12444121R0053
ATTACHMENT 2 - STATEMENT OF WORK (SOW)
Bulk Lime and Fertilizer Application
12444121R0053
ATTACHMENT 2 - STATEMENT OF WORK (SOW)
Bulk Lime and Fertilizer Application
1.0 INTRODUCTION:
Application of fertilizer and lime applied in bulk form to the ACP Post Closure Units (Burial Caps)
2.0 SCOPE:
The Application of Lime is to begin on/or after August 9, 2021 and to be completed by September 30th, 2021
Optional Item: The Application of Fertilizer is to begin on/or after March 29, 2022 and to be completed by April 30th, 2022
Optional Item: The Application of Lime is to begin on/or after August 9, 2022 and to be completed by September 30th, 2022
The Applicator will need to come by COR’s office for Remote Worker Map, Pager, List of Caps for Fertilizer Application and List of Caps with Fertilizer and Herbicide. The Application Truck will need to be inspected before use on the site.
3.0 PERSONNEL QUALIFICATIONS:
None, except as required by employer
4.0 GOVERNMENT-FURNISHED EQUIPMENT (GFE) AND MATERIALS:
1. Government Furnished Equipment:
a. Pager
b. Remote Worker Map
c. Post Closure Lock Key for Burial Cap
5.0 REGULATIONS/POLICIES:
Contractor will use specifications outlined in ATTACHMENT 3 - Specifications
6.0 Burial Cap Access:
The Contracting Officer’s Representative (COR) listed in paragraph 8.0 will assist with the Contractor’s entry into secure areas and inform the Contractor of security procedures. The Contractor shall comply with all security procedures.
7.0 TRAINING:
The Contractor is responsible for all training for its employees.
8.0 POINTS OF CONTACTS (POC):
Contracting Officer (CO): Kelly Updegraff 803-814-5080 or email: kelly.b.updegraff@usda.gov
| Contracting Officer’s Representative (COR): Tony Waiswilos | | 803-295-3008 |
| Contracting Officer’s Representative (COR): Travis McCullough | 803-725-1039 | |
O&M POST CLOSURE MAINTENANCE CAPS
Grid Location
| 1 |
| M-Area Settling Basin |
| 6.56 |
| acres |
| N5 – W7 |
| 2 |
| Metallurgical Laboratory |
| 1.07 |
| acre |
| N6 – W6 |
| 3 |
| M-Area Operable Area |
| 1 |
| acres |
| N7 - W6 |
| 4 |
| A-Area Burning Rubble Pit |
| 13.63 |
| acres |
| N4 – W7 |
| 5 |
| A-Area Misc. Rubble Pit |
| 2.15 |
| acre |
| N5 – W6 |
| 6 |
| Silverton Road Waste Unit |
| 6.85 |
| acres |
| N5 – W8 |
| 7 |
| Metals Burning Pit/Misc. Chemical Basin |
| 5.47 |
| acres |
| N4 – W7 |
| 8 |
| SREL Seepage Basin |
| 4.81 |
| acres |
| N6 – W6 |
| 9 |
| Non-Radioactive Waste Disposal Facility |
| 78.66 |
| acres |
| N3 – W5 |
| 10 |
| Interim Sanitary Landfill |
| 20 |
| acres |
| N3 – W5 |
| 11 |
| F-Area Burning Rubble Pits |
| 2.03 |
| acre |
| N2 –W4 |
| 12 |
| Old F-Area Seepage Basin |
| 3.1 |
| acre |
| N3 – W3 |
| 13 |
| F-Area Seepage Basin |
| 13.52 |
| acres |
| N2 – W3 |
| 14 |
| F-Area Retention Basin |
| 2.3 |
| acre |
| N2 – W3 |
| 15 |
| H-Area Seepage Basin |
| 36.81 |
| acres |
| N2 – W1 |
| 16 |
| Warner’s Pond |
| 6.47 |
| acres |
| N3 – W1 |
| 17 |
| H-Area Inactive Process Sewer Line |
| 0.63 |
| acres |
| Varies |
| 18 |
| H-Retention Basin |
| 3.47 |
| acres |
| N2 – W1 |
| 19 |
| HP 52 Ponds |
| 2.01 |
| acre |
| N2 – W1 |
| 20 |
| Old Radioactive Waste Burial Ground |
| 92.39 |
| acres |
| N2 – W2 |
| 21 |
| Mixed Waste Management Facility |
| 109.26 |
| acres |
| N3 – W2 |
| 22 |
| Central Shops Burning Rubble Pit |
| 5.54 |
| acres |
| N1 – W2 |
| 23 |
| Ford Building Seepage Basin |
| 0.5 |
| acre |
| S1 – W2 |
| 24 |
| C-Area Burning Rubble Pit |
| 2.55 |
| acre |
| S1 – W2 |
| 25 |
| C-Reactor Seepage Basin |
| 5.07 |
| acres |
| S1 – W3 |
| 26 |
| CMP Pits |
| 5.91 |
| acres |
| S2 - E1 |
| 27 |
| L-Area Oil Chemical Basin and Reactor Seepage Basin |
| 2.5 |
| acre |
| S3 – E1 |
| 28 |
| L-Area Bingham Pump Outage Pit |
| 0.71 |
| acre |
| S2 – E1 |
| 29 |
| K-Area Burning Rubble Pit |
| 1.76 |
| acres |
| S3 – W2 |
| 30 |
| K-Reactor Seepage Basin |
| 0.98 |
| acre |
| S3 – W2 |
| 31 |
| K-Area Bingham Pump Outage Pit |
| 0.72 |
| acre |
| S3 – W2 |
| 32 |
| P-Area Bingham Pump Outage Pit |
| 0.91 |
| acre |
| S2 – E4 |
| 33 |
| P-Area Burning Rubble Pit |
| 1.55 |
| acre |
| S2 – E3 |
| 34 |
| P-Area Seepage Basin |
| 4.81 |
| acres |
| S2 – E3 |
| 35 |
| P-Area Ash Basin |
| 36.66 |
| acre |
| S2 – E3 |
| 36 |
| R-Area Ash Basin |
| 16.83 |
| acres |
| N1- E4, N2 –E4 |
| 37 |
| R-Burning Rubble Pit |
| 1.17 |
| acre |
| N2 – E4 |
| 38 |
| R-Area Bingham Pump Outage Pit |
| 2.62 |
| acre |
| N2 – E4 |
| 39 |
| D-Area Ash Pit |
| 135.61 |
| acres |
| S3 –W7 |
| 40 |
| D-Area Coal Pile |
| 6.41 |
| Acres |
| S3 – W7 |
| 41 |
| D-Area Burning Rubble Pit |
| 0.91 |
| acre |
| S3 – W7 |
| 42 |
| D- Area Bubble Tower |
| 1.84 |
| acres |
| S3 – W7 |
| 43 |
| T-Area Operable Unit (TNX) |
| 31.82 |
| acres |
| S3 – W7 |