This is a Statement of Work (SOW) for the CDC/SAC Shed Disposal and Replacement Project at Schriever Space Force Base in Colorado. The project requires replacing twelve existing playground sheds in Building 60 with new wood A-frame sheds that include viewing panels to enhance child safety. The replacement sheds must be 8'x8', have a 7'4" wall height, include 18"x36" single-pane windows, 5' double doors with latches, and feature premium specifications such as water-resistant flooring, LP 50-year smart siding, 30-year architectural shingles, and hurricane clips.
The project timeline is set for completion by 30 June 2025, with the contractor responsible for removing existing structures through the DRMO process and installing new sheds on current concrete slabs across five different playgrounds (infant, pre-toddler, toddler, pre-school, and school-age). The sheds must be hail-resistant and comply with all federal, state, county, and base safety regulations. The contractor will need to coordinate site access, provide employee identification, and follow specific security and safety protocols while working on the Schriever Space Force Base premises.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTROLLED UNCLASSIFIED INFORMATION
STATEMENT OF WORK (SOW)
CDC/ SAC Shed Disposal and Replacement Project
Bldg 60 Rm Playground Schriever SFB, CO
Rev. 12 MARCH 2025
Prepared By
50 FSS/FSY
60 Hahn Ave, Bldg. 60
Schriever SFB, CO 80912-1020
CDC/ SAC Shed Disposal and Replacement Bldg 60
Rm Playground
Page. 1
1. SCOPE.
The CDC and SAC have a project to replace the twelve (12) existing playground sheds for Child and Youth Programs (FSY) in building 60. The new replacement sheds will include viewing panels (windows) to enhance the safety of children while on the playground. The current sheds lack viewing panels, as previously purchases of FSY sheds were made without them.
The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOW. All equipment, supplies, and materials provided shall be new and not refurbished.
2.0 REQUIREMENTS.
2.1 GENERAL REQUIREMENTS.
2.1.1 Safety Requirements.
The contractor shall comply with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.
2.1.2 Site Coordination.
The Contractor shall meet with the base safety officer upon arrival on site for review of the specific safety requirements prior to installation.
2.1.2.1 Confined Space.
The Contractors and Sub-contractors entering confined spaces on Schriever SFB, CO are responsible for the safety of their personnel and for their own permit space program as outlined in AFMAN 91-203. All confined space operations must be coordinated with the Base Fire Department prior to start of work. The primary Contractor is responsible for all Sub-contractor confined space operations.
2.1.2.2 Accident/Incident Reporting and Investigation.
The Contractor shall record and report all facts relating to each instance of injury to either Contractor or Government personnel. Notification shall be provided to the 50 FSS/FSY Project Manager and the Base Safety Office unless otherwise stated in the SOW. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
2.1.3 Security Requirements.
The Contractor shall process and provide a Site Visit Request Letter to 50 FSS/FSY within 5 calendar days after contract award. This letter shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who will be performing work under this SOW.
This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.
2.1.3.1 Security Clearances.
Stated work and associated products shall be performed at the UNCLASSIFIED level. However, some of this work may take place in secure areas where Contractor employees must be always escorted. The Contractor must coordinate access to secure areas at least five (5) calendar days ahead of time. It is the Government’s responsibility to provide escorts.
2.2 SPECIFIC REQUIREMENTS.
As indicated in this SOW Child and Youth Programs needs twelve replacement sheds with viewing panels at Bldg. 60 to enhance the safety of children while on five (5) playgrounds.
CDC/ SAC Shed Disposal and Replacement Bldg 60 Rm Playground Page. 2
2.3 Shed Requirements.
Listed below is the requirements for the twelve (12) sheds for Bldg 60, five (5) playgrounds
2.3.1 Existing Sheds.
There are 12 existing sheds previously installed on concrete slabs. Using the current concrete slabs, these replacement shed will be installed with viewing panels.
The contractor shall removal and dispose of existing structures through the DRMO process.
The contractor shall ensure the replacement sheds fit on current concrete slabs to enhance the safety of children at Bldg. 60, while on 5 different playgrounds.
The contractor shall ensure compliance with specific characteristics, including but not limited to, for the 12 replacement sheds at Bldg. 60, five (5) different playgrounds.
The contractor shall ensure all materials are hail resistant, to include but not limited to roof, siding, windows, doors etc.
The contractor will verify that the current concrete slabs were good prior to installation of replacement sheds.
Current structures sit on concrete sidewalks on the perimeter of infant, pre-toddler, toddler, pre-school, and school age playgrounds.
Timeline of project: 30 JUNE 2025
3.0 GENERAL INFORMATION.
3.1 Period of Performance.
3.2 Place of Performance.
The place of performance is Schriever SFB, CO.
Page. 3
Page. 4
CDC Sheds Salient Characteristics Qty: 12 Description: Wood A-Frame Shed with premium features water resistant flooring, a standard wall height of 7’ 4 ¼’’, and metal threshold as you enter with window in door and on each end.
Timeline: 30 JUNE 2025 Outside:
Size: 8WX8L Wall Height: 7’4” Faceboard: 4” Vent: 8”X8” on front and back of structure Overhang: 5” overhang on eaves Runners 4X4 Pressure Treated Runners Floor Joists: 2X4-16” OC Floor Joists Metal Threshold Trim: 3” Door: 5’ double door with latch – 5’ from ground (Windows can be in the doors of the structure or on each side of the structure. If windows are in doors – no additional window is needed.)
OR
Windows: 18X36 Single Pane back end – 5’ from ground (Essentially, we need to be able to see into the structure without having to stand on a ladder or step stool to see in. We should be able to walk up to the window to see into the structure.)
Dripedge: Aluminum drip edge roof perimeter Inside:
Hurricane clips Roof trusses with steel plates 2’x4 framing under flooring 7/16” OSB roof sheathing 2X4-16” OC wall framing Features:
LP 50 Year Smart siding 30-year architectural shingles Engineered room trusses with steel plates Water resistant engineered subfloor Primer plus two coats of paint Siding Color: Neutral Trim Color: Neutral Shingle Color: Gray
There are existing fiber optic cables installed by the SFS maintenance contractor. Using these cables requires the addition of breakout kits, connectors, and fusion splicing to complete the requested path.