About this file
This document contains the Special Provisions for the Woodford State Fish & Wildlife Area Septic System Improvements project in Woodford County, Illinois. The work under this contract includes the removal and replacement of existing septic system components, such as septic tanks, distribution boxes, and septic system piping, as well as HMA pavement removal and replacement, cleaning of existing septic field lines, surface restoration, and other miscellaneous work. The contract also includes requirements related to construction staking, subletting, construction inspection, existing utilities and drainage structures, disposal of materials, record drawings, and various construction materials and methods. The project is located on Conservation Lane west of Illinois Route 26 in Woodford County, and work is to commence within 30 calendar days of the contract execution.
The contract includes specific provisions for the scheduling of work, including coordination with third-party utilities, as well as requirements for project scheduling submittals. Disposal of materials must comply with all applicable local, state, and federal regulations, and the contractor is responsible for proper disposal of all materials removed from the project site. Payment for the work will be made as a lump sum for the "Rehabilitate Existing Septic Systems, Complete" item, which includes all labor, materials, and incidental work necessary to perform the various components of the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2Standard Terms and ConditionsV 23.2~57.pdf | ||
| Attachment 1 - Plans~3.pdf | ||
| Attachment 3 - County Private Sewage Permit Forms.pdf | ||
| Scope of Work - Large 2~11.docx | DOCX document | |
| 2SMALL CONSTRUCTION BID FORM1~87.docx | DOCX document | |
| 2Standard Illinois Certifications-v.23.1~57.docx | DOCX document | |
| Attachment 4 - Contractor Schedule of Values.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Special Provisions
The "Standard Specifications for Road and Bridge Construction" prepared by the Department of Transportation of the State of Illinois and adopted by said Department on January 1, 2022, and the Supplemental Specifications prepared by the Department of Transportation of the State of Illinois and adopted on January 1, 2022, by said Department to supplement the “Standard Specifications for Road and Bridge Construction”, shall govern the bidding, construction and execution of the proposed project. Where the term “Department” appears in the Specifications, the “Illinois Department of Natural Resources” shall be substituted therefore, and where any term for an employee of the Department is used, the designated Illinois Department of Natural Resources employee shall be substituted, therefore. Style, type and grade of all materials used for construction shall be approved by the Illinois Department of Natural Resources prior to bidding, ordering or placing any materials.
Herein after the terms "Owner", “Ownership”, “Department”, "Engineer", or any derivatives of such, shall mean the Illinois Department of Natural Resources or its designated representative and the term "Contractor" shall mean the entity who proposes to perform the work herein described or its designated subcontractors.
The following Special Provisions supplement the said specifications and, in case of conflict with any part or parts of said specifications, these Special Provisions shall take precedence and shall govern:
| Woodford | State | Fish | & | Wildlife | Area |
| Septic | System | Improvements |
Woodford County #1‐22‐011
LOCATION OF PROJECT
The project is located on Conservation Lane west of Illinois Route 26 in Woodford County.
DESCRIPTION OF WORK
The work under this contract includes, but is not limited to:
‐ Removal and Replacement of existing septic system components including:
o Septic Tanks (2) o Distribution Boxes (2) o Septic system piping (from septic tanks to septic fields)
‐ HMA pavement removal and replacement ‐ Cleaning existing septic field lines ‐ Surface Restoration ‐ Miscellaneous work as needed
CONSTRUCTION STAKING
The Department shall be responsible for setting and staking all grades as indicated on any applicable plans and cross sections. Any deviation from plans and grades without written authorization from the Department will not be accepted for payment until the Contractor has corrected the construction to the satisfaction of ownership.
CONTRACT SUBLETTING‐COOPERATION AMONG SUBCONTRACTORS
Public Acts 96-0795, 96-0920, and 97-0895 enacted substantial changes to the provisions of Code (30 ILCS 500). Among the changes are provisions affecting subcontractors. The Contractor awarded this contract will be required as a material condition of the contract to implement and enforce the contract requirements applicable to subcontractors that entered into a contractual agreement with a total value of $50,000 or more with a person or entity who has a contract subject to the Code and approved in accordance with article 108.01 of the Standard Specifications for Road and Bridge Construction.
If the Contractor seeks approval of subcontractors to perform a portion of the work, and approval is granted by the Department, the Contractor shall provide a copy of the subcontract to the Illinois Department of Natural Resources upon request within 15 calendar days after execution of the subcontract.
Financial disclosures required pursuant to Sec. 50-35 of the Code must be submitted for all applicable subcontractors. The subcontract shall contain the certifications required to be made by subcontractors pursuant to Article 50 of the Code. This Notice to Bidders includes a document incorporating all required subcontractor certifications and disclosures for use by the Contractor in compliance with this mandate. The document is entitled State Required Ethical Standards Governing Subcontractors.
CONSTRUCTION INSPECTION
Any work performed without the presence of an Owner’s designated representative to inspect said construction shall not be accepted for payment as directed by the Owner. Contractor shall notify Ownership a minimum of 24 hours in advance of the start of construction or the continuation of construction following a pause in work.
EXISTING UTILITIES AND DRAINAGE STRUCTURES LOCATIONS
Ownership does not guarantee the completeness or accuracy of the information regarding gas, water service lines, buffalo boxes, pipe culverts, inlets, power lines, poles or any other existing utilities or drainage structures. The contractor shall make their own investigation to verify or determine the existence, nature and location of all utilities on the site that may interfere with construction before commencing work. Care should be taken while working near these utilities to prevent their damage.
STARTING DATE
Work on the project shall commence within 30 calendar days of the execution of the contract. The Contractor shall contact the Department within the 30-day period to schedule a preconstruction conference prior to the beginning of actual construction operations.
FAILURE TO COMPLETE WORK ON TIME
The Schedule of Deductions for Each Day of Overrun in Contract Time shall be according to Section
108.09 of the IDOT Standard Specifications.
SCHEDULING OF WORK
Contractor acknowledges that alterations to the construction sequencing and schedule may be required for coordination with any third-party utilities. Contractor shall be responsible for any necessary coordination with utility companies. Any delay to the contract caused directly or indirectly by third party utilities shall not be cause for adjustment to the contract sum.
Contractor shall be responsible for providing updated project schedules in the provided format to be submitted each Friday by the end of business hours. Schedules shall be completed electronically using the format provided. Schedules shall be completed to the quality and satisfaction of project ownership.
DISPOSAL OF CLEAN CONSTRUCTION AND DEMOLITION DEBRIS (CCDD)
Per guidelines set by the Illinois Environmental Protection Agency (IEPA) (Public Act 96-1416, effective July 30, 2010) construction and disposal practices at jobsites and at CCDD sites have been changed as of July 30, 2010.
As stated by the IEPA: “Clean Construction and Demolition Debris (CCDD) is uncontaminated broken concrete without protruding metal bars, bricks, rock, stone, or reclaimed asphalt pavement generated from construction or demolition activities. When uncontaminated soil is mixed with any of these materials, the uncontaminated soil is also considered CCDD. Uncontaminated soil that is not mixed with other CCDD materials is not CCDD.”
Under this contract, material to be removed from the jobsite shall be disposed of at the contractor’s expense following all applicable local, state and federal requirements as well as any requirements set forth by the Illinois Environmental Protection Agency and the Illinois State Pollution Control Board.
These legal requirements specifically include but are not limited to the Illinois Environmental Protection Act (415 ILCS 5), IEPA CCDD Guidelines (Public Act 96-1416), and Title 35 of the Illinois Administrative Code.
It shall be the contractor’s responsibility to properly dispose of all material to be removed from the project limits including both CCDD and non CCDD material. Any additional costs incurred to the contractor for the disposal of material shall be considered included in the various excavation and removal pay items and will not be considered for additional payment of any kind. Such additional incidental costs may specifically include but are not limited to trucking and hauling, off-site material handling, over-weight permits, tipping fees, regulatory fees and surcharges, any applicable taxes, and any disposal costs including those for hazardous and non-hazardous special waste. No special pay item for Non-Special Waste Removal, Special Waste Removal, or Hazardous Waste Removal has been included in this contract, but the requirements for removal of such materials must still be in accordance with Articles 202 and 669 of the Standard Specifications for Road and Bridge
Construction.
Contractor shall make every effort to re-use all excavated material on site for trench backfill, parkway restoration, or any other uses within the scope of the contract plans and specifications. Re-use of material for any reason shall be approved by the owner prior to placement of material at the jobsite.
RECORD DRAWINGS
The Contractor shall keep a set of the plans on-site to be maintained as the official project Record Drawings. The Contractor shall mark up the set of plans with any revisions in the drawings on a daily basis.
The dimensions shall be indicated from physical features indicated on the drawings.
The contractor shall deliver the Record Drawings to the Department, along with the final request for payment on the project.
SAW CUTS
Work shall consist of sawing existing pavements to such a depth that when the pavement is removed, a clean neat edge will result with no spalling of the remaining pavement. Saw cutting shall be performed at all locations where pavement is removed and will be replaced. This work item shall be considered incidental to construction and no further compensation will be allowed.
MOBILIZATION
Refer to Article 671.02 of the Standard Specifications for Road and Bridge Construction and delete this paragraph in its entirety.
REMOVE EXISTING SEPTIC TANK
This work shall be constructed in accordance with Illinois Plumbing Code and La Salle County Health Department Code/Requirements.
Complete excavation and removal of all material necessary to remove and dispose of the existing septic tanks at an approved facility off-site. This work shall be done by a licensed and bonded septic pumping contractor. This work shall conform to Section 202 and Section 440 of the Standard Specifications.
Excavation through rock shall be considered incidental and no separate payment shall be made for rock excavation.
4” PVC SEPTIC PIPE
This work shall include sewer pipe, pipe bedding, trench backfill, making connections to existing structures, patching existing structures at new connections, stoppers and plugs, and any other incidental costs not specifically included under other items.
All work shall conform to details shown on the drawings, or to ordered modifications therefore, and to applicable portions of Sections 202 and 550 of the Standard Specifications and in accordance with the requirements of the Department.
All pipe and joints shall be tested by an approved testing laboratory in accordance with the most recent cited standard methods of AASHTO or ASTM at the Contractor's expense. Two (2) copies of each test certificate shall be promptly furnished to the Department.
Where unsuitable soil is encountered, pipe bedding of 4" well-graded durable gravel, crushed stone will be required. Trench backfill to the subgrade elevation above the top of the pipe will be required on pipe under roadway areas.
The Contractor shall be responsible for maintaining the current level of service to all users connected to the existing sanitary sewer.
Excavation through rock shall be considered incidental and no separate payment shall be made for rock excavation.
SEPTIC TANK ‐ 750 GALLON
This work shall be in accordance with Section 905.40 of the TITLE 77: PUBLIC HEALTH CHAPTER 1:
DEPARTMENT OF PUBLIC HEALTH SUBCHAPTER r: WATER AND SEWAGE PART 905 PRIVATE
SEWAGE DISPOSAL CODE.
This work shall include excavation of pit, bedding, trench backfill, making connections to between tanks and any other incidental costs related to the materials and construction of the septic tank.
Before ordering the septic tanks Shop Drawings shall be submitted for review and approval.
DISTRIBUTION BOX
This work shall be in accordance with Section 905.50 of the TITLE 77: PUBLIC HEALTH CHAPTER 1:
DEPARTMENT OF PUBLIC HEALTH SUBCHAPTER r: WATER AND SEWAGE PART 905 PRIVATE
SEWAGE DISPOSAL CODE.
This work shall include excavation of pit, bedding, trench backfill, making new connections to dosing chamber and any other incidental costs related to the materials and construction of the distribution boxes.
Before ordering the distribution box Shop Drawings shall be submitted for review and approval.
CLEAN EXISTING SEPTIC FIELD LINES
This work shall include cleaning the interior of the existing perforated-pipe septic field lines and flushing out the wastewater and built-up debris. The lines shall be cleaned by low pressure jetting and vacuuming to remove the built-up sludge, followed by chemical treatment. After the low-pressure jetting and vacuuming operation is complete, hydrogen peroxide shall be introduced into the field line by inserting a chemical feed line into each field line lateral to the ends/extents of each lateral. After the feed line has reached the extents of the laterals, it shall be pulled back while injecting and releasing the hydrogen peroxide. Excavation will be required at each lateral in order to provide a means by which the low-pressure jetting line and chemical feed line can access the field lines.
After the field line cleaning operation is complete, the contractor shall televise each field line to confirm that it has been cleaned to the satisfaction of the Illinois Department of Natural Resources and the Woodford County Health Department. A copy of the video shall be provided to the IDNR.
The contractor shall submit a shop drawing to fully describe the septic field line cleaning operation prior to beginning the work.
| NITROGEN | FERTILIZER | NUTRIENT, | PHOSPHOROUS | FERTILIZER | NUTRIENT, | & |
| POTASSIUM | FERTILIZER | NUTRIENT |
This work shall be in accordance with Section 250 of the Standard Specifications for Road and Bridge Construction.
TRENCH BACKFILL
This work shall be in accordance with Section 208 of the IDOT Standard Specifications and details on the plans. Trench backfill shall be provided in any location where trenching for the installation of pipe culverts is under or within 2 feet of any edge of pavement, sidewalk, or driveway.
SEEDING, CLASS 1B LAWN MIXTURE
This work will consist of Furnishing and Placing grass seed mixture and hydraulic mulch that meets the requirements of section 250 and 251 of the Standard Specifications for Road and Bridge Construction in all areas disturbed as part of the contract including areas used by the contractor.
The contractor shall apply to any seeded area, light duty hydraulic mulch as prescribed in MULCH METHOD 3. This work shall be incidental to SEEDING, CLASS 1B LAWN MIXTURE, and no other compensation shall be considered.
Revise Note 7 of the BDE Special Provisions to read:
The Contractor guarantees a minimum of 80 percent uniform growth over the entire seeded area(s) after one growing season. The guarantee shall be submitted to the Engineer in writing prior to performing the work. After one growing season, areas not sustaining 80 percent uniform growth shall be inter-seeded or reseeded, as determined by the Engineer, at the Contractor's expense.
AGGREGATE BASE COURSE, TYPE B
This work shall be constructed in accordance with Section 351 of the Standard Specifications to a minimum compacted thickness of 8-inches or 12-inches where indicated on the plans. The material shall have a gradation equal to CA-6 except that said material shall be crushed gravel or crushed stone. Preparation for paving will include but not be limited to reshaping, recompacting, removal of segregated aggregates, addition of aggregates as needed and re-priming if needed.
HOT‐MIX ASPHALT SURFACE COURSE, IL 9.5, MIX “D”, N50
This work shall be constructed in accordance with Section 406 of the Standard Specifications.
Recycled material will not be allowed in the surface mix unless an equivalent or superior IDOT-approved mix with RAP is approved by the Owner. The HOT-MIX ASPHALT SURFACE COURSE, IL 9.5, N50, MIX C utilize the IL-9.5 mixture composition unless otherwise directed by the Owner.
Mix designs and verification of IDOT certification must be submitted to the Illinois Department of Natural Resources for approval prior to Notice to Proceed on contract.
Vibrating Rollers will not be allowed. In the absence of a vibratory roller, densities shall be 93% minimum unless specified by the Owner.
TOPSOIL FURNISH AND PLACE
This work shall be in accordance with Sections 202, 204 and 211 of the Standard Specifications.
This work shall consist of placing 4” topsoil at all areas disturbed as part of the contract including areas used by the contractor. The contractor may choose to use native topsoil from the site. Any excess topsoil not required to be placed per the plans, shall be removed from the site. Any shortage of native topsoil will require the haul of additional topsoil to complete the work. Any work required including stripping, stockpile hauling and placing shall be considered part of this pay item.
EROSION CONTROL, COMPLETE
This work shall conform to the applicable portions of section 280 of the Standard Specifications and the attached details, and all requirements set forth in the General NPDES Permit No. ILR10. The management practices, controls, and other provisions contained in the erosion and sediment control plan must be at least as protective as the requirements contained in the Illinois Urban Manual.
The Contractor will be responsible for erosion and sediment control and any discharge from the work area as designated on the construction plans. If the contractor fails to repair NPDES permit non-compliance items and/or eliminate discharge as directed by the Department, in the time specified by the Department, a fine of $750 per violation per day will be deducted from the pay request.
PERIMETER EROSION BARRIER
This item shall include all labor, materials and equipment needed for the installation, maintenance, removal, quantification, and disposal of the temporary erosion control system. This item must be installed, inspected and approved before construction activities begin, and proper protection must be maintained until the site is deemed stabilized by the ENGINEER and the volume of sediment collected is quantified and documented.
TRAFFIC CONTROL AND PROTECTION, (SPECIAL)
This work shall consist of furnishing, installing and maintaining all signs, signals, temporary pavement markings, other required traffic control markings, barricades, warning lights, and other devices which are to be used to regulate, warn or guide traffic during construction of this improvement. All work shall be in conformance with the current edition of the Illinois Department of Transportation's Manual on Uniform Traffic Control Devices for Street and Highways.
The CONTRACTOR will be required to furnish all traffic control devices necessary for the convenience and protection of vehicular and pedestrian traffic. Whenever the operation of the CONTRACTOR endangers or interferes with vehicular traffic or pedestrians, as determined by the ENGINEER, the CONTRACTOR shall furnish any additional traffic control devices necessary to direct and protect his workers at no extra cost to satisfy the requirements of the ENGINEER. The CONTRACTOR will be required to furnish the necessary flaggers as specified in the Plans or required by the ENGINEER on a continuous basis whenever construction operations are in progress.
The CONTRACTOR will be responsible for the proper location, installation and arrangement of all traffic control devices furnished by him. Whenever operations indicate that relocation of a proposed or existing traffic control device is advisable, as determined by the ENGINEER, the CONTRACTOR shall remove, relocate and reinstall the device in question.
All advance warning signs for lane closure, intermediate information signs and standard signs shall be installed in accordance with Illinois Highway Standard Division 700.
The “WORKERS” (W21-1a (0)-48) signs shall be replaced with symbol “Right or Left Lane Closed Ahead” (W4-2R or L (0)- 48) signs.
All advance warning signs and traffic control devices shall be removed or covered by the CONTRACTOR when such signs and devices are not in effect or at the direction of the ENGINEER.
The CONTRACTOR will be responsible for the maintenance of all traffic control devices installed by him as designated in the Plans and Specifications or as required by the ENGINEER. The CONTRACTOR will provide surveillance of all barricades, barrels, warning signs and lights which he has installed on a 24-hour a day basis for each day of this contract. In the event of severe weather conditions, the CONTRACTOR shall be required to furnish any additional personnel required to maintain all traffic control devices as required by the ENGINEER. Surveillance shall mean checking control devices periodically, but not less than once every 12 hours.
The CONTRACTOR shall provide the Department with the name, address and telephone number of two (2) persons who will be responsible for maintaining the traffic control devices and who will be available to the Department on an immediate basis 24 hours a day. If, for any reason, one or both of the persons become unavailable, the CONTRACTOR shall furnish the same information for other individuals who will be available.
The CONTRACTOR will be required to remove all traffic control devices which were furnished, installed or maintained by him under this contract and such devices shall remain the property of the CONTRACTOR upon said removal. All traffic control devices must remain in place until specific authorization for removal is received from the Department.
REHABILITATE EXISTING SEPTIC SYSTEMS, COMPLETE
This item shall include all labor, materials, equipment, mobilization, transportation, handling and incidental work necessary to remove existing septic system components, clean existing septic field lines, furnish and install the following items previously described in these Special Provisions:
Saw Cuts Mobilization Remove Existing Septic Tank 4” PVC Septic Pipe Septic Tank – 750 Gallon Distribution Box Clean Existing Septic Field Lines Nitrogen, Phosphorus and Potassium Fertilizer Nutrients Trench Backfill Seeding, Class 1B Lawn Mixture Aggregate Base Course, Type B Hot-Mix Asphalt Surface Course, IL 9.5, Mix “D”, N50 Topsoil Furnish and Place Erosion Control, Complete Traffic Control and Protection (Special)
| Basis of Payment: This work shall be paid for at the contract LUMP | SUM price for REHABILITATE | ||
| EXISTING | SEPTIC | SYSTEMS, | COMPLETE. |