This is a Schedule of Items (SOI) pricing template for critical housing deferred maintenance work at the Idaho City Work Center on the Boise National Forest. The document establishes a firm-fixed-price structure for both base and optional construction line items across multiple buildings, with offerors required to input unit prices for each work task.

The base scope includes five facilities: a Ranger Cabin (1107) with eight line items covering selective demolition, window replacement, flooring, painting, hot water heater, radon system, and mini-split installation; a 2-Bedroom House (1134) with thirteen line items including concrete sidewalk, framing, doors, interior/exterior painting, appliances, and utility system upgrades; Montgomery (1167) with four items for demolition, foundation repair, window replacement, and painting; Middle Fork Bunkhouse (1173) with four items for HVAC and demolition work; South Fork Bunkhouse (1175) with four items for HVAC and soffit repair; and North Fork Bunkhouse (1179) with identical HVAC and soffit repair scope. Optional work includes Centerville (1135) with five items, additional window/flooring/siding repairs for the three bunkhouses, a Detached Garage (1399), and Storage Shed (1643). All line items are listed as lump-sum (LS) quantities with blank unit prices requiring offeror completion. Offerors must submit signed SOI documentation certifying accuracy of all calculated values, with the government disclaiming liability for calculation errors. The solicitation is a 100% small business set-aside with quotes due April 14, 2026, and an estimated construction cost between $500,000 and $1,000,000, requiring payment and performance bonds.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOI

SCHEDULE OF ITEMS
GAOA CRITICAL HOUSING DEFERRED MAINTENANCE AT IDAHO CITY WORK CENTER
ForestBoise NF
Ranger District:Idaho City
County:Boise NF
Solicitation Number1240LT26R0007
BASE ITEMS
CostsTotal Cost
Line #Item #DescriptionQtyUnit PriceUnits
1011900Mobilization1$ - 0LS$ - 0
1107 Ranger Cabin
2017320Selective Demo1$ - 0LS$ - 0
3112113Window Replacement1$ - 0LS$ - 0
4096519Flooring1$ - 0LS$ - 0
5099123Painting1$ - 0LS$ - 0
6113100HW heater 40gal1$ - 0LS$ - 0
7312113Radon System1$ - 0LS$ - 0
822131627,000 BTU Mini-Split1$ - 0LS$ - 0
1107 TOTAL$ - 0
1134 2BR House
9017320Selective Demo1$ - 0LS$ - 0
10061000Concrete Sidewalk1$ - 0LS$ - 0
11072100Rough Framing1$ - 0LS$ - 0
12077253Doors1$ - 0LS$ - 0
13096519Painting exterior1$ - 0LS$ - 0
14099113Painting interior1$ - 0LS$ - 0
15099123Toilet and Bath Accessories1$ - 0LS$ - 0
16102800Laundry Appliances and Accessories1$ - 0LS$ - 0
17113100Kitchen Appliances and Accessories1$ - 0LS$ - 0
18220500Water System upgrades1$ - 0LS$ - 0
19221316Sewer System upgrades1$ - 0LS$ - 0
20260000Electrical Upgrades (Lighting, Heating…)1$ - 0LS$ - 0
21260001Flooring1$ - 0LS$ - 0
1134 TOTAL$ - 0
1167 Montgomery
22017320Selective Demo1$ - 0LS$ - 0
23061000Foundation Repair1$ - 0LS$ - 0
24077253Window Replacement1$ - 0LS$ - 0
25081416Painting1$ - 0LS$ - 0
1167 TOTAL$ - 0
1173 Middle Fork Bunkhouse
26017320Selective Demo1$ - 0LS$ - 0
27072100HW heater1$ - 0LS$ - 0
28236313Replace Air Conditioner1$ - 0LS$ - 0
29260000Replace Furnace1$ - 0LS$ - 0
1173 TOTAL$ - 0
1175 South Fork Bunkhouse
30017320Selective Demo1$ - 0LS$ - 0
31236313Replace Central AC, In-Kind1$ - 0LS$ - 0
32260000Replace Furnace1$ - 0LS$ - 0
33081416Soffit Repair1$ - 0LS$ - 0
1175 TOTAL$ - 0
1179 North Fork Bunkhouse
34017320Selective Demo1$ - 0LS$ - 0
35236313Replace Central AC, In-Kind1$ - 0LS$ - 0
36260000Replace Furnace1$ - 0LS$ - 0
37081416Soffit Repair1$ - 0LS$ - 0
1179 TOTAL$ - 0
Mobilization$ - 0
1107 TOTAL$ - 0
1134 TOTAL$ - 0
1167 TOTAL$ - 0
1173 TOTAL$ - 0
1175 TOTAL$ - 0
1179 TOTAL$ - 0
Total Base Cost:$ - 0

OPTIONAL ITEMS

1135 Centerville
38017320Selective Demo1$ - 0LS$ - 0
39061000Doors1$ - 0LS$ - 0
40081416Window Replacement1$ - 0LS$ - 0
41077253Painting1$ - 0LS$ - 0
4211211324,000 BTU Mini-Split1$ - 0LS$ - 0
1135 TOTAL$ - 0
1173 Middle Fork Bunkhouse
43017320Window Replacement1$ - 0LS$ - 0
44061000Flooring1$ - 0LS$ - 0
45Vinyl Siding repair1$ - 0LS$ - 0
1173 TOTAL$ - 0
1175 South Fork Bunkhouse
46017320Window Replacement1$ - 0LS$ - 0
47061000Flooring1$ - 0LS$ - 0
48081416Soffit Repair1$ - 0LS$ - 0
1175 TOTAL$ - 0
1179 North Fork Bunkhouse
49017320Window Replacement1$ - 0LS$ - 0
50061000Flooring1$ - 0LS$ - 0
1179 TOTAL$ - 0
1399 Detached Garage
51017320Selective Demo1$ - 0LS$ - 0
52061000Garage Doors1$ - 0LS$ - 0
1399 TOTAL$ - 0
1643 Storage shed
53017320Selective Demo1$ - 0LS$ - 0
54099123Painting1$ - 0LS$ - 0
1643 TOTAL$ - 0
1135 TOTAL$ - 0
1173 TOTAL$ - 0
1175 TOTAL$ - 0
1179 TOTAL$ - 0
1399 TOTAL$ - 0
1643 TOTAL$ - 0
Total Option Cost:$ - 0
Total Base Bid$ - 0
Total Option Cost$ - 0
Task Order Total Cost:$ - 0
NOTE 1: Offeror input Unit Prices
NOTE 2: Auto Calculated Values
NOTE 3: Submission of a signed SOI represents the Offerors commitment to the data herein. It is the responsibility of the Offeror to verify that all values presented in the signature certified SOI, including auto-calculated cells, accurately represent the Offeror's intended price elements. The Government shall not be held liable for any errors in calculation or pricing data.

OFFEROR NAME: BUSINESS EMAIL:

SAM UEI #: BUSINESS PHONE:

AUTHORIZED TO SIGN: (NAME & TITLE)

SIGNATURE: DATE:

File details come from the government source that posted it. Updated .