Attachment 2 - Hamilton Jet Overhaul Spec Rev. 12-07-2024.docx

DOCX document 104 KB Posted

Attached to
Hamilton Jet Drive Overhaul Combined Synopsis/Solicitation
Solicitation number
70Z04025Q51661B00
Issued by

About this file

This document is a detailed Hamilton Jet Drive Overhaul Specification for the United States Coast Guard (USCG), specifically covering the remanufacturing of Hamilton Jet HJ 292 and HJ 213 jet drive units installed on 17' Cutter Boat-Medium (CB-M) and Cutter Boat-Over the Horizon IV (CB-OTH-IV) boats. The specification requires a comprehensive overhaul process that includes complete disassembly, inspection, mandatory parts replacement, bench testing, preservation, packaging, and technical support, with a 60-calendar day completion timeline from core condition report approval.

Key requirements include using only Original Equipment Manufacturer (OEM) parts, replacing all gaskets, seals, and specified components, conducting thorough bench and load testing, and providing a one-year or 1,000-operating-hour warranty. The contractor must also be prepared to provide on-site technical representative services within 36 hours of notification, potentially traveling to Coast Guard units throughout the continental United States, Hawaii, and Alaska. The solicitation (Number 70Z04025Q51661B00) has a question submission deadline of 24 June 2025 at 2:00 PM EST and a proposal submission deadline of 1 July 2025 at 2:00 PM EST, with the work to be performed for the USCG Surface Force Logistics Center's Small Boat Product Line.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISION No. N/A___

HAMILTON JET DRIVE OVERHAUL SPECIFICATION

FOR

HJ 292 & HJ213

ORIGINATED BY: Thomas Taylor DATE: December 11, 2024

ORIGINATOR’S COMMAND SURFACE FORCES LOGISTICS CENTER

DEPARTMENT / DIVISION SMALL BOAT PRODUCT LINE

INTERNAL REVIEWER_____________________________ DATE____________

SWORB APPROVAL____________________________ DATE____________

HAMILTON JET DRIVES OVERHAUL SPECIFICATION

1.0 SCOPE

1.1 General -This document sets forth the requirements for the overhaul of the following assets to Original Equipment Material (OEM) specifications, parts, and standards:

a. Hamilton Jet HJ 292

b. Hamilton Jet HJ 213 Upon receipt, the contractor shall inspect each wooden or metal crate to determine crates condition. This inspection shall be documented with the crate’s discrepancies, plan of repairs or replacement and cost associated with it.

These Hamilton Jet Drives, with attached hang-ons, shall be bench and/or load tested, preserved, painted, packaged, and shipped back to the Coast Guard Yard, Baltimore, MD. All of the machinery being remanufactured is to be used onboard various U.S. Coast Guard boats.

1.2Government Furnished Property (GFP) – The below listed items are property of, and managed by the USCG Surface Forces Logistic Center (SFLC) Baltimore, MD.
a.Hamilton Jet HJ 213 (NSN: 2010-98-206-2591).
b.Hamilton Jet HJ 292 (NSN: 4320-01-624-5473).
c.Shipping container for HJ 213 (NSN: N/A).
d.Shipping container for HJ 292 (NSN: N/A).

2.0 APPLICABLE DOCUMENTS

2.1. Document Availability – To obtain the referenced documents see section 6.1.

2.2. Government Documents – The following specifications and standards form a part of this specification to the extent specified herein. Unless otherwise specified, the documents listed here by number and date shall be those in the current Department of Defense Single Stock Point (DODSSP) for military specifications, standards, and related publications.

a. USCG Surfaces Forces Logistics Center- D-000-0100 REV G, Dated 2/06, Bar Coding for USCG SFLC Material.

b. USCG SFLC Standard Specification 3101.

2.2.1. Military Specifications

a. MIL-L-2104F, Dated 28 Sep 1992, Lubricating Oil.

b. MIL-D-3464E, Dated 21 Apr 1987, Desiccant, Activated Bag.

c. MIL-PRF-32295A, Dated 19 APR 2010, Cleaner, Non-Aqueous, Low-VOC, HAP-Free.

d. MIL-I-24092D, Dated 21 Sep 1993, Insulating Varnishes and Solvent less Resins for Application by the Dip Process.

e. MIL-STD-2073-1E, Dated May 2008, Standard for Military Packaging.

2.3. Commercial Documents – The Following documents form a part of this specification to the extent specified here. The documents shall be the version listed by number and date from the referenced industry organization. Commercial documents may be listed in the Department of Defense Single Stock Point (DODSSP).

2.3.1. American National Standards Institute (ANSI)/ National Conference of Standards Laboratories (NCSL).

a. ANSI/NCSL Z540, Dated 2006, Requirements for the Calibration of Measuring and Test Equipment.

b. ANSI/ASQC Q9003, Dated 1994, Quality Systems – Model for Quality Assurance in Final Inspection and Test.

2.3.2. American Society for Testing and Materials (ASTM).

2.3.3. Hamilton Jet Corporation.

a. HJ 213 Shop Manual No. HJ-213/HSRX.

b. HJ 213 Parts Manual No. HJ-213/HSRX.

c. HJ 292 Shop Manual No. HJ-292.

d. HJ 292 Parts Manual No. HJ-292.

2.4. Specification Order of Precedence – In the event of a conflict between the text of this specification and the references cited herein, this specification shall take precedence.

2.4.1. Departure from Specification - Departure from this specification shall not be allowed unless approved by the Coast Guard Contracting Officer.

a. If the contractor finds it necessary to implement changes or depart from applicable specifications, they shall be requested.

b. Request for changes by contractors shall clearly describe the changes proposed, the reasons for and advantages of the changes proposed, and the contract’s price increase or decrease (if any) that would result.

3.0 REQUIREMENTS

3.1. General - The contractor shall remanufacture/recondition the jet drive units within sixty (60) calendar days after approval of the Core Condition report (Appendix A). The contractor shall provide all labor, equipment, special tools, parts and materials required to accomplish the following:

a. Submit a Core Condition Report (Appendix A).

b. Submit a Disassembly Report (Appendix B).

f. Perform Bench Testing.

g. Perform Internal Preservation.

j. Preserve and Properly Label Shipping Container.

3.2. Government Furnished Property – The Government reserves the right to supply Government Furnished Property (GFP) at any time during the existence of this contract. The contractor shall provide protective storage for the GFP when not in use, and safe handling when in use.

3.2.1. The storage area shall at a minimum be closed on all sides, dry, and locked when unattended. Uncrated jet drives shall be always stored inside. Empty containers may be stored outside in a covered area.

3.3. Internal Inspection – For any part included on the Disassembly Report (Appendix B) the Contractor shall supply the Contracting Officer’s Representative (COR) with pictures of the faulty part, clearly displaying the part failure.

3.4. Overhaul Parts – The contractor shall use only OEM parts for the overhaul of the Hamilton Jet Drives.

3.5. All gaskets, seals, o- rings, copper seals, hoses, belts, and sensors shall be replaced with new regardless of condition. At a minimum, all parts listed in Appendix F shall be replaced during the remanufacturing. All other parts not listed shall be inspected for critical dimensions and wear limits and replaced as authorized by the KO. The Government reserves the right to supply parts as Government Furnished Property at any time during this contact.

3.6. Propulsion Unit – The Hamilton Jet HJ 213 & HJ 292 units shall be remanufactured in accordance with OEM specifications and standards, restoring each unit to a like- new condition.

3.7. Technical Representative Services – After the contractor overhauls the Jet Drives, within the warranty time frame, any troubleshooting and repair of technical problems may require Contractor personnel to travel to Coast Guard units. In correcting technical problems, the Contractor shall abide by the following:

3.7.1. Technical Services Performed Onsite – The Contractor shall perform all services onboard the USCG vessel unless otherwise directed by the Contracting Officer.

Hours of Operation – The Contractor employees shall generally perform all work between the hours of 0800 and 1630 local time, Monday through Friday. However, Contractor employees shall be required to work other than normal business hours, including weekends and holidays.

Locations – The services will primarily be required in vessel homeports located throughout the continental United States, Hawaii and Alaska.

Contractor Response – The Contractor shall be required to supply a Technical Representative to the designated location within thirty-six (36) hours after notification by the Contracting Officer. The Contracting Officer shall establish the dates the Technical Representative is required.

Task Orders (T.O.) – Surface Forces Logistics Center (SFLC) will issue a T.O. stating where and when the services are required. SFLC will supply the Contractor with the nature of the problem (if known) along with a POC and phone number. The Contractor shall be responsible to contact the POC within twenty-four (24) hours after notification by the Contracting Officer.

The results of the Representative's findings shall be provided in writing within twenty-four (24) hours of arrival. Approval to perform repairs will be made by the Contracting Officer after evaluation from the USCG Contracting Officer’s Technical Representative.

3.8. Paint Requirement for Metal Shipping Containers- All internal & external surfaces shall have all scale and loose paint removed. The containers will then be primed as per The Society for Protective Coatings (SSCP) Paint 25 and painted with two coats of the corresponding colors mentioned below and sited in [FED STD 595 C with CHANGE NOTICE 1] using paint in accordance with Commercial Item Description (CID) A-A-2962A.

a. Shipping container for Hamilton Jet, HJ 213 & HJ 292 – Use color number.

3.9. Labor – Contractor shall perform all labor, and authorized machinists, mechanics and technicians.

3.10. Core Acceptance Criteria – The contractor shall accept the core based on a complete internal inspection and submit written notification and reasoning of non-acceptance for jet drive units not acceptable for overhaul within ten (10) calendar days after the receipt of the jet drive units.

3.11. Documentation – This specification sets forth the requirements for the following documentation.

a. Core Condition Report, in accordance with Appendix A

b. Disassembly Report, in accordance with Appendix B

c. Bench Test Report, in accordance with Hamilton Jet

d. Mandatory Replacement Parts List in accordance with Appendix C

e. Contingency Replacement Parts List in accordance with Appendix D

f. Warranty Notice in accordance with Appendix E

3.12. Core Condition and Disassembly Reports – The contractor shall submit a completed Appendix A to the contracting officer within ten (10) calendar days after receipt of a jet drive unit. Appendix B will be sent to the contracting officer (15) fifteen calendar days after Appendix A.

3.13. Warranty - A warranty of one year from installation or 1000 operating hours, whichever occurs first, and 24 months of storage is required covering the entire jet drive unit. Storage commences upon receipt of engine at the designated Coast Guard facility. The contractor shall contact the field unit to arrange a resolution of a claim within 24 (twenty-four) hours after receiving notification by the Coast Guard of a warranty claim. The contractor shall contact SFLC’s Contracting Officers Representative (COR) to evaluate the contractor’s proposed duration of warranty repair time.

In the event the Coast Guard decides the proposed warranty repair time compromises the Coast Guards mission and decides on removal/replacement, the contractor shall coordinate and fund all necessary shipping arrangements for the failed jet drive to be returned to the origin of exchanged/overhaul facility for repairs and returned to a designated Coast Guard facility after repairs have been completed.

The contractor shall repair/rebuild the failed jet drive to the condition level necessary for the contractor to honor a new full warranty (to be funded by the Coast Guard.) In the event that the work is found not to be warranted, the contractor shall stop work immediately and contact the Contracting Officer.

The contractor shall submit to the Contracting Officer an inspection report for approval containing any parts and pricing for any work/repairs that are required that were not a result of the specific casualty.

3.14. Notifications & Inspections – The contractor shall be responsible for notifying the Contracting Officer’s Contracting Officer Representative (COR) at least seven (7) calendar days prior to inspections or monitored testing required herein.

3.15. Failure Analysis - In the event of a failure, the Technical Representative shall determine the cause of casualty, systems, root cause, and corrective action. And a report of the findings shall be submitted to the Contracting Officer.

3.0 QUALITY ASSURANCE

4.1. General – The contractor shall maintain an inspection system, which shall insure that each item offered to the Coast Guard for acceptance, or approval conforms to the contract requirements. The inspection system shall be documented, meet the requirements of ASQC-Q9003-1994 and be available for review by the Coast Guard.

4.2. Records – The contractor shall maintain records of all inspections and tests. The records at a minimum shall indicate the nature and number of observations made, the number and type of deficiencies found, and the corrective action taken.

4.3. Calibration System – The contractor, as well as any subcontractors, shall be required to maintain a test equipment calibration program in compliance with ANSI/NCSL Z540, Dated 2006. The program shall be documented and traceable to the National Institute of Standards (NIST).

4.4 Responsibility for Inspection – The contractor shall be responsible for the performance of all inspection requirements specified herein. The contractor shall provide space, personnel, and test equipment for conducting all inspection requirements. All inspection and testing shall be performed at the contractor’s plant or at other facilities acceptable to the Coast Guard. The Coast Guard reserves the right to verify or have performed any of the inspections that are deemed necessary to assure that supplies and services conform to the prescribed requirements. The contractor shall notify the KO seven (7) working days prior to all inspections and tests.

4.5 Responsibility for Compliance – All items shall meet the provisions of sections 3 & 5. The inspections set forth in this specification shall become part of the contractor’s overall inspection system or quality program. The absence of any inspection requirements in the specification shall not relieve the contractor of the responsibility of assuring that all products or supplies submitted to the government for acceptance comply with all requirements of the contract. Sampling for quality conformance does not authorize submission of known defective material (either indicated or actual) nor does it commit the government to acceptance of defective material.

4.6 Inspection System – The contractor shall maintain an inspection system, which shall insure that each item offered to the Coast Guard for acceptance, or approval conforms to the contract requirements. The inspection system shall be documented and available for review by the Coast Guard.

4.7 Tests & Inspections – The inspections/tests required here is the minimum required and are not intended to replace any controls, examination, inspections or tests normally employed by the contractor to assure the quality of the jet drive unit.

4.7.1 Each jet drive provided under this contract shall be tested/ inspected on an approved bench test under load to ensure the jet drive unit performance is in accordance with the manufacturer’s requirements. The contractor shall complete and submit the report required as per the Hamilton Jet Manual.

4.8 Bench Test Reports – The contractor shall submit a bench test report, per the manufacture manual, within seven (7) calendar days after completion of the bench test. The report shall consist of the data obtained during the prime unit test. One copy of the report shall be packed and delivered with each jet drive unit under this contract.

4.9 Failure Responsibility – If the jet drive unit fails to pass any inspection/test the contractor shall report the failure and the recommended solution to the Contracting Officer. If approved, the corrective action on the materials or processes shall be taken in accordance with this section.

a. The inspection/test shall be discontinued until all corrective action has been taken.

b. After all corrective actions have been taken the inspection/test shall be continued or repeated at the option of the Contracting Officer.

c. Acceptance shall be withheld until re-inspection has been shown that the corrective action was successful, and the item satisfactorily passes all inspections and tests.

d. All corrective actions shall be documented as part of the contractor’s inspection system and submitted for approval to the Contracting Officer.

5.0 PRESERVATION, PACKAGING, PACKING, & MARKING

5.1. Internal Preservation – Preservation in accordance with O.E.M. Policy shall not be started until a successful dynamometer test has been completed and accepted by the Contracting Officer’s Representative (COR).

5.2. External Preservation – After completion of the internal preservation, the jet drive unit shall be prepared in accordance with the following procedure.

a. All surfaces shall be cleaned of grease and oil.

b. All loose scale and paint shall be removed; areas feathered and brought to a smooth surface.

c. The following items shall be masked and not painted.

1. Rubber hoses and wires

2. All identification plates

3. The jet drive shaft output flange

4. The front and rear seals

d. All exposed metal surfaces shall be primed with one coat (2-3 mils) of primer in accordance with Hamilton Jet. Allow a minimum of seven (7) hours to dry.

e. Two color coats approximately (2 mil’s); total thickness (3-5 mil’s) shall be sprayed on all surfaces. Allow seven (7) hours drying time between coats. The color shall be Hamilton Marine Grey.

f. When all paint is dry, the masking shall be removed.

g. Coat all unpainted metal surfaces with a light amount of grease, except for hot surfaces.

h. Plug any fittings/flanges or openings that will allow foreign material to enter the engine during storage.

i. A completed Appendix D and Appendix E shall be attached to the top of the jet drive unit in a plastic bag.

j. The contractor shall place a total of 80 units of desiccant conforming to MIL-D-3464E (activated bag: 1 ounce equals 1 unit), in the interior of the shipping container in the receptacle provided.

k. The contractor shall install the jet drive unit into the metal or wooden shipping container. The contractor shall ensure that all of the container accessories (if applicable), such as rubber mounts, desiccant, humidity indicator, pressure valve, and sealing gasket are in place and in good working order. The container shall be sealed such that the cover makes 100% contact with the sealing gasket.

l. The Humidity Indicator (if applicable) shall have the inner retaining nut permanently attached to the inside of the container to allow for the removal and replacement of the indicator.

5.3. Marking – Each preserved and packaged item shall be marked in the upper left-hand side and end of each box. The lettering shall be stenciled and at least 1” high, in black print lettering on a highly contrasting background.

5.3.1. This marking shall consist of the STOCK NUMBER, MODEL NUMBER, ITEM NAME, SERIAL NUMBER, CONTRACT NUMBER, TASK ORDER NUMBER, GROSS WEIGHT (in lbs), CONDITION CODE, QUANTITY AND UNIT OF ISSUE, AND LABELED; COAST GUARD SFLC MATERIAL.

Stock Number2010-98-206-2591 for HJ 213 & 2010-01-624-5473 for HJ 292
Model NumberHJ 213 or HJ 292
Item NameJet Drive Assembly
Serial NumberSee the jet drive
Contract NumberSee Contract
Task Order NumberSee Task Order
Shipping WeightAs Determined By Contractor
Condition CodeCondition “A”
Quantity & Unit of Issue1 – Each

(And the Following):

Reusable Shipping Container – Do Not Damage. Do Not Stack More Than Two High. Remove Bolts Prior To Removing Cover. Use Forklift To Unload – Do Not Lift By Cover. Preserved For Long Term Storage.

5.3.2. Special Markings – (IF APPLICABLE) The container shall be marked with the following special markings:

a. LOCATING DOWEL (place above locating dowel, if applicable)

b. VENT: DO NOT BLOCK (place next to vent, if applicable)

c. HUMIDITY INDICATOR (place next to indicator, if applicable)

5.3.3. The contractor shall paint over all other marking not required by paragraph 5.3.

5.4. Bar Coding – The contractor shall supply bar code labels on all Contract Line-Item Number’s (CLIN) except for those that require data submissions only.

5.4.1. All bar-coded labels shall be in accordance with SFLC specification D-000-0100 Rev G, FEB/06.

a. The actual labels shall be Type “V“. Grade “A“, Style “2“, Composition “B” with plastic laminate.

b. Each label shall contain encoded data for the Stock Number, Contract Number, and the Task Order Number as applicable.

c. The marking required in 5.3 can be applied separately or as part of the Bar Code Label.

6.0 NOTES

6.1. Government & Commercial Document Sources

6.1.1. Government Documents

a. Department of Defense Single Stock Point for Military Specifications, Standards, and Related Publications (DODSSP Documents) Http://dodssp.daps.dla.mil/

b. DOD & Navy Publications and Forms (Other Than DODSSP) Naval Publication and Forms Center 5801 Tabor Ave.

Philadelphia, PA 19120 215-697-2000

c. USCG Surface Forces Logistics Center 2401 Hawkins Point Road Baltimore, MD 21226-5000 410-762-6229 ATTN: Contracting Officer SBPL

6.1.2. Commercial Documents

a. Society of Automotive Engineers INC. (SAE) 400 Commonwealth Drive Warrendale, PA 15096 412-776-4841

FAX 412-776-5760

b. American Society for Testing & Materials (ASTM) 1916 Race Street Philadelphia, PA 19103-1187 215-299-5585

FAX 215-977-9679

c. American National Standards Institute (ANSI) 1430 Broadway New York, NY 10018 212-642-4900

d. American Society for Quality Control (ASQC) 611 East Wisconsin Avenue Milwaukee, Wisconsin 53202

6.2. Appendices – The following Appendices form a part of this specification.

Appendix A: Core Condition Appendix B: Disassembly Report Appendix C: Mandatory Replacement Parts List Appendix D: Contingency Replacement Parts List Appendix E: Warranty Notice

6.3. Glossary

a. C.P.L. – Control Parts List

b. Core – Either the engine block or the generator housing including the attachments mentioned in Appendix A.

c. Field Unit – United States Coast Guard units located throughout the fifty (50) United States and it territories.

d. O.E.M. – Original Equipment Manufacturer

e. O.E.P.L. – Original Equipment Parts List

f. Prime Mover – An engine used to transfer power, in the form of a turning motion, to the generator or reduction gear.

g. Jet Drive Unit – Jet Drive Units listed in section 1.2, B through E.

h. Exchange – Exchange of used parts for original equipment manufacturer (OEM) parts.

i. Recondition – To recondition parts with O.E.M. parts to O.E.M. new specifications.

USCG-SFLC

APPENDIX A

Core Condition Report (For HJ 213 & HJ 292) Work Order #____________ Task Order #__________ Jet Drive Serial # _______________ Jet Drive Model # ___________________ Core Acceptance is based on the following:

a. Core must be in the configuration of Master Serial Numbers listed above (Section 1.2).

b. Core must have no non-operational damage.

c. Core must be a complete unit and not disassembled.

NOTE: Missing parts from Appendix A are to be replaced and priced as per Appendix B of this contract.

1. Core Acceptable__________, Non-Acceptable___________ Remarks _______________________________________________________________________________

2. Condition of shipping container;

Serviceable_______________________
Needs Repair_____________________

3. Photograph of prime mover; front, right side, left side, and rear views to include serial number in picture frame.

APPENDIX A

(CONTINUED)

Jet Drive Model (Circle one): HJ 213 & HJ 292

ITEM
NAME
P/N
MISSING
1.
SAGINAW PUMP
2.
REVERSE DUCK
3.
STEERING NOZZLE
4.
STEERING SHAFT
5.
TAILPIPE
6.
HSRX CYLINDER
7.
IMPELLER
8.
INTAKE GRATE
9.
WEAR RING
10.
DRIVE COUPLING
11.
THRUST BEARING ASSY.
12.
WATER BEARING SLEEVE
13.
DRIVE BELT
14.
PIVOT PIN
15.
PIVOT BUSHINGS
16.
ROTARY SEAL

METAL SHIPPING CONTAINER:

ITEM
NAME
P/N
MISSING
1.
HUMIDITY INDICATOR
2.
SEALING GASKET
3.
VALVE, PRESSURE
4.
RUBBER MOUNT
5.
WOOD SKID

REMARKS:

Disassembly Report B

Task Order Number: ___________________

Date: ___________________________________

Jet Drive Model Number: ____________________

Jet Drive Serial Number: ____________________

Reason for Replacement
Qty
Part No.
Part Description
Unit Price
Amount

Total

APPENDIX C

MANDATORY REPLACEMENT PARTS LIST

MACHINERY DESCRIPTION

Manufacturer
Hamilton Jet
Jet Drive Model #
HJ 213
Description
Reverse and Forward Propulsion

Item Serial Number

MANDATORY REPLACEMENT PARTS FOR EACH REMANUFACRURE

No.
Description
Part No.
Qty.
UoI
Total Price
1
Water Seal 213-241
61483
1
EA
2
O-ring 5.34x85.1x9508 340n70
61488
1
EA
3
Rotary Seal Grease
61458
2
EA
4
Seal Sleeve 213
106004
2
EA
5
Bearing (Thrust)
201439
1
EA
6
Carrier Bearing
106005
1
EA
7
Holder, Seal Face MK2 213 241
111717
1
EA
8
Split Pin
201074
1
EA
9
Bearing Marine
106011
1
EA
10
Bearing Sleeve
110379
1
EA
11
O-ring
200985
1
EA
12
Wear Ring
107537
1
EA
13
Insulator Wear Ring
107538
1
EA
14
O-ring Tailpipe
200999
1
EA
15
Anode Aluminum
212094
4
EA
16
O-Ring 25.07 x 2.62
64726
3
EA
17
V-Belt PJ559 10
64430
2
EA
18
O-Ring
200964
1
EA
19
Bushing Steering
105998
2
EA
20
Pin Cotter Assy
103171
1
EA
21
Ball Joint Morse S.S.
201553
1
EA
22
O-ring
200962
2
EA
23
Clamp & Shim Assembly Morse
80934
1
EA
24
Bush Flange Pivot Steering
111387
2
EA
25
Seal, Bonded
64996
1
EA
26
Seal, Bonded
201767
2
EA
27
HSRX Hose Kit HJ213
CTHSE12002
1
EA
28
Pivot Duct Rev
111723
2
EA
29
Nut Nyloc M8
201330
13
EA
30
Washer Flat
201383
6
EA
31
Bush Rod Cylinder Rev
111808
1
EA
32
Anode mk3
203124
5
EA
33
Hex Nut M8
201309
10
EA
34
Washer Spring M8
201394
19
EA
35
O-Ring 314 X 9.5 Transom
107618
1
EA
36
Relief Valve
202986
1
EA
37
Kit Seal HSRX mk2
112078
1
EA
38
Saginaw Pump Kit, Zinc Plated
206264
1
EA
MANDATORY REPLACEMENT PARTS LIST (CONT’)
MACHINERY DESCRIPTION
Manufacturer
Hamilton Jet
Jet Drive Model #
HJ 213
Description
Reverse and Forward Propulsion

Item Serial Number

MANDATORY REPLACEMENT PARTS FOR EACH REMANUFACTURE

No.
Description
Part No.
Qty.
UoI
Total Price
39
Crank Str
107550
1
EA
40
Plate Anode
109702
1
EA
41
Zerk, Grease
200917
1
EA
42
Bushing Shld Str
109515
1
EA
43
Anode Hatch
203123
1
EA
44
Bearing Grease Tube
GREASE
1
EA
45
O-Ring Cooler
109836
1
EA
46
Washer M10 Flat
201834
4
EA
47
Nut Nyloc M10
201331
4
EA
48
O-Ring Rake Plug
200994
2
EA
49
Sealant Installation
201414
1
EA

MACHINERY DESCRIPTION

Manufacturer
Hamilton Jet
Jet Drive Model #
HJ 292
Description
Reverse and Forward Propulsion

Item Serial Number

MANDATORY REPLACEMENT PARTS FOR EACH REMANUFACTURE

No.
Description
Part No.
Qty.
UoI
Total Price
1
Anode Aluminum
203133
8
EA
2
Anode Aluminum
203130
1
EA
3
Anode Aluminum
203123
2
EA
4
Anode Aluminum
203124
1
EA
5
Anode Aluminum
203131
4
EA
6
Belt
203969
4
EA
7
Saginaw Pump Kit
206264
1
EA
8
Saginaw Pump Sensor
202993
1
EA
9
Valve Assembly
111554
1
EA
10
Parker Valve Spool Cover MK2
209327
1
EA
11
Parker Valve Spool Cover MK2
209327-1
1
EA
12
Insert Tube Plastic
208151
4
EA
13
Nut Nyloc M8 SS316
201330
14
EA
14
Nut M8
201309
8
EA
15
Washer Spring M8
201394
22
EA
16
O-Ring 304x 1.78
104916
1
EA
17
Bearing Marine
106265
1
EA
18
Sleeve Bearing Marine
111202
1
EA
19
O-Ring 132.72x 6.99
200991
1
EA
20
Wear Ring 292
104211
1
EA
21
Insulator Wear Ring
104674
1
EA
22
Seal Impeller
104190
1
EA
23
Bushing Shaft Steering
111124
2
EA
24
Seal Oil
61362
1
EA
25
Seal Scraper Wyclip
61353
1
EA
MANDATORY REPLACEMENT PARTS LIST (CONT’)
MACHINERY DESCRIPTION
Manufacturer
Hamilton Jet
Jet Drive Model #
HJ 292
Description
Reverse and Forward Propulsion

Item Serial Number

MANDATORY REPLACEMENT PARTS FOR EACH REMANUFACTURE

No.
Description
Part No.
Qty.
UoI
Total Price
26
Bush Pivot Steering
111480
2
EA
27
Washer
105139
2
EA
28
Lip Seal
111332
2
EA
29
Kit, Seal Rev Cyl MK2 HJ292
112516
1
EA
30
Bush Pivot
104610
2
EA
31
Washer Poly
63955
2
EA
32
Bearing
201447
1
EA
33
Seal, Oil
201449
2
EA
34
Sleeve Seal
104617
2
EA
35
Seal Rotary
61528
1
EA
36
O-Ring 113.89x 3.53
200978
1
EA
37
Bearing Carrier
104621
1
EA
38
O-Ring 66.27x 3.53
206347
2
EA
39
Element Filter
63699
1
EA
40
O-Ring 228.19x 3.53
200998
1
EA
41
O-Ring 36.09x 3.53
200967
2
EA
42
O-Ring 418x 9.5 Transom
111183
1
EA
43
Seal Bonded P-line switch
64996
2
EA
44
Hose Kit
CTHSE12019
1
EA
45
Bearing
201457
1
EA
46
Rod End
65072
1
EA
47
Washer Lock Internal
65073
1
EA
48
Clevis & Pin Kit SS316
106261
1
EA
49
Pin Split
201077
2
EA
50
Seal Bonded 1/2
201768
3
EA
51
Seal Bonded 3/8
201767
1
EA
52
Seal Bonded 1/4
201766
2
EA
53
Rod End
201475
2
EA
54
Clamp & Shim Assy Morse
80934
1
EA
55
Circlip General
104201
1
EA
56
3.0mm
111479-2
1
EA
57
3.5mm
111479-3
2
EA
58
O-Ring Tube Base
204357
1
EA
59
Plate Anode
111655
1
EA
60
Crank
109241
1
EA
61
Bush Crank
109706
1
EA
62
Zerk Grease
200917
1
EA
63
Zerk Rev
200918
1
EA
64
Coupling HJ292
204465
1
EA
65
Sealant Installation
201414
1
EA
66
Loctite 243 Installation
201714
1
EA
67
Sleeve Rev
112338
1
EA
68
Nyloc Nut M12
201332
4
EA

APPENDIX D

CONTINGENCY REPLACEMENT PARTS LIST
MACHINERY DESCRIPTION
Manufacturer
Hamilton Jet
Jet Drive Model #
HJ 213 & 292
Description
Reverse and Forward Propulsion

Item Serial Number

MANDATORY REPLACEMENT PARTS FOR EACH REMANUFACTURE

No.
Description
Part No.
Qty.
UoI
Total Price
1
REVERSE DUCT KIT HJ292
112243
1
EA
2
STEERING NOZZLE KIT HJ292
111512
1
EA
3
PIVOT PIN HJ292
111481
2
EA
4
PIVOT BUSHING WASHER (SN) 2.5mm
111479-1
2
EA
5
4.0mm
111479-4
2
EA
6
SLEEVE PIVOT BUSHING HJ292
111483
2
EA
7
STEERING SHAFT HJ292
111203
1
EA
8
TAILPIPE KIT HJ292
111239
1
EA
9
HSRX CYLINDER
112515
1
EA
10
IMPELLER 2.9kW HJ213
106228
1
EA
11
IMPELLER 4.2kW HJ213
211658
1
EA
12
INTAKE GRATE (0°)
111033
1
EA
13
INTAKE GRATE (5°)
111034
1
EA
14
DRIVE COUPLING (871)
108632
1
EA
15
DRIVE COUPLING (1062)
108634
1
EA
16
THRUST BEARING ASSY.
111240
1
EA
17
PIVOT PIN (REVERSE BUCKET)
104609
2
EA
18
PIVOT BUSHING REV THREADED
104608
2
EA
19
REVERSE CYLINDER HJ213
112079
1
EA
20
SAGINAW ASSEMBLY (PUMP & PULLEY HJ213)
110857
1
EA
21
SPRING WASHER
201394
10
EA
22
COTTER PIN
102834
2
EA
23
HEX NUT
201310
2
EA
24
WASHER 25MM
102993
3
EA
25
LOCK WASHER
201395
2
EA
26
CONNECTING PIN
106503
1
EA
27
SPLIT PIN 3/32IN x 3/4IN
201063
1
EA
28
REVERSING CYL. BUSH PIN
111014
2
EA
29
REVERSE DUCT KIT HJ213
112241
1
EA
30
STEERING NOZZLE (SN)
109842
1
EA
31
PIVOT PIN (SN)
30763
2
EA
32
PIVOT BUSHING (SN)
107676
2
EA
33
PIVOT BUSHING WASHER (SN)
111712
2
EA
34
STEERING SHAFT
111721
1
EA
35
TAILPIPE ASSY HJ213
111776
1
EA
36
INTAKE GRATE (0°)
109766
1
EA
37
THRUST BEARING ASSY.
109839
1
EA
38
PIVOT PIN (REVERSE BUCKET)
201160
2
EA
39
PIVOT PIN REV HJ213 (RB)
111722
2
EA
40
PIVOT BUSHING REV HJ213 (RB)
111723
2
EA
CONTINGENCY REPLACEMENT PARTS LIST (CONT’)
MACHINERY DESCRIPTION
Manufacturer
Hamilton Jet
Jet Drive Model #
HJ 213 & 292
Description
Reverse and Forward Propulsion

Item Serial Number

MANDATORY REPLACEMENT PARTS FOR EACH REMANUFACTURE

No.
Description
Part No.
Qty.
UoI
Total Price
41
PIVOT BUSHING WASHER REV HJ213 (RB)
111724
2
EA
42
Bearing
201466
1
EA
43
Washer
103637
1
EA
44
Washer Adjusting Stepped
111712
2
EA
45
Washer Duct Rev
111724
2
EA
46
COVER INSPECTION
212140
1
EA
47
STUD M8x56
109411
1
EA
48
MAINSHAFT
109754
1
EA
49
HOUSING BEARING
108568
1
EA
50
NUT COUPLING/IMPELLER
203395
2
EA
51
KEY COUPLING/IMPELLER
110343
2
EA
52
TAILPIPE KIT HJ213
111776
1
EA
53
BUSHING STR PIVOT
107676
2
EA
54
SHAFT, STEERING
111721
1
EA
55
INSERT STR
110236
1
EA
56
SHAFT ASSY REV
109775
1
EA
57
BUSHING REV PIVOT
111722
2
EA
58
TRANSOM PLATE HJ213
108881
1
EA
59
FRONT HEAD KIT REV
112239
1
EA
60
BACK HEAD KIT REV
112049
1
EA
61
HANDLE HSRX
106561
1
EA
62
SCREW SET M6x10
201244
1
EA
63
WASHER M6 FLAT
201382
5
EA
64
CABLE PLATE HSRX
108553
1
EA
65
SPOOL HSRX
108569
1
EA
66
BARREL
108572
1
EA
67
NUT RETAINING HSRX
108550
1
EA
68
WASHER FLAT HSRX
108564
1
EA
69
PIN STOP
108927
1
EA
70
NOZZLE HOUSING KIT
111406
1
EA
71
NOZZLE KIT
205659
1
EA
72
OIL COOLER COVER
109750
1
EA
73
SPLASH GUARD
111649
1
EA
74
SCREEN INTAKE
109766
1
EA
75
STUD M12x78
111617
4
EA
76
MOUNT HYD PUMP
108618
1
EA
77
ARM TENSIONER PUMP
303222
1
EA
78
SCREW M680
303131
1
EA
79
BLOCK TENSIONER SAGINAW
303133
1
EA
80
INTAKE KIT HJ213
109837
1
EA
81
SCREW M16x45
30763
2
EA
82
BOLT M16x50
201160
2
EA
83
STUD M8x51
30661
1
EA
84
STUD M12x90
103927
3
EA
CONTINGENCY REPLACEMENT PARTS LIST (CONT’)
MACHINERY DESCRIPTION
Manufacturer
Hamilton Jet
Jet Drive Model #
HJ 213 & 292
Description
Reverse and Forward Propulsion

Item Serial Number

MANDATORY REPLACEMENT PARTS FOR EACH REMANUFACTURE

No.
Description
Part No.
Qty.
UoI
Total Price
85
WASHER M12 SPRING
201396
7
EA
86
NUT M12
201311
7
EA
87
IMPELLER 22.4kW HJ292
207777
1
EA
88
FAIRING IMPELLER
210253
1
EA
89
SCREW SET M6
201243
3
EA
90
FAIRING TAILPIPE
104618
1
EA
91
STEERING ARM
109240
1
EA
92
SHAFT STR
111203
1
EA
93
FILTER ASSY
63703
1
EA
94
HSRC FEEDBACK ASSY
CTVLV01007
1
EA
95
SEASTAR STEERING RAM
65024
1
EA
96
PULLEY 2 BELT
203961
1
EA
97
SWITCH & MANIFOLD ASSY
110858
1
EA
98
BRACKET PUMP
109190
1
EA
99
TENSIONER PUMP
303129
1
EA
100
COUNTERBALANCE VALVE
201843
2
EA
101
RELIEF VALVE
201844
1
EA
102
LEVER HSRC
107150
1
EA
103
BUSH HSRC
107149
1
EA
104
SCREW M5x35
30836
4
EA
105
WASHER LOCK M5
201393
4
EA
106
HSRC MOUNT PLATE
107262
1
EA
107
BLOCK HSRC
111262
1
EA
108
SHAFT ASSY REV
111226
1
EA
109
FRONT/BACK HEAD
107416
2
EA
110
EXTENSION FRONT HEAD
112337
1
EA
111
CYLINDER
106555
1
EA
112
NUT RETAINING
111207
1
EA
113
WASHER REV GLAND
112341
1
EA
114
NOZZLE HOUSING KIT
111513
1
EA
115
NOZZLE INSERT
109239
1
EA
116
STUD M10x51 STR
206680
16
EA
117
KMT BEARING NUT
63937
1
EA
118
BEARING HOUSING
111038
1
EA
119
BEARING CAP
111069
1
EA
120
HOUSING STEERING BUSH
111123
1
EA
121
TRANSOM PLATE
111037
1
EA
122
REVERSE CYLINDER ASSY
112515
1
EA
123
STUD M12x54
30658
4
EA
124
TILLER
111344
1
EA
125
BUSH PUMP
110806
1
EA
126
NIPPLE 3/8 x 1/2 BSPP
205066
3
EA
127
NIPPLE 1/4 x 1/4 BSPP
205062
4
EA

APPENDIX E

HAMILTON JET 213 & 292

WARRANTY NOTICE

This item has a warranty for whichever comes first:

1 year of operation from installation Or 1000 hours of operation If any discrepancies are noted upon receipt

1. DO NOT REPAIR OR REPLACE!

2. CALL: USCG SURFACE FORCES LOGISTICS CENTER

CENTRAL ENGINE REMANUFACTURE

SMALL BOAT PRODUCT LINE (SBPL)

COMMERCIAL (410) 762-6237/6159

Have the following information ready when calling the (SBPL)

________ Date Received________ Date Installed
________ Serial No.________ Vessel Home Port
________ Engine Hours________ Vessel Hull No
3. A Report of Discrepancy (ROD) Form 364 must also be submitted to Surface Forces Logistics Center.

NOTES:

(1) Preventative Maintenance (PMS) should still be performed as per applicable Maintenance Procedure Cards (MPC’s). PMS does not void the warranty.
(2) If the above procedure is not followed, the warranty may be affected.

File details come from the government source that posted it. Updated .