This file is a Pricing Schedule for a door replacement project at the FEMA MERS VSAB Building B in Maynard, Massachusetts. The solicitation (Number 70FBR125B00000001) involves replacing a Sensitive Compartmented Information Facility (SCIF) door and hardware to meet current security standards. The project requires comprehensive door replacement services, including site preparation, demolition, wall assessment, frame and door installation, hardware mounting, weatherproofing, and functionality testing. The period of performance is 120 days from award, with the project estimated between $25,000 and $100,000 in construction value. The pricing schedule is structured as a lot-based (LO) itemized template where offerors must input unit prices for each specific work component, with a total project cost to be calculated by summing individual line items and potential contingency amounts.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| MA MERS SCIF Door Replacement at the FEMA, MERS, VSAB, Bldg. B | |
| Attachment 2: | Pricing Schedule |
| Solicitation Number: | 70FBR125B00000001 |
| Title: | MA MERS SCIF Door Replacement at the FEMA, MERS, VSAB, Bldg. B |
| Offeror Name: | [Insert Offeror's Name] |
| Offeror Address: | [Insert Offeror's Address] |
| Itemized Pricing Schedule: | |||||
| Item No. | Description of Work | Unit | Quantity | Unit Price ($) | Total Price ($) |
| 1 | MA MERS SCIF Door Replacement at the FEMA, MERS, VSAB, Bldg. B | LO | 1 | [Insert Unit Price] | [Insert Total Price] |
| 0001AA | Site preparation | LO | 1 | [Insert Unit Price] | [Insert Total Price] |
| 0001AB | Demolition and removal of existing doors, frames, and hardware | LO | 1 | [Insert Unit Price] | [Insert Total Price] |
| 0001AC | Assessing wall structure around door opening for adjustments or reinforcements; site protection & cleanup | LO | 1 | [Insert Unit Price] | [Insert Total Price] |
| 0001AD | Installation of new door frames, shims, ensuring proper fit; installing new secure door leaf on frame & ensuring proper alignment | LO | 1 | [Insert Unit Price] | [Insert Total Price] |
| 0001AE | Door frames; hardware installation | LO | 1 | [Insert Unit Price] | [Insert Total Price] |
| 0001AF | Weatherproofing & sealing; functionality testing | LO | 1 | [Insert Unit Price] | [Insert Total Price] |
Total Project Cost: $ - 0 $ - 0
| Description | Amount ($) |
| Subtotal | [Insert Subtotal] |
| Contingency (if applicable | [Insert Contingency Amount] |
| Total Cost | $ - 0 |
| Notes: | |
| 1 | LO: Lot |
| 2 | LS: Lump Sum |
| Offeror Certification: |
| By submitting this pricing schedule, the offeror certifies that the prices provided are accurate and reflect the full scope of work as described in the Statement of Work (SOW). |
| Offeror Signature: | [Insert Signature] |
| Date: | [Insert Date] |
This Pricing Schedule should be filled out by the offeror with the appropriate unit prices and total prices for each item. The total project cost should be calculated based on the sum of all items, including any contingency amounts if applicable. The offeror should sign and date the schedule to certify the accuracy of the pricing information provided.