United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

RENOVATE AAO OFFICES

PACIFIC WEST AREA

ALBANY, CA

Date: February 7, 2023

STATEMENT OF WORK

1.0 CONTRACT PROJECT:

a. Project Title: Renovate AAO Offices

b. Project Location: Pacific West Area 800 Buchanan St, Albany, CA

2.0 PROJECT CONTACT PERSONS:

a. CONTRACTING OFFICER (CO):

Lam Pham

USDA-ARS-PWA

Email: lam.pham@usda.gov Tel. No.: 510-559-6307

b. LOCATION MONITOR (LM):

Ken Cushman

USDA-ARS-PWA

800 Buchanan Street Albany, CA 94710 Email: ken.cushman@usda.gov Tel. No.: 510-529-5921

c. CONTRACTING OFFICERS REPRESENTATIVE (COR):

Peter Lane

USDA-ARS-PWA

Email: peter.lane@usda.gov Tel. No.: 510-559-6340

d. AREA SAFETY AND HEALTH MANAGER Ken Cushman

USDA-ARS-PWA

Email: ken.cushman@usda.gov Tel. No.: 510-529-5921

e. ENGINEERING PROJECT MANAGER (EPM) Peter Lane

USDA-ARS-PWA

800 Buchanan St. Albany, CA 94710

Email: peter.lane@usda.gov Tel. No.: 510-559-6340 mailto:ken.cushman@usda.gov mailto:peter.lane@usda.gov mailto:ken.cushman@usda.gov mailto:peter.lane@usda.gov

3.0 PROJECT DESCRIPTION:

The Area Administrative Office (AAO) for the Pacific West Area (PWA) of the Agricultural Research Service (ARS) is renovating offices spaces as part of an office consolidation.

Renovate offices according to the project specifications and drawings. Work includes carpet, hard flooring, painting, interior wall remodeling, mechanical, electrical, IT and other work as described in the project specifications and drawings.

4.0 PROJECT REQUIREMENTS:

a. Do not disturb hazardous materials and report condition immediately to the Contracting Officer’s Representative (COR) regarding potentially hazardous conditions that are uncovered. Stop work in the area of the questionable material or condition until identification and direction is provided.

b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.

c. Access the site between 8:00 am and 4:00 pm Monday through Friday excluding federal holidays. Contractor staff must sign-in on the first day of arrival and then sign-out on the final day of the project, upon completion. All Contractor personnel on-site must be US Citizens or permanent residents.

4.1 Background & Site Description:

The Western Regional Research Center (WRRC) building has several federal tenants, including the AAO offices. The AAO provide administrative support to all ARS locations within PWA. The AAO is consolidating and reducing office space in the WRRC building to better meet mission needs and current personnel numbers. This project will renovate the new or existing AAO offices to enable this office move. A separate contract will provide and install integrated workstations and standalone office furniture.

4.1 Bid Schedule:

Provide all labor, equipment and materials to perform this Statement of Work and Schedule of Items.

Description Units Quantity Total

All work not otherwise specified LS 1 Room 2020 sound wall LS 1

3025/3025A cover metal partition wall LS 1 3032 flooring and base LS 1

4.2 Description of Work:

See attached plans and specifications.

4.3 Government Furnished Equipment\Services

a. Government will furnish a reasonable amount of electricity and water.

5.0 GENERAL REQUIREMENTS:

5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

The Contractor shall obtain building permit from the City of Albany and coordinate inspections.

5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Government prior to starting demolition operations.

Contractor shall legally dispose all any materials removed that will not be retained.

5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor and Engineering Project Manager for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements.

Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.

5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor.

5.6 Protection of Work and Property/Safety Requirements:

a. Contractor shall furnish an Injury-Illness Prevention Plan (IIP) (APP) in accordance with California and OSHA requirements ten days after contract award. SSSP / APP shall be approved by the Government before construction work commences.

b. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.

c. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

d. Contractor is responsible for verifying location of any underground utilities and is responsible for any damaged caused to such utilities.

5.7 Temporary Facilities:

a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.

b. Should the Contractor require any power or utility shutdowns during construction, the

Contractor shall obtain approval for such shutdown from the Location Monitor and Engineering Project Manager fourteen (14) calendar days prior to the need.

5.8 Materials and Equipment:

a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.

b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the Government.

c. Government will not furnish any labor or equipment to unload or move materials or supplies.

5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.

5.10 Warranty:

a. Submit data concerning the standard one year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO

FINAL PAYMENT (other documents may also be required):

a. General contractor’s minimum one (1) year warranty on work.

b. Release of liens

c. Final Invoice

6.0 Project Schedule:

All work except 1025/2020 doors must be completed within 45 calendar days from Notice to

Proceed. The 1025/2020 doors must be completed within 5 calendar days after furniture is installed by 15 June 2023.

Do not start construction in room 3025 and 3025A until room 3032 is complete. Allow

Government 5 calendar days to relocate from 3025 and 3025A to 3032.

7.0 Attachments

- Furniture plan

8.0 Figures

Room 2020, SE corner facing NW

Room 2020, SE corner facing W

Room 2020, NW corner facing E

Room 2020, SW corner facing E

Room 2022, doorway facing E

Room 2023, doorway facing W

Room 2023, mid-room facing E

Room 2024, doorway facing E

Room 2024, mid-room facing W

Room 3025, doorway facing W

Room 3025A, mid-room facing W

Room 3032, hallway facing S

LFH

WB

WB

LFH

WB

WB

LFH

WB

WB

LFH

WB

WB

DRAWN

DESIGNER

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DWG SHEET NO.

OFSHEET

United States Department of Agriculture Agricultural Research Service

2/1 0/2

3 1 5:

P

ET

ER

.L

AN

E C:

\U

SE

RS

\P

ET

ER

.L

AN

E\

ON

ED

RI

VE

US

DA

\A

LB

AN

Y\

FY

M

OV

E

OU

T\

RE

NO

VA

TI

ON

S\

DR

AW

IN

GS

\A

AO

R

EN

OV

AT

IO

N

X1 7.D

W G;

02/10/2023

P. LANE

P. LANE

K. CUSHMAN

G-01

005001

RENOVATE AAO OFFICES

USDA AGRICULTURAL RESEARCH SERVICE

PACIFIC WEST AREA

ALBANY, CA

PROJECT LOCATION

PROJECT LOCATION

800 BUCHANAN ST

ALBANY, CA

AREA MAP

LOCATION MAP

INDEX OF SHEETS

SHEET SHEET TITLE DATE

G-01 COVER SHEET

A-01 2ND FLOOR PLAN

A-02 3RD FLOOR PLAN

A-03 IT/AV PLAN

A-04 GENERAL NOTES AND SPECIFICATIONS

2ND FLOOR KEY MAP

3RD FLOOR KEY MAP

PROJECT LOCATION

PROJECT

LOCATION

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 2030A

AutoCAD SHX Text 2030B

AutoCAD SHX Text 2006A

AutoCAD SHX Text 2006B

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 2200C

AutoCAD SHX Text 2200D

AutoCAD SHX Text 2200F

AutoCAD SHX Text 2200A

AutoCAD SHX Text 2201A

AutoCAD SHX Text 2201F

AutoCAD SHX Text 2201D

AutoCAD SHX Text 2201C

AutoCAD SHX Text 2200B

AutoCAD SHX Text 2201B

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 3015A

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 3002A

AutoCAD SHX Text 3004A

AutoCAD SHX Text 3006A

AutoCAD SHX Text 3010A

AutoCAD SHX Text 3030A

AutoCAD SHX Text

AutoCAD SHX Text 3025A

AutoCAD SHX Text 3023A

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 3200C

AutoCAD SHX Text 3200D

AutoCAD SHX Text 3200F

AutoCAD SHX Text 3200A

AutoCAD SHX Text 3201A

AutoCAD SHX Text 3201F

AutoCAD SHX Text 3201D

AutoCAD SHX Text 3200G

AutoCAD SHX Text 3201G

AutoCAD SHX Text 3201C

11'-9" 12'

'-6

12' 12' 24'-6"

'-6

17 17

DRAWING TITLE

PROJECT NAME

DRAWN

DESIGNER

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DWG SHEET NO.

OFSHEET

United States Department of Agriculture Agricultural Research Service

2/1 0/2

3 1 5:

P

ET

ER

.L

AN

E C:

\U

SE

RS

\P

ET

ER

.L

AN

E\

ON

ED

RI

VE

US

DA

\A

LB

AN

Y\

FY

M

OV

E

OU

T\

RE

NO

VA

TI

ON

S\

DR

AW

IN

GS

\A

AO

R

EN

OV

AT

IO

N

X1 7.D

W G;

RENOVATE AAO

OFFICES

PACIFIC WEST AREA

800 BUCHANAN ST

ALBANY, CA

2ND FLOOR PLAN

02/10/2023

P. LANE

P. LANE

K. CUSHMAN

A-01

005002

ABBREVIATIONS AND NOTES

CPT-1: CARPET

CLN-1: CLEAN EXISTING CARPET

RB-1: RUBBER BASE

PNT-1: PAINT ALL INTERIOR WALLS

PNT-2: SPOT/TOUCH UP PAINT

NIC: NOT IN CONTRACT

KEY NOTES

1. FILL IN (2) INTERIOR WINDOWS, EACH APPROX 44" x 44". MATCH EXISTING WALLS

AND PAINT.

2. SWITCH DOORS AND LOCK HARDWARE BETWEEN ROOM 1025 AND 2020. THIS ITEM

MUST BE COMPLETE AFTER FURNITURE INSTALL IN ONE DAY TO MAINTAIN

SECURITY

3. FILL IN INTERIOR DOOR. MATCH EXISTING WALLS AND PAINT.

4. REMOVE LOOSE 12X12 CEILING TILES, APPROX QTY 6

5. REPLACE 2x4 CEILING TILES (ROOM 2020 = 4, 2022 = 5, 2024 = 4, 2025 = 3)

6. REMOVE CEILING FAN AND REPLACE 1 SECTION OF CEILING GRID. REMOVE

WIRING BACK TO JUNCTION BOX.

7. REPLACE 1 SECTION OF CEILING GRID

8. REMOVE WALL-MOUNTED WOOD FURNITURE SUPPORT. MATCH EXISTING WALLS

AND PAINT.

9. INSTALL SOUND REDUCING DRYWALL ON FURRING STRIPS UP TO CONCRETE

BEAM. MODIFY CEILING GRID AND TILES AS REQUIRED TO MATCH NEW SURFACE.

REATTACH AC UNIT AND OTHER SURFACE MOUNTED CONDUIT AND WIRES TO

NEW WALL.

10. SCRAPE AND REMOVE BUBBLING DRYWALL/PATCH COMPOUND

15. RELOCATE THERMOSTAT FROM SOUTH WALL TO WEST WALL BY DOOR

16. NOT USED

17. PATCH CONCRETE FLOOR WITH NONSHRINK GROUT. PATCH AND REPAIR WALL

TO MATCH ADJACENT WALLS. RADIATOR WILL BE REMOVED AND STEAM PIPING

PLUGGED BY OTHERS.

2ND FLOOR PLAN

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

6' -3

32"

32"

32"

5'

32"

7'

'-4

5'-10"

30"

85' -8

9 9

9'

70"

70"

DRAWING TITLE

PROJECT NAME

DRAWN

DESIGNER

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DWG SHEET NO.

OFSHEET

United States Department of Agriculture Agricultural Research Service

2/1 0/2

3 1 5:

P

ET

ER

.L

AN

E C:

\U

SE

RS

\P

ET

ER

.L

AN

E\

ON

ED

RI

VE

US

DA

\A

LB

AN

Y\

FY

M

OV

E

OU

T\

RE

NO

VA

TI

ON

S\

DR

AW

IN

GS

\A

AO

R

EN

OV

AT

IO

N

X1 7.D

W G;

RENOVATE AAO

OFFICES

PACIFIC WEST AREA

800 BUCHANAN ST

ALBANY, CA

IT/AV PLAN

02/10/2023

P. LANE

P. LANE

K. CUSHMAN

A-04

005004

2ND FLOOR ELECTRICAL AND IT PLAN

3RD FLOOR ELECTRICAL AND IT PLAN

NETWORK LEGEND

NETWORK DROP TO REMAIN

NETWORK DROP TO BE RELOCATED

RELOCATED NETWORK DROP NEW LOCATION

NETWORK DROP TO CHANGE HEIGHT

32"

3 NUMBER OF NETWORK CABLES. ALL IF NOT SPECIFIED

HEIGHT FROM FLOOR TO BOTTOM OF NETWORK

BOX. 15" IF NOT SPECIFIED.

KEY NOTES

1. PARTIAL LENGTH OF WALL MOUNTED ELECTRICAL RACEWAY WILL BE REMOVED BY OTHERS.

2. PROVIDE AND INSTALL ON-FLOOR WIREWAY. PROVIDE THE FOLLOWING AT END OF THE WIREWAY:

2.1. FOUR OUTLETS WITH ELECTRICAL PIGTAIL. PIGTAIL WILL BE CONNECTED TO ELECTRICAL SYSTEM

BY OTHERS.

2.2. THREE NETWORK DROPS. TERMINATE IN JACK.

2.3. COILED ENDS OF 3 HDMI CABLES AND 1 ETHERNET CABLE PER BELOW.

3. PROVIDE AND INSTALL WALL CHANNEL FROM FLOOR TO DROP CEILING.

4. PROVIDE QTY=1, 50' ROUTED HDMI CABLE FROM END OF ON-FLOOR WIREWAY TO CEILING AT LOCATION

INDICATED. COIL CABLE ENDS IN CEILING AND ON FLOOR.

5. PROVIDE QTY=2, 25' ROUTED HDMI CABLES FROM END OF ON-FLOOR WIREWAY TO CEILING AT

LOCATION INDICATED. COIL CABLE ENDS IN CEILING AND ON FLOOR.

6. PROVIDE QTY=1, 50' ROUTED CAT-6 ETHERNET CABLE FROM END OF ON-FLOOR WIREWAY TO CEILING

AT LOCATION INDICATED. COIL CABLE ENDS IN CEILING AND ON FLOOR.

7. CEILING MOUNTED SINGLE GANG OUTLET AT LOCATION INDICATED FOR PROJECTOR WILL BE

PROVIDED BY OTHERS.

8. PROVIDE QTY=1, ROUTED USB AND QTY 1, ROUTED HDMI THROUGH CEILINGS AT LOCATIONS SHOWN.

TERMINATE IN FEMALE PLUGS IN BOXES. ON SOUTH WALL, MOUNT 15" ABOVE FLOOR. ON NORTH

WALL, MOUNT 32" ABOVE FLOOR ADJACENT TO NEW ELECTRICAL OUTLET.

9. REMOVE PHONE JUNCTION BOXES AND ASSOCIATED PLYWOOD AND SURFACE MOUNTED CONDUIT UP

TO ELECTRICAL CHASE

10. REMOVE 3 SURFACE MOUNTED TELEPHONE BOXES

11. COVER EXISTING JUNCTION BOX WITH FACEPLATE

12. USE PATCH NETWORK CABLE PLUGGED INTO EXISTING TERMINATIONS. ROUTE CABLE THROUGH

SURFACE MOUNTED CONDUIT TO IN-FLOOR RACEWAY.

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

3025A

DRAWING TITLE

PROJECT NAME

DRAWN

DESIGNER

CHECKED

ARCHIVE NO.

DATE

PROJECT NO.

DWG SHEET NO.

OFSHEET

United States Department of Agriculture Agricultural Research Service

2/1 0/2

3 1 5:

P

ET

ER

.L

AN

E C:

\U

SE

RS

\P

ET

ER

.L

AN

E\

ON

ED

RI

VE

US

DA

\A

LB

AN

Y\

FY

M

OV

E

OU

T\

RE

NO

VA

TI

ON

S\

DR

AW

IN

GS

\A

AO

R

EN

OV

AT

IO

N

X1 7.D

W G;

RENOVATE AAO

OFFICES

PACIFIC WEST AREA

800 BUCHANAN ST

ALBANY, CA

GENERAL NOTES AND

SPECIFICATIONS

02/10/2023

P. LANE

P. LANE

K. CUSHMAN

A-05

005005

GENERAL NOTES

ALL MEASUREMENTS ARE APPROXIMATE. FIELD VERIFY.

REVIEW AND FIELD VERIFY ALL LOCATIONS WITH GOVERNMENT.

THE CONTRACTOR SHALL OBTAIN BUILDING PERMIT FROM THE CITY OF ALBANY AND

COORDINATE INSPECTIONS.

CARPET

REMOVE AND DISPOSE OF EXISTING CARPET. REUSE EXISTING THRESHOLDS.

PREPARE SURFACE AND INSTALL PER MANUFACTURER'S RECOMMENDATIONS

CARPET TO BE SHAW DATELINE TODAY 54823 WITH COLOR RECAPS 00210 OR

APPROVED EQUAL.

- FIBER: NYLON

- CONSTRUCTION: LOOP

- STITCHES PER INCH: 10

- DYE METHOD: SOLUTION DYED

- TUFTED WEIGHT: 28 OZ/YD3

- AVERAGE DENSITY: 8064 OZ/YD3

- FINISHED PILE THICKNESS: 0.125"

- TOTAL THICKNESS: 0.28"

- ROLL SIZE: 12'

CARPET CLEANING

VACUUM AND DEEP CLEAN CARPET. PRETREAT AND REMOVE SPOTS AND STAINS. USE

SOLUTION AND EXTRACT WITH A DEEP CLEANING SYSTEM. DRY CARPET.

SHEET LINOLEUM

REMOVE AND DISPOSE OF EXISTING FLOORING. REUSE EXISTING THRESHOLDS.

CONFORM TO ASTM F1303, TYPE I, GRADE 1, CLASS A-NON-ASBESTOS FORMULATED

FIBROUS BACKING OR CLASS B-NONFOAMED PLASTIC BACKING (MINIMUM WEAR LAYER

THICKNESS 0.5 MM 0.020 INCH AND MINIMUM OVERALL THICKNESS 0.080 INCH) AND A

MINIMUM 6 FEET WIDE. AS REQUIRED, PROVIDE WELDING RODS AS RECOMMENDED BY

THE MANUFACTURER FOR HEAT WELDING OF JOINTS.

PREPARE SURFACE AND INSTALL PER MANUFACTURER'S RECOMMENDATIONS

PROVIDE COLOR SAMPLES FOR SELECTION

RUBBER BASE

REMOVE AND DISPOSE OF EXISTING BASE. SIZE NEW: 6" COVE

PAINT

- COLOR AND SHEEN TO MATCH ROOM 2025. MATCH MULTIPLE SAMPLES UNTIL

APPROVED BY GOVERNMENT.

- PAINT TO BE ON MASTER PAINT INSTITUTE (MPI) #145 APPROVED PRODUCT LIST

- FOR INTERIOR PAINT AND SPOT/TOUCH UP PAINT, REMOVE SCREWS, NAILS,

HOOKS, REPAIR MINOR JOINTS, CRACKS, HOLES, SURFACE IRREGULARITIES AND

OTHER MINOR DEFECTS WITH PATCHING PLASTER OR SPACKLING COMPOUND

AND SAND SMOOTH.

- FOR INTERIOR PAINT AND SPOT/TOUCH UP PAINT, CLEAN SURFACES AS

RECOMMENDED BY PAINT MANUFACTURER

- WHERE INDICATED TO PAINT INTERIOR WALLS, PAINT DOORS AND INTERIOR TRIM

TO MATCH EXISTING

INTERIOR CONSTRUCTION

FILL IN OR REMOVE WINDOWS AND DOORS AS INDICATED OR CONSTRUCT WALLS AND

INFALL AS INDICATED. USE 2x4 WOOD OR METAL STUDS, 5/8" GYPSUM WALLBOARD, TAPE AND TEXTURE TO MATCH ADJACENT WALLS ON BOTH SIDES OF WALL. COAT

WITH TWO COATS OF PAINT.

SOUND REDUCING DRYWALL TO BE QUIETROCK 530 OR APPROVED EQUAL, 5/8" THICK

WITH RATED STC IN FULL WALL ASSEMBLIES TO BE MINIMUM OF 52.

ELECTRICAL WIRING

CONNECT GOVERNMENT PROVIDED WIRING PIGTAILS FOR NEW CUBICLE

WORKSTATIONS. COORDINATE CONNECTION WITH FURNITURE INSTALLERS. HARD

WIRE CONNECTION AT APPROXIMATE LOCATION INDICATED ON FURNITURE

ELECTRICAL PLAN.

ROUTE WIRE THROUGH WALLS. WHERE WALLS ARE NOT STUD FRAMING, USE

SURFACE MOUNTED CONDUIT.

ALL ELECTRICAL TO BE DONE BY LICENSED ELECTRICIAN.

HDMI/USB CABLE AND CONNECTIONS

USE FEMALE-FEMALE CABLE OR PROVIDE FEMALE-MALE CONNECTORS WITH

MALE-MALE CABLE. CABLE AND CONNECTIONS TO BE SHIELDED, RATED TO HDMI 2.1a /

USB 3.0 AND IN-WALL USE.

ROUTE WIRE THROUGH WALLS. WHERE WALLS ARE NOT STUD FRAMING, USE

SURFACE MOUNTED CONDUIT.

DEMONSTRATE FUNCTIONALITY TO GOVERNMENT.

NETWORK WIRING

THE TELECOMMUNICATIONS INSTALLER SHALL BE A FIRM WHICH IS REGULARLY AND

PROFESSIONALLY ENGAGED IN THE BUSINESS OF THE APPLICATIONS, INSTALLATION,

AND TESTING OF THE SPECIFIED TELECOMMUNICATIONS SYSTEMS AND EQUIPMENT.

PROVIDE CAT-6e CABLES, SURFACE MOUNTED CONDUIT, JUNCTION BOXES, FACEPLATES, TERMINATIONS AND OTHER ACCESSORIES AS REQUIRED. MAINTAIN

EXISTING LABELS AND RELABEL AS DIRECTED BY GOVERNMENT. TEST IN

ACCORDANCE WITH TIA-568 AND PROVIDE RESULTS TO GOVERNMENT. ASSIST

GOVERNMENT IN DATA VERIFICATION TESTS.

ALL NETWORK CABLES CONNECT TO SWITCHES IN ROOM 3016.

ROUTE WIRE THROUGH WALLS AND CEILING EXCEPT WHERE INDICATED. WHERE

WALLS ARE NOT STUD FRAMING, USE SURFACE MOUNTED CONDUIT.

IN ROOM 2020, EXISTING CABLES HAVE BEEN CUT AND ARE NOT LABELED. TEST AND

LABEL CABLES TO CORRESPOND WITH LABELS AT SWITCH.

ON-FLOOR CONDUIT AND CONFERENCE TABLE WIRING AND CONNECTIONS

CONDUIT TO BE SOUTHWEST SOLUTIONS CONNECTRAC ON-FLOOR WIREWAY SYSTEM

OR APPROVED EQUAL WITH THE FOLLOWING CHARACTERISTICS:

- LOW PROFILE EXTRUDED ALUMINUM CHANNEL WITH DURABLE, CLEAR ANODIZED

ALUMINUM FINISH

- LAY DIRECTLY ON FINISHED FLOOR AND FASTENED TO CONCRETE SUBFLOOR

- REMOVABLE WIREWAY TOP CAP

- ADA COMPLIANT

- ON-FLOOR COMPONENT 9" WIDE AND 0.86" HIGH. INSIDE DIMENSIONS 3.1" x 0.6".

- AT END OF WIRE-WAY, QUAD RECEPTACLE AND TELECOM OPENINGS, PART

NUMBER PM-RECM-QD-1111

- WALL CHANNEL PART NUMBER AC-WC-144-AL

O ff ic e

Fu rn itu re

G ro up

Fi rs t S tr ee t N .W

. B ui ld in g

W as hi ng to n, D

.C un ic or

.g ov

/o fg

Ò

/
United States Department of Agriculture
Agricultural Research Service
AAO Renovation 11x17 Drawings.pdf
Sheets and Views
AAO Renovation 11x17-Cover
AAO Renovation 11x17-Page 1
AAO Renovation 11x17-Page 2
AAO Renovation 11x17-Page 3
AAO Renovation 11x17-Page 4

File details come from the government source that posted it. Updated .