About this file
This document is a Sources Sought / Request for Information notice for a federal contract opportunity titled "Vehicle Barriers: RSS 2000 Cover Plate Welding & Bolts" with Solicitation Number FA461325Q2000. The requirement is being issued by the Department of the Air Force Global Strike Command for work to be performed at Francis E. Warren Air Force Base in Wyoming. The contract will involve providing labor, materials, equipment, and supervision to secure the cover plates for two RSS 2000 wedge barriers at the base's Gate 2. The procurement is under NAICS code 811210 with a small business size standard of $34 million. Responses are requested from interested parties using the provided Attachment 2 - Response Form to answer questions about site visits, work start time and duration, and welding preferences. All responses must be submitted electronically by 11:00am Mountain Standard Time on Wednesday, October 23, 2024. This is a market research exercise, and no award will be made from this announcement. The government may set aside the requirement for small businesses or pursue full and open competition based on the responses received.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Response Form
Sources Sought / Request for Information Notice Number: FA461325Q2000
Description: RSS 2000 Cover Plate Welding & Bolts
Company Information
Company Name (as registered in SAM.gov):
Company Doing Business As (if applicable):
Cage Number: Unique Entity ID
Socioeconomic Status (SB, SDB, WOSB, EDWOSB, VOSB, SDVOSB, 8(a), 8(a) JV, HUBZone):
Point of Contact:
Email: Phone number:
Questions
1. Is a site visit necessary? If so, how long would a site visit in hours (round up to nearest hour) take to complete?
2. How long after award, in calendar days, would you be able to begin work? What is the estimated lead time of materials? How much estimated time would it take to complete?
3. What is the preferred method of welding from Attachment 1 – SOW beneath “1.
Description of Performance”, either Step 2 or Step 3?