Attachment (2) J-0200000-10 Exhibit Line Item Numbers N4008422R7003.pdf

PDF 453 KB Posted

Attached to
MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT, BLDG. 961, NAF MISAWA, JAPAN
Solicitation number
N4008422R7003
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI//FEDCON (when filled in)

ELIN /

Sub

ELIN

Description Quantity Unit of Issue

Unit Price Total CAC

1604000 Facility Investment A001 Service Orders A001AA Emergency Service Orders 12 MO -¥ -¥ 712S A001AB Urgent Service Orders 12 MO -¥ -¥ 712S A001AC Routine Service Orders 12 MO -¥ -¥ 712S

A002 Preventive Maintenance (PM) Program

A002AA

Compressed Air Distribution Systems. Spec Item 3.2.1

12 MO -¥ -¥ 712S

A002AB

Wastewater Instrumentation Systems. Spec Item 3.2.2

12 MO -¥ -¥ 712S

A002AC

Sewage Sump Pumps, Agitators, and Shooters. Spec Item

3.2.3 12 MO -¥ -¥ 712S

A002AD Valves, Piping, and Automatic Controls. Spec Item 3.2.4 12 MO -¥ -¥ 712S

A002AE

Adjustment Tanks, Sewage Tanks, Filtration Tower/Tanks.

Spec Item 3.2.5 1 YR -¥ -¥ 712S

A002AF Chemical Replenishment. Spec Item 3.2.6 12 MO -¥ -¥ 712S

A002AG

Sand and Activated Carbon Filtration System. Spec Item

3.2.7 1 YR -¥ -¥ 712S

A003 Inspection, Testing, and Certification Program A003AA Valves, Piping, and Automatic Controls. Spec Item 3.3.1 12 MO -¥ -¥ 712S A003AB Water Quality Analysis. Spec Item 3.3.2 12 MO -¥ -¥ 712S A003AC Bacterial Analysis. Spec Item 3.3.3 12 MO -¥ -¥ 712S A003AD Engineering Support Services. Spec Item 3.3.4 12 MO -¥ -¥ 712S A003AE Record Keeping 12 MO -¥ -¥ 712S

TOTAL LINE ITEM 0001 RECURRING WORK BASE YEAR

(Enter this amount into Schedule of Work, Item No. 0001, Net Amount

EXHIBIT A - CLIN 9000

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Line Item 0001 Recurring Work Price - Base Period

PROVIDE PRICES FOR FACILITY INVESTMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 ELIN A001AA through A003AE.

A001 Sub Total

A002 Sub Total

A003 Sub Total

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

Wastewater Treatment Plant - Misawa Section J, Page 43 of 75

ELIN Product Name (120 Characters)

Description Extended Estimated Quantity

Unit of Issue

Unit Price Extended Price IMAP CAC(s)

A700 Unit Priced Labor Work for 1604000 -

MUST BE

NEGOTIATED BY

THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order labor cost will be negotiated.

200 HR (Estimated Maximum Labor Cost)

712S

A701 Material Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order material cost will be negotiated. Use with ELIN A700.

1 LS (Estimated Maximum Material Cost)

712S

A702 Equipment Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order equipment cost will be negotiated. Use with ELIN A700.

1 LS (Estimated Maximum Equipment Cost)

712S

A703 Percentage to be added to cost of labor hours for emergency response

Provide an emergency response for repairs when the contractor has to respond to an emergency related Non-Recurring work.

% (Estimated Maximum Emergency Response)

712S

Notes:

(2) UPT work requiring addtional contractual and safety oversight shall NOT be ordered through DoD FEDMALL. If the Contractor SSHO identifies any high risk in the DoD FEDMALL work ordered the Contractor QM shall notify the KO or COR immediately before start of work.

PROVIDE PRICES FOR FACILITY INVESTMENT - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 ELINs A700 through A703.

TOTAL LINE ITEM 0002 NON-RECURRING WORK PRICE BASE YEAR

(Enter this amount into Schedule of Work, Item No. 0002, Net Amount)

(1) The Government will compensate the Contractor for the direct cost of materials and equipment and not necessarily the total amount shown in this Schedule.

Line Item 0002 Non-Recurring Work - Base Period

EXHIBIT A - CLIN 9000

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Section J, Page 44 of 75

ELIN /

Sub

ELIN

Description Quantity Unit of Issue

Unit Price Total CAC

1604000 Facility Investment B001 Service Orders B001AA Emergency Service Orders 12 MO -¥ -¥ 712S B001AB Urgent Service Orders 12 MO -¥ -¥ 712S B001AC Routine Service Orders 12 MO -¥ -¥ 712S

B002 Preventive Maintenance (PM) Program

B002AA Compressed Air Distribution Systems. Spec Item 3.2.1

12 MO -¥ -¥ 712S

B002AB Wastewater Instrumentation Systems. Spec Item 3.2.2

12 MO -¥ -¥ 712S

B002AC

Sewage Sump Pumps, Agitators, and Shooters. Spec Item

3.2.3 12 MO -¥ -¥ 712S

B002AD Valves, Piping, and Automatic Controls. Spec Item 3.2.4 12 MO -¥ -¥ 712S

B002AE

Adjustment Tanks, Sewage Tanks, Filtration Tower/Tanks.

Spec Item 3.2.5 1 YR -¥ -¥ 712S

B002AF Chemical Replenishment. Spec Item 3.2.6 12 MO -¥ -¥ 712S

B002AG

Sand and Activated Carbon Filtration System. Spec Item

3.2.7 1 YR -¥ -¥

B003 Inspection, Testing, and Certification Program B003AA Valves, Piping, and Automatic Controls. Spec Item 3.3.1 12 MO -¥ -¥ 712S B003AB Water Quality Analysis. Spec Item 3.3.2 12 MO -¥ -¥ 712S B003AC Bacterial Analysis. Spec Item 3.3.3 12 MO -¥ -¥ 712S B003AD Engineering Support Services. Spec Item 3.3.4 12 MO -¥ -¥ 712S B003AE Record Keeping 12 MO -¥ -¥ 712S

TOTAL LINE ITEM 0003 RECURRING WORK 1ST OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0003, Net Amount

EXHIBIT B - CLIN 9001

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Line Item 0003 Recurring Work Price - 1st Option Period

PROVIDE PRICES FOR FACILITY INVESTMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 ELIN B001AA through B003AE.

B001 Sub Total

B002 Sub Total

B003 Sub Total

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

Section J, Page 45 of 75

ELIN Product Name (120 Characters)

Description Extended Estimated Quantity

Unit of Issue

Unit Price Extended Price IMAP CAC(s)

B700 Unit Priced Labor Work for 1604000 -

MUST BE

NEGOTIATED BY

THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order labor cost will be negotiated.

200 HR (Estimated Maximum Labor Cost)

712S

B701 Material Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order material cost will be negotiated. Use with ELIN B700.

1 LS (Estimated Maximum Material Cost)

712S

B702 Equipment Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order equipment cost will be negotiated. Use with ELIN B700.

1 LS (Estimated Maximum Equipment Cost)

712S

B703 Percentage to be added to cost of labor hours for emergency response

Provide an emergency response for repairs when the contractor has to respond to an emergency related Non-Recurring work.

% (Estimated Maximum Emergency Response)

712S

Notes:

(2) UPT work requiring addtional contractual and safety oversight shall NOT be ordered through DoD FEDMALL. If the Contractor SSHO identifies any high risk in the DoD FEDMALL work ordered the Contractor QM shall notify the KO or COR immediately before start of work.

PROVIDE PRICES FOR FACILITY INVESTMENT - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 ELINs B700 through B703.

TOTAL LINE ITEM 0004 NON-RECURRING WORK PRICE 1ST OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0004, Net Amount)

(1) The Government will compensate the Contractor for the direct cost of materials and equipment and not necessarily the total amount shown in this Schedule.

Line Item 0004 Non-Recurring Work - 1st Option Period

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

EXHIBIT B - CLIN 9001

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Section J, Page 46 of 75

ELIN /

Sub

ELIN

Description Quantity Unit of Issue

Unit Price Total CAC

1604000 Facility Investment C001 Service Orders C001AA Emergency Service Orders 12 MO -¥ -¥ 712S C001AB Urgent Service Orders 12 MO -¥ -¥ 712S C001AC Routine Service Orders 12 MO -¥ -¥ 712S

C002 Preventive Maintenance (PM) Program

C002AA Compressed Air Distribution Systems. Spec Item 3.2.1

12 MO -¥ -¥ 712S

C002AB Wastewater Instrumentation Systems. Spec Item 3.2.2

12 MO -¥ -¥ 712S

C002AC

Sewage Sump Pumps, Agitators, and Shooters. Spec Item

3.2.3 12 MO -¥ -¥ 712S

C002AD Valves, Piping, and Automatic Controls. Spec Item 3.2.4 12 MO -¥ -¥ 712S

C002AE

Adjustment Tanks, Sewage Tanks, Filtration Tower/Tanks.

Spec Item 3.2.5 1 YR -¥ -¥ 712S

C002AF Chemical Replenishment. Spec Item 3.2.6 12 MO -¥ -¥ 712S

C002AG

Sand and Activated Carbon Filtration System. Spec Item

3.2.7 1 YR -¥ -¥ 712S

C003 Inspection, Testing, and Certification Program C003AA Valves, Piping, and Automatic Controls. Spec Item 3.3.1 12 MO -¥ -¥ 712S C003AB Water Quality Analysis. Spec Item 3.3.2 12 MO -¥ -¥ 712S C003AC Bacterial Analysis. Spec Item 3.3.3 12 MO -¥ -¥ 712S C003AD Engineering Support Services. Spec Item 3.3.4 12 MO -¥ -¥ 712S C003AE Record Keeping 12 MO -¥ -¥ 712S

TOTAL LINE ITEM 0005 RECURRING WORK 2ND OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0005, Net Amount

EXHIBIT C - CLIN 9002

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Line Item 0005 Recurring Work Price - 2nd Option Period

PROVIDE PRICES FOR FACILITY INVESTMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 ELIN C001AA through C003AE.

C001 Sub Total

C002 Sub Total

C003 Sub Total

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

Section J, Page 47 of 75

ELIN Product Name (120 Characters)

Description Extended Estimated Quantity

Unit of Issue

Unit Price Extended Price IMAP CAC(s)

C700 Unit Priced Labor Work for 1604000 -

MUST BE

NEGOTIATED BY

THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order labor cost will be negotiated.

200 HR (Estimated Maximum Labor Cost)

712S

C701 Material Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order material cost will be negotiated. Use with ELIN C700.

1 LS (Estimated Maximum Material Cost)

712S

C702 Equipment Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order equipment cost will be negotiated. Use with ELIN C700.

1 LS (Estimated Maximum Equipment Cost)

712S

C703 Percentage to be added to cost of labor hours for emergency response

Provide an emergency response for repairs when the contractor has to respond to an emergency related Non-Recurring work.

% (Estimated Maximum Emergency Response)

712S

Notes:

(2) UPT work requiring addtional contractual and safety oversight shall NOT be ordered through DoD FEDMALL. If the Contractor SSHO identifies any high risk in the DoD FEDMALL work ordered the Contractor QM shall notify the KO or COR immediately before start of work.

PROVIDE PRICES FOR FACILITY INVESTMENT - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 ELINs C700 through C703.

TOTAL LINE ITEM 0006 NON-RECURRING WORK PRICE 2ND OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0006, Net Amount)

(1) The Government will compensate the Contractor for the direct cost of materials and equipment and not necessarily the total amount shown in this Schedule.

Line Item 0006 Non-Recurring Work - 2nd Option Period

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

EXHIBIT C - CLIN 9002

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Section J, Page 48 of 75

ELIN /

Sub

ELIN

Description Quantity Unit of Issue

Unit Price Total CAC

1604000 Facility Investment D001 Service Orders D001AA Emergency Service Orders 12 MO -¥ -¥ 712S D001AB Urgent Service Orders 12 MO -¥ -¥ 712S D001AC Routine Service Orders 12 MO -¥ -¥ 712S

D002 Preventive Maintenance (PM) Program

D002AA Compressed Air Distribution Systems. Spec Item 3.2.1

12 MO -¥ -¥ 712S

D002AB Wastewater Instrumentation Systems. Spec Item 3.2.2

12 MO -¥ -¥ 712S

D002AC

Sewage Sump Pumps, Agitators, and Shooters. Spec Item

3.2.3 12 MO -¥ -¥ 712S

D002AD Valves, Piping, and Automatic Controls. Spec Item 3.2.4 12 MO -¥ -¥ 712S

D002AE

Adjustment Tanks, Sewage Tanks, Filtration Tower/Tanks.

Spec Item 3.2.5 1 YR -¥ -¥ 712S

D002AF Chemical Replenishment. Spec Item 3.2.6 12 MO -¥ -¥ 712S

D002AG

Sand and Activated Carbon Filtration System. Spec Item

3.2.7 1 YR -¥ -¥ 712S

D003 Inspection, Testing, and Certification Program D003AA Valves, Piping, and Automatic Controls. Spec Item 3.3.1 12 MO -¥ -¥ 712S D003AB Water Quality Analysis. Spec Item 3.3.2 12 MO -¥ -¥ 712S D003AC Bacterial Analysis. Spec Item 3.3.3 12 MO -¥ -¥ 712S D003AD Engineering Support Services. Spec Item 3.3.4 12 MO -¥ -¥ 712S D003AE Record Keeping 12 MO -¥ -¥ 712S

TOTAL LINE ITEM 0007 RECURRING WORK 3RD OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0007, Net Amount

EXHIBIT D - CLIN 9003

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Line Item 0007 Recurring Work Price - 3rd Option Period

PROVIDE PRICES FOR FACILITY INVESTMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 ELIN D001AA through D003AE.

D001 Sub Total

D002 Sub Total

D003 Sub Total

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

Section J, Page 49 of 75

ELIN Product Name (120 Characters)

Description Extended Estimated Quantity

Unit of Issue

Unit Price Extended Price IMAP CAC(s)

D700 Unit Priced Labor Work for 1604000 -

MUST BE

NEGOTIATED BY

THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order labor cost will be negotiated.

200 HR (Estimated Maximum Labor Cost)

712S

D701 Material Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order material cost will be negotiated. Use with ELIN D700.

1 LS (Estimated Maximum Material Cost)

712S

D702 Equipment Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order equipment cost will be negotiated. Use with ELIN D700.

1 LS (Estimated Maximum Equipment Cost)

712S

D703 Percentage to be added to cost of labor hours for emergency response

Provide an emergency response for repairs when the contractor has to respond to an emergency related Non-Recurring work.

% (Estimated Maximum Emergency Response)

712S

Notes:

(2) UPT work requiring addtional contractual and safety oversight shall NOT be ordered through DoD FEDMALL. If the Contractor SSHO identifies any high risk in the DoD FEDMALL work ordered the Contractor QM shall notify the KO or COR immediately before start of work.

PROVIDE PRICES FOR FACILITY INVESTMENT - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 ELINs D700 through D703.

TOTAL LINE ITEM 0008 NON-RECURRING WORK PRICE 3RD OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0008, Net Amount)

(1) The Government will compensate the Contractor for the direct cost of materials and equipment and not necessarily the total amount shown in this Schedule.

Line Item 0008 Non-Recurring Work - 3rd Option Period

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

EXHIBIT D - CLIN 9003

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Section J, Page 50 of 75

ELIN /

Sub

ELIN

Description Quantity Unit of Issue

Unit Price Total CAC

1604000 Facility Investment E001 Service Orders E001AA Emergency Service Orders 12 MO -¥ -¥ 712S E001AB Urgent Service Orders 12 MO -¥ -¥ 712S E001AC Routine Service Orders 12 MO -¥ -¥ 712S

E002 Preventive Maintenance (PM) Program

E002AA Compressed Air Distribution Systems. Spec Item 3.2.1

12 MO -¥ -¥ 712S

E002AB Wastewater Instrumentation Systems. Spec Item 3.2.2

12 MO -¥ -¥ 712S

E002AC

Sewage Sump Pumps, Agitators, and Shooters. Spec Item

3.2.3 12 MO -¥ -¥ 712S

E002AD Valves, Piping, and Automatic Controls. Spec Item 3.2.4 12 MO -¥ -¥ 712S

E002AE

Adjustment Tanks, Sewage Tanks, Filtration Tower/Tanks.

Spec Item 3.2.5 1 YR -¥ -¥ 712S

E002AF Chemical Replenishment. Spec Item 3.2.6 12 MO -¥ -¥ 712S

E002AG

Sand and Activated Carbon Filtration System. Spec Item

3.2.7 1 YR -¥ -¥ 712S

E003 Inspection, Testing, and Certification Program E003AA Valves, Piping, and Automatic Controls. Spec Item 3.3.1 12 MO -¥ -¥ 712S E003AB Water Quality Analysis. Spec Item 3.3.2 12 MO -¥ -¥ 712S E003AC Bacterial Analysis. Spec Item 3.3.3 12 MO -¥ -¥ 712S E003AD Engineering Support Services. Spec Item 3.3.4 12 MO -¥ -¥ 712S E003AE Record Keeping 12 MO -¥ -¥ 712S

TOTAL LINE ITEM 0009 RECURRING WORK 4TH OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0009, Net Amount

EXHIBIT E - CLIN 9004

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Line Item 0009 Recurring Work Price - 4th Option Period

PROVIDE PRICES FOR FACILITY INVESTMENT - RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 3 ELIN E001AA through E003AE.

E001 Sub Total

E002 Sub Total

E003 Sub Total

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

Section J, Page 51 of 75

ELIN Product Name (120 Characters)

Description Extended Estimated Quantity

Unit of Issue

Unit Price Extended Price IMAP CAC(s)

E700 Unit Priced Labor Work for 1604000 -

MUST BE

NEGOTIATED BY

THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order labor cost will be negotiated.

200 HR (Estimated Maximum Labor Cost)

712S

E701 Material Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order material cost will be negotiated. Use with ELIN E700.

1 LS (Estimated Maximum Material Cost)

712S

E702 Equipment Costs for

1604000 - MUST

BE NEGOTIATED

BY THE KO.

Performance of requirements that exceeds recurring work limitations of 1604000. Each task order equipment cost will be negotiated. Use with ELIN E700.

1 LS (Estimated Maximum Equipment Cost)

712S

E703 Percentage to be added to cost of labor hours for emergency response

Provide an emergency response for repairs when the contractor has to respond to an emergency related Non-Recurring work.

% (Estimated Maximum Emergency Response)

712S

Notes:

(2) UPT work requiring addtional contractual and safety oversight shall NOT be ordered through DoD FEDMALL. If the Contractor SSHO identifies any high risk in the DoD FEDMALL work ordered the Contractor QM shall notify the KO or COR immediately before start of work.

PROVIDE PRICES FOR FACILITY INVESTMENT - NON-RECURRING WORK - IN ACCORDANCE WITH SECTION C, SPEC ITEM 4 ELINs E700 through E703.

TOTAL LINE ITEM 0010 NON-RECURRING WORK PRICE 4TH OPT YEAR

(Enter this amount into Schedule of Work, Item No. 0010, Net Amount)

(1) The Government will compensate the Contractor for the direct cost of materials and equipment and not necessarily the total amount shown in this Schedule.

Line Item 0010 Non-Recurring Work - 4th Option Period

ATTACHMENT J-0200000-10

EXHIBIT LINE ITEM NUMBERS

SOLICITATION/CONTRACT #RFP No.

EXHIBIT E - CLIN 9004

MAINTENANCE SERVICES FOR WASTEWATER TREATMENT PLANT B-961, NAF

MISAWA

Section J, Page 52 of 75

File details come from the government source that posted it. Updated .