W, Internal, Preserve WORK ITEM 16: Chain Lockers, Clean and Inspect WORK ITEM 17: Tanks, MP Fuel Stowage and Overflow, Clean and Inspect WORK ITEM 18: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 19: Tanks, Potable Water, Clean and Inspect WORK ITEM 20: Tanks, Lube Oil, Clean and Inspect WORK ITEM 21: Tanks, Ballast, Clean and Inspect WORK ITEM 22: Voids, Accessible, Clean and Inspect WORK ITEM 23: Tanks, Dirty Oil and Waste, Clean and Inspect WORK ITEM 24: Hydraulically Operated Cargo Hatch, Inspect and Service WORK ITEM 25: Both Main Diesel Engine Mounts, Renewal WORK ITEM 26: Main Diesel Engine, Check Alignment WORK ITEM 27: Both Z-Drive Propulsion Trains, Alignment WORK ITEM 28: Propulsion Shaft Bulkhead Seals, Overhaul WORK ITEM 29: Z-Drive Input Drive Shaft, Bearings Inspect WORK ITEM 30: Z-Drive Input Drive Shaft, Alignment Check WORK ITEM 31: Z-Drive Propulsion Units, Overhaul WORK ITEM 32: Z-Drive Coolers, Clean and Inspect WORK ITEM 33: Z-Drive Input Drive Shaft, Thrust Bearing Renewal WORK ITEM 34: Heat Exchangers, Clean, Inspect And Hydro WORK ITEM 35: Circuit Breakers (60 Hz), Inspect and Test WORK ITEM 36: Fathometer Transducer, Renew WORK ITEM 37: Underwater Speed Log, Transducers, Renew WORK ITEM 38: Sea Valves and Waster Pieces, Overhaul Or Renew WORK ITEM 39: Sea Strainers, All Sizes, Renew WORK ITEM 40: Sea Strainers, Duplex, All Sizes, Overhaul WORK ITEM 41: Sea Strainers, Simplex, All Sizes, Clean and Inspect WORK ITEM 42: Sea Bay, Preserve - Partial iii (Rev-0)

WORK ITEM 43: Sea Bay, Clean and Inspect WORK ITEM 44: Sea Bay, Preserve 100% WORK ITEM 45: Thruster Unit (General), Overhaul WORK ITEM 46: Thruster Unit Bearings, Renew WORK ITEM 47: Anchor Windlass, Inspect And Service WORK ITEM 48: Anchor Chains and Ground Tackle, Inspect and Repair WORK ITEM 49: Anchor Chain and Ground Tackle, Preserve WORK ITEM 50: Anchors, Preserve WORK ITEM 51: Hawse Pipes, Preserve WORK ITEM 52: Towing Bitts, Chocks, and Fairleads, Inspect and Test WORK ITEM 53: Hull Fittings (Mooring and Towing), Inspect and Test WORK ITEM 54: Warping Capstan (Aft), Inspect and Service WORK ITEM 55: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 56: Sewage Holding Tanks, Clean and Inspect WORK ITEM 57: Tanks, Grey Water Holding, Preserve, Partial WORK ITEM 58: Tanks (Sewage Holding), Preserve, 100 percent WORK ITEM 59: Tanks (Sewage Holding), Preserve, Partial WORK ITEM 60: Tanks, Ballast, Preserve, 100 Percent WORK ITEM 61: Tanks, Ballast, Preserve, Partial WORK ITEM 62: Chain Locker, Preserve, 100 Percent WORK ITEM 63: Tanks, Dirty Oil and Waste, Preserve, 100 Percent, WORK ITEM 64: Tanks, Dirty Oil and Waste, Preserve, Partial, WORK ITEM 65: Tanks, Grey Water Holding, Preserve, 100 Percent WORK ITEM 66: Tanks, MP Fuel Service, Preserve, Partial WORK ITEM 67: Tanks, MP Fuel Storage and Overflow, Preserve, Partial WORK ITEM 68: Tanks, MP Fuel Storage and Overflow, Preserve 100 Percent WORK ITEM 69: Tanks, Potable Water Preserve, 100 Percent WORK ITEM 70: Tanks, Potable Water, Preserve, Partial, WORK ITEM 71: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 72: Decks - Exterior, Preserve, Non-Skid MIL-PRF-24667 System, WORK ITEM 73: Hull Plating Freeboard (Buoy Port Areas), Preserve WORK ITEM 74: Superstructure, Preserve, 100 Percent WORK ITEM 75: Superstructure, Preserve, Partial WORK ITEM 76: Exhaust Stacks, Exterior, Preserve WORK ITEM 77: Exhaust Stacks (Exterior), Preserve - Partial WORK ITEM 78: Cathodic Protection, Zinc Anodes, Renew, WORK ITEM 79: Drydock WORK ITEM 80: Temporary Services, Provide - Cutter WORK ITEM 81: Cargo Hatch Gasket, Renew WORK ITEM 82: Mast (FWD), Preserve WORK ITEM 83: Main Mast, Preserve, 100% WORK ITEM 84: Main Mast, Preserve - Partial WORK ITEM 85: Cargo Hold Deck, Preserve 100% WORK ITEM 86: Superstructure Surfaces (Buoy Deck Area), Preserve WORK ITEM 87: ATON Tie-down, Install WORK ITEM 88: Flame Detectors, Replace WORK ITEM 89: Chief Petty Officer Engineer Stateroom Window, Renew WORK ITEM 90: Watertight Scuttles, Renew WORK ITEM 91: Weathertight Doors, Renew WORK ITEM 92: Buoy Chain Port Renew WORK ITEM 93: Quick Acting Watertight Door, Renew iv (Rev-0)

WORK ITEM 94: Fuel Oil (FO) System Piping, Renew WORK ITEM 95: Bow Thruster Room Plating Repair WORK ITEM 96: Engine Room Demister, Inspect, Repair, and Preserve WORK ITEM 97: Supply/Exhaust System, Renew WORK ITEM 98: Exterior Window, Renew WORK ITEM 99: Tenting, Provide WORK ITEM 100: Independent NACE Inspector (Level 3), Provide v (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

vi (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard 175 WLM 541-001, Rev H, FUEL OIL SYSTEM DIAGRAM

Coast Guard 175 WLM 541-003, Rev F, FUEL OIL SERVICE A/D HULL BLOCK 940, 970

Coast Guard Drawing {xxxxxx}, Rev {x}, Title

Coast Guard Drawing 175 WLM 170-1, Rev H; Mast Arrangement & Details

Coast Guard Drawing 175 WLM 114-001, Rev D, Shell Appendages

Coast Guard Drawing 175 WLM 130-001, Rev -, Mods to Buoy Deck Incidental to Hawser Pipe Cover

Coast Guard Drawing 175 WLM 130-001, Rev -Mods to Buoy Deck Incidental to Hawser Pipe Cover

Coast Guard Drawing 175 WLM 162-1, Rev E, Stack A & D 1 & 2 Panels

Coast Guard Drawing 175 WLM 170-1, Rev H; Mast Arrangement & Details

Coast Guard Drawing 175 WLM 184-001, Rev A, V850 Transducer Adaptor Ring

Coast Guard Drawing 175 WLM 184-001, Rev-, CRP-V850 Transducer Adapter Ring

Coast Guard Drawing 175 WLM 184-001, V850 Transducer Adaptor Ring

Coast Guard Drawing 175 WLM 201-001, Rev C, Machinery Spaces Arrangement

Coast Guard Drawing 175 WLM 243-001, Rev -, Propulsion Shafting Arrangement

Coast Guard Drawing 175 WLM 243-002, Rev F, Propulsion Shaft Arrangement

Coast Guard Drawing 175 WLM 243-002, Rev F, Propulsion Shafting Arrangement

Coast Guard Drawing 175 WLM 243-1, Rev -, Propulsion Shaft Arrangement

Coast Guard Drawing 175 WLM 243-2, Rev E, Propulsion Shaft Arrangement

Coast Guard Drawing 175 WLM 243-2, Rev F, Propulsion Shaft Arrangement

Coast Guard Drawing 175 WLM 243-2, Rev F, Propulsion Shaft Arrangement

Coast Guard Drawing 175 WLM 244-001, Rev -, 4.438” TYPE ND Bulkhead Seal

Coast Guard Drawing 175 WLM 245-2, Rev A, Z DRIVE PROPELLER DETAILS, MODIFIED

Coast Guard Drawing 175 WLM 256-001, Rev J, Sea Water Cooling System Diagram

Coast Guard Drawing 175 WLM 256-001, Rev K, Seawater Cooling System Diagram

Coast Guard Drawing 175 WLM 256-003, Rev D, Seawater Cooling System FR 61 Forward

Coast Guard Drawing 175 WLM 256-004, Rev J, Sea Water Cooling System Arrangements and Details

Coast Guard Drawing 175 WLM 256-004, Rev J, Seawater Cooling System Arrangements and Details

Coast Guard Drawing 175 WLM 256-004, Rev J, Sheets 5 and 13, Seawater Cooling System A & D, Hull Blocks 940-970 vii (Rev-0)

Coast Guard Drawing 175 WLM 256-005, Rev -, Z-Drive Lube Oil Heat Exchanger Tube Bundle, Replacement and Piping Mods

Coast Guard Drawing 175 WLM 256-012, Rev B, Auxiliary Seawater System Piping Mods

Coast Guard Drawing 175 WLM 256-013, Rev A, Sea Bay Thermometer Installation

Coast Guard Drawing 175 WLM 505-003, Rev B, Sea Connection Arrangements

Coast Guard Drawing 175 WLM 506-001, Rev G, Overflows, Air Escapes & Sounding Tubes Diagram

Coast Guard Drawing 175 WLM 512-13, Rev C, HVAC Std Details & General Instructions

Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950

Coast Guard Drawing 175 WLM 541-001, Rev H, Fuel Oil System Diagram

Coast Guard Drawing 175 WLM 541-006, Rev C, Independent Tanks, Emergency Generator Day Tank

IIP:7-1

Coast Guard Drawing 175 WLM 549-001, Rev E, Onboard Lubrication Requirements

Coast Guard Drawing 175 WLM 573-001, Rev T, Buoy Deck Arrangement

Coast Guard Drawing 175 WLM 581-001, Rev E, Anchor Handling System Arrangement

Coast Guard Drawing 175 WLM 581-001, Rev F, Anchor Handling System Arrangement

Coast Guard Drawing 175 WLM 581-001, Rev F, Anchor Handling System

Coast Guard Drawing 175 WLM 582-001, Rev D, Mooring and Towing, A & D

Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage & Waste Water System Diagram

Coast Guard Drawing 175 WLM 593-009, Rev E, Independent Tanks, Sewage Holding Tank

Coast Guard Drawing 175 WLM 601-001, Rev L, General Arrangement and Inboard and Outboard Profiles

Coast Guard Drawing 175 WLM 601-001, Rev L; General Arrangement Inboard and Outboard Profiles

Coast Guard Drawing 175 WLM 601-001, Rev P, General Arrangement and Inboard and Outboard Profiles

Coast Guard Drawing 175 WLM 601-001, Rev P, General Arrangement Inboard and Outboard Profiles

Coast Guard Drawing 175 WLM 601-001, Rev R; General Arrangement Inboard and Outboard Profiles

Coast Guard Drawing 175 WLM 601-001, Rev T, General Arrangement Inboard and Outboard Profiles

Coast Guard Drawing 175 WLM 601-002, Rev H, Booklet of General Drawings (IDA LEWIS)

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings (552-564)

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings 552-564

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans

Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet Of General Plans

Coast Guard Drawing 175 WLM 601-003, Rev L; Booklet Of General Drawings 552-564

Coast Guard Drawing 175 WLM 601-003, Rev N; Booklet Of General Plans (552-564)

Coast Guard Drawing 175 WLM 601-1, Rev T, Arrangement, Inboard And Outboard Profiles

Coast Guard Drawing 175 WLM 633-001, Rev D, Cathodic Protection

Coast Guard Drawing 175 WLM 635-001, Rev F, Hull, Thermal, & Acoustic Insulation Schedule

Coast Guard Drawing 175 WLM 801-001, Rev A, Hull Lines

Coast Guard Drawing 175 WLM 801-003, Rev A, Curves of Form

Coast Guard Drawing 175 WLM 801-006, Rev H, Docking Plan

Coast Guard Drawing 175 WLM 801-006, Rev J, Docking Drawing viii (Rev-0)

Coast Guard Drawing 175 WLM 801-006, Rev J, Docking Plan

Coast Guard Drawing 175 WLM 801-019, Rev C, Shell Expansion

Coast Guard Drawing 175 WLM 801-19, Rev C; Shell Expansion

Coast Guard Drawing 175 WLM 801-6, Rev H; Docking Plan

Coast Guard Drawing 175 WLM 920-001, Rev K, Hull Block 920 Panels

Coast Guard Drawing 175 WLM 940-001, Rev J, Hull Block 940 Panels

Coast Guard Drawing 175 WLM-528-001, Rev E, Plumbing and Interior Deck Drains Diagram

Coast Guard Drawing 175-WLB-167-001, Rev L, Structural Closures

Coast Guard Drawing 175-WLM 256-5, Rev -, Z-Drive Lube Oil Heat Exchanger Tube Bundle Replcmnt & Piping Mods

Coast Guard Drawing 175-WLM 568-001, Rev B, Bow Thruster Arrangement & Detail

Coast Guard Drawing 175-WLM 130-001, Rev -, Mods to Buoy Deck Incid to Hawser Pipe Cover

Coast Guard Drawing 175-WLM 256-001, Rev H, Seawater Cooling System Diagram

Coast Guard Drawing 175-WLM 256-001, Rev J, Seawater Cooling System Diagram

Coast Guard Drawing 175-WLM 256-001, Rev K, Seawater Cooling System Diagram

Coast Guard Drawing 175-WLM 256-003, Rev A, Seawater Cooling System, Fr 61 Fwd Blocks 910, 920, Coast Guard Drawing 175-WLM 256-003, Rev D, Seawater Cooling System, Fr 61 Fwd Blocks 910, 920, Coast Guard Drawing 175-WLM 256-004, Rev J, Seawater Cooling System A & D, Hull Blks 940-970

Coast Guard Drawing 175-WLM 256-012, Rev B, ASW System Piping Modifications

Coast Guard Drawing 175-WLM 320-1, Rev U, Electrical One-Line Diagram

Coast Guard Drawing 175-WLM 436-1, Rev H, Fire & Smoke Detection System Block, Isometric, and Elementary Wiring Diagram (Circuit SM)

Coast Guard Drawing 175-WLM 568-002, Rev N, Bow Thruster Detail

Coast Guard Drawing 175-WLM 568-002, Rev N, Bow Thruster Detail

Coast Guard Drawing 175-WLM 573-008, Rev C, Aton Tie Downs

Coast Guard Drawing 175-WLM 601-001, Rev T, General Arrangement, Inbd and Outbd Profiles

Coast Guard Drawing 175-WLM 601-03, Rev L, Booklet of General Plans

Coast Guard Drawing 175-WLM 635-001, Rev F, Hull Thermal & Acoustic Insulation Schedule

Coast Guard Drawing 175-WLM 635-1, Rev F, Hull Thermal & Acoustic Insulation Schedule

Coast Guard Drawing 175-WLM 910-04, Rev H, Hull Block 910 - Transverse Frames & Bulkheads

Coast Guard Drawing 175-WLM 920-001, Rev K, Hull Block 920 Panels

Coast Guard Drawing 175-WLM 930-001, Rev K, Hull Block 930 Panels

Coast Guard Drawing 175-WLM-167-001, Rev L, Structural Closures

Coast Guard Drawing 175-WLM-259-51, Rev _, Main Engine Combustion Air & Ventilation Modifications

Coast Guard Drawing 175-WLM-437-8, Rev G, HVAC Control Sys Block, Iso & Elementary Wiring Diagram

Coast Guard Drawing 175-WLM-505-002 Rev F Mechanical Remote Valve Operators Arrangement and Details

Coast Guard Drawing 175-WLM-512-1, Rev E, HVAC Diagram ix (Rev-0)

Coast Guard Drawing 175-WLM-512-11, Rev E, HVAC A & D, FR 70-50, Main Deck & Above, Hull Block 960

Coast Guard Drawing 175-WLM-512-12, Rev D, HVAC A & D, Frame 70-88 Main Deck & Above, Hull Block 970

Coast Guard Drawing 175-WLM-529-002 Rev G Main Drainage System Diagram

Coast Guard Drawing 175-WLM-601-001, Rev T, General Arrangement Inboard and Outboard Profiles

Coast Guard Drawing 175-WLM-625-001 Rev K, Windows and Portlights

Coast Guard Drawing 175-WLM-970-3, Rev B, Hull Block 970 Assembly

Coast Guard Drawing 225B WLB 601-002 Rev K, Booklet of General Drawings

Coast Guard Drawing 225B-WLB 601-001, Rev P, General Arrangements Inboard and Outboard Profiles

Coast Guard Drawing FL-1602-89, Rev -, Fleet 26” x 66” Weathertight Door

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

DESIGN

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 3446, Jun 2009, Doppler Speed Log, Model SRD-500 Dual Axis

Coast Guard Technical Publication (TP) 3498, Section A, Jul 2015, Buoy Chain Winch

Coast Guard Technical Publication (TP) 3610, Section 167-A, July 2002, Power Operated Cargo Hatch, Coastal Buoy Tender, Model No. D-WK-787

Coast Guard Technical Publication (TP) 3610, Section 167-A, Nov 2005, Hydraulic Cargo Hatch - Model No. D-WK-787

Coast Guard Technical Publication (TP) 3613, Oct 1997; Flexible Coupling

Coast Guard Technical Publication (TP) 3613, Tab 243-B, Bulkhead Seal

Coast Guard Technical Publication (TP) 3619, 13-AUG-98, Manufacturers Instruction Book-SWBS Group(s) 324

Coast Guard Technical Publication (TP) 3621, SWBS 436, June 2020, Fire Detection System - Operation, Installation and Maintenance Manual, July 2020

Coast Guard Technical Publication (TP) 3628, Mar 2017; Vol 4 of 9, Instruction Manual, Bow Thruster

Coast Guard Technical Publication (TP) 3631, Section 581-A, Sep 2013, Manufacturer's Instruction Book-SWBS Groups 573-581, Anchor Windlass

Coast Guard Technical Publication (TP) 3632, Section 582-A, March 2014, Manufacturer's Instruction Book-SWBS Groups 582-583, Aft Capstan

Coast Guard Technical Publication (TP) 3653, Jul 2013; SWBS 245, Section A; Z-Drive - Model 1350-H

Coast Guard Technical Publication (TP) 3653, Jul 2013; SWBS 245, Section A; Z-DRIVE - MODEL 1350-H

Fire Prevention and Response

NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation Details

NAVSEA Dwg 2803-980209, Plates, Label

Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3042, 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation x (Rev-0)

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes.

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC Electrical Motors

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses

OTHER REFERENCES

American Bureau of Shipping (ABS) Approved Chain, Accessory and Bar Manufacturing Facilities List, Oct 2016

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities

American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System Components - Health Effects

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects

American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2020, Recommended Practice for Personal Qualification and Certification in Nondestructive Testing

American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and Welding End

American Welding Society (AWS) D1.1, Structural Welding Code - Steel, Coated and Uncoated Galvanized Steel, Stainless Steels, and Non-Ferrous Metals

APM: If work is being done in DD, no cofferdam is needed; delete cofferdam protective measures paragraph 3.1.3 and above NAVSEA ref. Above NAVSEA ref is accessible on-line

ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D1330, 2022, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component Adhesives (AN)

ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Code of Federal Regulations (CFR) Title 29, Part 1910, Occupational Safety and Health Standards xi (Rev-0)

Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

Code of Federal Regulations (CFR) Title 40, Protection of the Environment

Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust- Petrolatum

Commercial Item Description (CID) A-A-59323, Rev A, Cloths, Cleaning, Low-Lint

Commercial Item Description (CID) A-A-59588, 2013, Rubber Silicone

Commercial Item Description (CID) A-A-59588, Jul 2005, Rubber Silicone

Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert

Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections

Federal Specification (Fed Spec) RR-C-271, Rev E, Dec 2010, Chain and Attachments, Welded and Weldless

Federal Specification (Fed Spec) RR-C-271, Rev E, Mar 2016, Chains and Attachments, Carbon and Alloy Steel

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2018 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-C-24633, Oct 2014, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded

MIL-DTL-23549, Sep 2016, Grease, General Purpose

MIL-F-24402, May 1995, Filters (Hydraulic), Filter Elements (High Efficiency), and Filter Differential Pressure Indicators, General Specification

MIL-PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application

MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application

MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant

MIL-STD-2003-3, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships & Submarines (Penetrations)

MIL-STD-2003-4, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships & Submarines (Cableways)

National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications xii (Rev-0)

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA- PRO-160, Nov 2011, Chapter 16, Cofferdams

Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA- PRO-160, Nov 2011, Chapter 16, Cofferdams

NAVSEA Drawing 803-1401890, Rev G, Scuttle, WT, Raised, Quick Acting, 18” Dia 35 PSI- Arrangement

NAVSEA Drawing 803-1401892, Rev J, Scuttle, WT, Raised, Quick Acting, 21” Dia

NAVSEA Drawing 803-6397268, Rev B, Doors Watertight, Quick Acting Arrangement

NAVSEA OP 4, Thirteenth Revision, May 2023, Ammunition and Explosives Safety Afloat

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

QPL-24667, Qualified Product List (Military) of Products Qualified Under Detail Specification MIL- PRF-24667, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C-6183B, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183B, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2020 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

Society of Automotive Engineers (SAE) AMS-G-6032, August 2020, Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2016, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning to Bare Metal xiii (Rev-0)

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), Power Tool Cleaning)

The Society for Protective Coatings (SSPC), Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2017, Waterjet Cleaning of Metals – Very Thorough Cleaning

The Society for Protective Coatings (SSPC)/NACE Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2004, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No. SSPC-SP 12/NACE No.5, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting Prior to Recoating

The Society for Protective Coatings SSPC-SP 10/NACE No.2, Near-White Blast Cleaning

This reference is only applicable if paragraph 3.7.2 is required.

Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker

Wartsila Defense, Inc. Technical Manual for Type ND Seal xiv (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

25 N Christie & Grey

Resilient Engine Mount PN: TSC T10 65/400 4 ea. 600.00

25 Y Christie & Grey Resilient Engine Mount

PN: TSC T10 65/800 4 ea. 600.00

25 N Vulkan RATO Flexible Coupling Element

(EG1721R000)

PN: 01-466-3015 2 ea. 12,020.00

28 N Diaphragm Assembly, ND Seal With O-Cord

(H76287-01-2)

NSN: 5360-01-572-6773 4 ea. 4.500.00

28 N Packing, Preformed (O- Cord) (H76287-01-2-2)

NSN: 5330-01-572-8893 4 ea. 125.00

30 Y Z Drive Alignment Tool NSN: 5220-01-F16-4720 1 ea. 3600.00 31 N Z-Drive Propeller Shaft

Seal Kit NSN: 5330-20-009-3957 2 ea. 31,116.67

31 N Z-Drive Steering Seal Kit

NSN: 5330-20-009-5500 2 ea. 2,379.50

31 N Clutch Overhaul Kit (New Clutch)

NSN: 2520-01-645-8279 2 ea. 9,055.00

33 N #3 Thrust Bearing Cooper Bearing, 02BCP110MMGR

NSN: 3040-01-F12-2610 2 ea. 10,902.00

34 Y **Z-Drive Hyd. Fluid Cooler

NSN: 4420-01-505-9267 2 ea. 7,725.00

34 Y **Z-Drive Lube Oil Cooler

NSN: 4420-01-603-3557 2 ea. 3,910.00

34 N Heat Exchanger, Gasket NSN: 5330-01-449-2451 2 ea. 22.53 34 N Heat Exchanger, Gasket NSN: 5330-01-449-2479 2 ea. 18.66 36 N ***Fathometer

Transducer, Shallow Water, 50-200 kHz

(Airmar Technology

SS505)

NSN: 5845-01-470-2500 1 ea. 343.63

37 Y ***Sperry SRD 500 Doppler speed log

NSN: 5999-01-472-7499 1 ea. 16504.43

39 N **8†Simplex Strainer

BF-150B, with T-bolt hinged cover)

2 ea. 20,000.00

39 N **3†Duplex Strainer NSN: 4730-01-643-2221 PN:

3-792FB (Mueller)

1 ea. 10,400.00

45 N Seal Kit, Thruster NSN: 2010-01-555-9048 1 ea. 4376.00 45 N Anode, Zinc NSN: 5365-01-495-5350 9 ea. 113.75 45 N **Seal Spacer NSN: 2010-01-495-6823 1 ea. 700.00 xv (Rev-0)

(B125SM44178)

45 N **Shaft Sleeve NSN: 2010-01-495-2638 1 ea. 5702.40 46 N Bearing, Roller, Tapered 3110-01-495-3354 1 ea. 10220.00

46 N Bearing, Roller, Tapered

3110-01-495-3344 1.ea. 1755.22

46 N Bearing, Roller, Tapered

3110-01-495-3334 1 ea. 4925.42

46 N Bearing, Roller, Tapered

3110-01-495-3465 1 ea. 3225.00

46 N Shaft Sleeve 2010-01-495-2638 1 ea. 5702.40 47 N Anchor Windlass

Overhaul kit NSN: 5430-01-546-4684 1 ea. 9,677.05

47 N Ball Valve NSN: 4820-01-013-3430 1 ea. 38.55 47 N Valve, Counterbalance NSN: 4820-01-F16-4571 PN:

CBEH-LKN-BCL Sun Hydraulics Corp

1 ea. 202.85

47 Y ** Motor, Hydraulic NSN: 4320-01-419-3520 1 ea. 2,577.98 47 N ** Valve, Linear, Directional Control NSN: 4810-01-511-3173 1 ea. 2,343.85

47 Y Hydraulic Brake NSN: 2530-01-F14-4033 P/N:

90B3C4G087

1 ea 1,189.44

79 Y *Transducer Cover Plate

N/A 2 ea. 50.00

87 N Coast Guard (C-G)

CGDR50TDRASS01

Flush Pad-eye Assembly: Coast Guard

(C-G) (CGDR50T01)

D-Ring (rated load 12,300 lbs.), welded strap, fabricated bowl.

NSN# 2020-01-682-7587 51

88 Y Semiconductor Device, Photo

NSN: 5961-01-599-4004 PN:

20/20MI-11SF

9 ea. 1,489.00

88 N Bracket, Mounting NSN: 5340-01-599-4015 PN:

20/20-005 (ST.ST.316L)

9 ea. 45.55

89 N Window, fixed, 24†x30†, S.S, 1/2†heat treated clear

2090-01-566-3759 / KS-

28560-17

1 ea. $2000 ea.

90 N Raised Watertight Scuttle, 18†dia, 12†coaming height

NAVSEA 803-1401890 2 ea. $3500

90 N Raised Watertight Scuttle, 21†dia, 12†coaming height

NAVSEA 803-1401892 1 ea. $4000

91 N Weathertight Steel Door 26†x66†, Right

Hand, w/ hasp and

USCG DWG FL-1602-89 2 ea. $6000 xvi (Rev-0) staple, 14†x18†fixed light

93 N Quick Acting Watertight Steel Door 30†x66†, Right Hand, 10 Dog w/ hasp and staple, w/ fixed light

NAVSEA Drawing 803- 6397268

1 ea. $8000

98 N Window, 24†x30†fixed, S.S, 1/2†heat treated clear, Item 15

2090-01-566-3759 / KS-

28560-17

2 ea. $2500

98 N Window, 24†x18†fixed, S.S, 1/2†heat treated clear, Item 16

2090-01-566-3766 / KS-

28560-18

2 ea. $2500

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xvii (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item

Title

2 Hull Plating, Side Scan, Ultrasonic Testing

3 U/W Body, Preserve, 100 percent

14 Appendages, U/W, Leak Test

16 Chain Lockers, Clean and Inspect

17 Tanks, MP Fuel Stowage and Overflow, Clean and Inspect

18 Tanks, MP Fuel Service, Clean and Inspect

21 Tanks, Ballast, Clean and Inspect

24 Hydraulically Operated Cargo Hatch, Inspect and Service

31 Z-Drive Propulsion Units, Overhaul

40 Sea Strainers, Duplex, All Sizes, Overhaul

41 Sea Strainers, Simplex, All Sizes, Clean and Inspect

43 Sea Bay, Clean and Inspect

46 Thruster Unit Bearings, Renew

47 Anchor Windlass, Inspect And Service

48 Anchor Chains and Ground Tackle, Inspect and Repair

54 Warping Capstan (Aft), Inspect and Service

79 Drydock

89 Chief Petty Officer Engineer Stateroom Window, Renew

94 Fuel Oil (FO) System Piping, Renew

96 Engine Room Demister, Inspect, Repair, and Preserve

97 Supply/Exhaust System, Renew xviii (Rev-0)

98 Exterior Window, Renew xix (Rev-0)

PRINCIPAL CHARACTERISTICS - TENDER

175' WLM, BUOY TENDER

PHYSICAL

Length overall 174' 8" Length between perpendiculars 155' 1" Depth 14' 8" Maximum beam 36' 0" Designed draft 8' 0" Mast height (above 8' waterline) 58' 8" Frame spacing 20" Full load displacement 855.15 Long Tons SW Light load displacement 719.78 Long Tons SW Minimum op condition displ 852.19 Long Tons SW

HULL

Hull material Steel

MACHINERY

Main propulsion Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM

Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM

Reduction gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio Shaft seal John Crane Type ND Shaft bearings Five pedestal mounted, Cooper split roller bearings Number of propellers 2 Number of blades 4 Diameter 57.1" Rudders None; Z-drive Ship's service generators Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800

RPM

Emergency diesel generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM

TANK CAPACITIES

Diesel oil capacity (100%) 16,385 gal Fresh water capacity (100%) 7,339 gal Lubricating oil (100%) 86 gal

1 (Rev-0)

00000_0226_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

2 (Rev-0)

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

3 (Rev-0)

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Strenx 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental

4 (Rev-0) requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Per…