Attachment 2 - Project Specifications~2.pdf

PDF 150 KB Posted

Attached to
DNR Union County SFWA - Construct Pole Barn at Hunter Check Station
Solicitation number
26-422DNR-REALT-B-51162
Issued by
Tazewell County, Illinois

About this file

Project Specifications Summary

This document is a project specifications attachment for the Illinois Department of Natural Resources (IDNR) project file 5-25-029, detailing construction requirements for a pre-engineered pole building at Union County SFWA in Jonesboro, Illinois. The scope of work includes construction of a pre-engineered pole building package with gutters, downspouts, and snow and ice guards, along with related work encompassing general conditions, grading, excavation, backfilling, electrical work, doors and windows, sealants and caulking, and steel bollards. The project specifications establish design loading conditions including a 30 psf snow load, 20 psf wind load with 80 mph wind speed, and 2,000 psf soil bearing pressure. Contractors and manufacturers must demonstrate minimum five years of experience in comparable building systems, with the contractor requiring manufacturer approval for the selected building package.

Acceptable pre-engineered building manufacturers include Lester Buildings Inc., Cleary Building Corp., Economy Builders & Supply, Morton Buildings, Sturdi-Built, Wick Buildings, and O'Neil Building Systems, with provisions allowing alternative manufacturers to be considered if demonstrated equivalent to listed manufacturers. The specifications require materials including No. 1 Southern Yellow Pine for posts and framing, galvanized steel roof and sidewall panels with Kynar paint finish, stainless steel fasteners, and concrete with minimum 3,000 psi compressive strength for postholes and concrete sills. Manufacturer warranties include 40-year coverage against rot and decay on treated posts and paint finishes, five-year warranty on roof leaks and structural panels against snow load damage, and contractor warranty on workmanship and materials for one year. All construction must comply with referenced standards including ACI 301 for concrete, TPI specifications for wood trusses, and Uniform Building Code requirements.

View the file

Other files

File Type Posted
0 standard terms and conditions V23.2~41.pdf PDF
5-25-029 SOW Small.docx DOCX document
Attachment 1 - Project Plans~5.pdf PDF
0 standard-illinois-certifications-v-26-2~4.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IDNR File No.: 5-25-029

ATTACHMENT 2

Project Specifications

FILE# 5-25-029 13126-1 April 2025

Section 13126 - Pre-Engineered Pole Building

1. GENERAL.

1-01. WORK INCLUDES.

A. Base Bid:

General Contractor: pre-engineered building package, including:

a. Pre-engineered pole building

b. Gutters and downspouts

c. Snow & Ice Guards

1-02. RELATED WORK.

A. Specified in the Scope of Work:

1. General Conditions

2. Grading and Layout

3. Excavation, Backfilling, and Compaction

4. Pre-Engineered Pole Building

5. Sealants and Caulking

6. Doors and Windows

7. Electrical

8. Steel Bollards

B. Specified Elsewhere:

1-03. QUALITY ASSURANCE.

A. Qualifications:

1. Of Manufacturer: Minimum five (5) years’ experience in design and fabrication of similar building systems.

2. Of Contractor or Builder:

a. Minimum five (5) years’ experience in erection of comparable building systems.

b. Approved by Manufacturer of building package.

1-04. DESIGN LOADING CONDITIONS.

A. Snow load: 30 psf.

B. Wind load: 20 psf with a wind speed of 80 mph. Contractor shall verify that this requirement conforms to the Uniform Building Code.

C. Soil bearing pressure: 2,000 psf.

FILE# 5-25-029 13126-2 April 2025

1-05. SUBMITTALS.

A. In accord with other shop drawing submittal requirements detailed elsewhere.

1. Shop Drawings:

a. Pole building package. Furnish Shop Drawings in addition to Construction Drawings.

2. Product Data:

a. Pole building package

3. Samples

a. Manufacturer's standard color samples for color selection.

1-06. REFERENCED STANDARDS.

A. Concrete: ACI 301 - Specifications for Structural Concrete for Buildings.(ACI)

B. Lumber Standards:

1. Dimension Lumber Standard: US Product Standard PS-20.

2. Grading Standards:

a. Southern Pine: Southern Pine Inspection Bureau (SPIB)

b. Douglas Fir-Larch:

(1). West Coast Lumber Inspection Bureau

(WCLIB)

(2). Western Wood Products Association (WWPA)

3. Wood Treatment Standard:

a. American Wood Preservers Association (AWPA)

b. American Wood Preservers Board (AWPB)

C. Wood Truss Standards:

1. Design and Fabrication Standards:

a. Truss Plate Institute (TPI) National Specifications for Metal Plate Connected Wood Trusses.

b. TPI Quality Standards for Metal Plate Connected Wood Trusses.

2. Truss Erection Standards:

a. TPI Commentary and Recommendations for

Handling and Erecting Wood Trusses.

b. TPI Commentary and Recommendations for Bracing Wood

Trusses.

D. Steel or Aluminum Fascia, Soffits and Gutters:

1-07. WARRANTY.

A. Manufacturer's Warranty:

1. Warranty pressure treated posts against rot, decay or insect attack for a period of forty (40) years.

FILE# 5-25-029 13126-3 April 2025

2. Warranty against leaks in roof for a period of five (5) years.

3. Warranty building frame work, wall and roof panels against damage from snow loads for a period of five (5) years.

4. Warranty paint finish on panels against blistering, peeling, checking, chalking, fading or loss of adhesion for a period of forty

(40) years.

B. Contractor: warranty workmanship and material for a period of one (1) year.

2. MATERIALS.

2-01. CONCRETE FOR POSTHOLES AND CONCRETE SILL.

A. Materials:

1. Portland Cement: conform to ASTM C-150.

2. Aggregates: conform to ASTM C-33

3. Mixing water: potable

B. Ready mix concrete: conform to ASTM C-94. Minimum Ultimate

Compressive Strength (F'c): 3,000 psi @ 28 days.

2-02. PRE-ENGINEERED POLE BUILDING.

A. Acceptable manufacturers for pole building package:

1. Lester Buildings Inc., Charleston IL

2. Cleary Building Corp., Verona WI

3. Economy Builders & Supply, Princeville IL

4. Morton Buildings, Morton IL

5. Sturdi-Built, Charleston IL 6 Wick Buildings, Mazomanie, WI

7. O’Neil Building Systems, Sauget, IL

Other manufacturers may also be considered, provided their products can be demonstrated to be of the same quality of materials and components as those on the list of acceptable manufacturers, and meet the minimum requirements of this specification. Burden of proof that the building system is an equivalent of the acceptable manufacturers in on the contractor. Regardless of manufacturer, contractor shall provide construction drawings of the proposed building sealed by a Structural Engineer licensed in the State of Illinois verifying compliance with all applicable codes, loading requirements, and project specifications.

B. Framing materials:

1. Posts: No. 1 Southern Yellow Pine (SYP); CCA treated at 0.60 pcf at portion below grade; solid or laminated, at Manufacturer's option.

2. Skirt boards: No. 1 SYP; CCA treated at 0.40 pcf.

FILE# 5-25-029 13126-4 April 2025

3. Roof girts and wall purlins: No. 2 SYP

C. Roof Trusses:

1. Materials:

a. Top Chord: No. 1 Southern Yellow Pine

b. Bottom Chord: No. 1 Southern Yellow Pine

c. Webs: No. 2 southern Yellow Pine

d. Plates: minimum 20 gauge steel; galvanized; conforming to TPI Specifications.

2. Fabrication:

a. Conform to the following:

(1). Truss Plate Institute (TPI) National Specifications for Plate Connected Wood Trusses

(2). TPI Quality Standard for Metal Plate Connected Wood Trusses.

b. Fabricate trusses in plant using mechanical or hydraulic jigs to bring members into contact. Install plates as per TPI recommendations.

D. Roof and Sidewall Panels:

1. Roof and sidewall panels: roll formed (minimum) 29 gauge galvanized (G90) steel, aluminum coated steel or aluminum alloy;

5/8" high rib pattern; minimum 48,000 psi tensile strength.

2. Protective Coating: all trim, roof, and sidewall panels shall be coated with a Kynar paint finish. This finish shall be a dispersion coating based on Kynar 500® FSF® resin as formulated by an Arkema Kynar 500®licensee. This finish, based on Kynar 500® FSF® resin, shall meet the performance criteria of AAMA 2605 specification and be certified by the formulator as containing Kynar 500® FSF® resin.

E. Accessories:

1. Trim: die formed 29 gauge steel; same finish as panels.

2. Fasteners: No. 18 stainless steel screws with neoprene washers.

Nails not permitted. Fasteners shall penetrate purlins and girts a minimum of 1½".

3. Filler strips: Manufacturer's standard foam, designed to conform to profile of panels.

4. Furnish Manufacturer's standard continuous ridge vent; full length of building. Provide insect screen and fiber fill

FILE# 5-25-029 13126-5 April 2025

5. Vapor Barrier: Provide a synthetic plastic sheet metal roof underlayment made of polyethylene, polyolefin, or polypropylene. Minimum thickness shall be 12 mils. Overlap adjacent pieces by at least 12-inches.

6. Gutters: Sized per manufacturer’s standard configuration. 29 gauge aluminum or steel, color to match building. Manufacturer’s standard support bracket spaced a maximum 48-inch on center.

7. Downspouts: Downspouts to match the material and finish of the gutters. Manufacturer’s standard downspout, 5” x 3” minimum size. Attached to wall with sheet metal straps to match downspout at 48” o.c. Provide concrete splash blocks.

8. Sealants and Caulking: Sealants in joints between system components shall be as specified or recommended by the building manufacturer.

9. Snow and Ice Guards: Provide and install snow and ice guards to the roof of the pole building. Guards shall be installed per building manufacturer’s recommendations to prevent ice sheets from sliding off the roof.

3. EXECUTION.

3-01. BUILDING LAYOUT.

A. Layout Building as per approved Shop Drawings. Establish finish floor elevation as indicated or directed. Layout building square and in proper alignment.

3-02. FRAMING SYSTEM ERECTION.

A. Set in accord with approved Shop Drawings and Manufacturer's printed instructions and recommendations. Set building components square, plumb, straight and in proper alignment.

B. Set poles in full depth concrete. Backfilling posts with gravel, earth or any material other than concrete not permitted. Anchor pole ends as per approved Shop Drawings. Install built-up lintels, headers and other framing components as required. Introduce temporary bracing as required to maintain proper alignment of building during erection.

C Store, handle and set roof trusses as per TPI "Commentary and

Recommendations for Handling and Erecting Wood Trusses". Anchor to posts as per approved Shop Drawings. Brace trusses as per TPI "Commentary and Recommendations for Bracing Wood Trusses".

D. Install roof purlins, splash boards, sidewall girts and other framing components or accessories as indicated or required. Minimum size/spacing for framing members:

FILE# 5-25-029 13126-6 April 2025

1. Roof purlins: 2 X 6 minimum, spaced at 24" max. on centers.

2. Wall girts: 2 X 6 minimum, spaced at 30" max. on centers.

3. Splash boards: 2 X 8 minimum.

4. Do not exceed maximum spacing of supports recommended by

Manufacturer of roof and wall panels.

E. Provide knee braces, corner bracing, lateral bracing and other incidental framing indicated on Shop Drawings.

3-03. METAL ROOFING AND SIDING.

A. Install roof and wall panels, lapping as per Manufacturer's printed instructions. Install panels with stainless steel screws and neoprene washers. Nails not permitted.

B. Provide starter strips, filler strips, corner trim. fascia, vented soffit, ridge vent, metal trim at openings and other accessories required for complete and finished job. No exposed wood other than splash board permitted on exterior of building.

3-04. COMPLETION.

A. Upon completion, carefully inspect installation. Repair and/or replace damage or improperly installed components. Touch up damaged or defective paint or finish with material furnished by Building Manufacturer.

END 13126

Attachment 2 - Project Specifications.pdf