Attachment 2_FY26_NASA_Wallops_Survey_Price Spreadsheet.pdf

PDF 544 KB Posted

Attached to
PRE-DEMOLITION SURVEY VARIOUS BUILDINGS NASA WALLOPS FLIGHT FACILITY SURVEY WALLOPS, VA
Solicitation number
W912DY26RA086
Issued by

About this file

This is a cost proposal worksheet for a Facilities Reduction Program pre-demolition survey contract at NASA Wallops for Fiscal Year 2026. The project encompasses 19 facilities requiring assessment and potential abatement and demolition services.

The proposal is structured in three sections: Section #1 addresses sunk costs including pre-mobilization documentation, pre-demolition building assessment, mobilization/site setup, de-mobilization, and contractor reporting; Section #2 itemizes ACM (asbestos-containing materials) abatement and demolition by individual structure, covering 19 facilities totaling 101,108 square feet, ranging from the 28,200 square foot Cafeteria/Photo Lab (E-002) to small structures such as chemical storage buildings (69-195 square feet); Section #3 provides aggregate pricing for abatement, demolition, site restoration, and salvage value. The facilities include various building types such as laboratories, administrative offices, utility structures, and specialized facilities like a gymnasium, radar control building, and meteorological development lab. All cost fields remain blank in the template, indicating this is a framework for contractor pricing submission. The worksheet references specific Performance Work Statement (PWS) paragraphs governing survey requirements and reporting obligations. The grand total cost is calculated both with and without Option 1, though specific option details are not defined in this document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Company Name:

Project Site/Locations: NASA Wallops Survey Contract Phase: Pre-Demolition Survey Proposal Date:

Fiscal Year: FY26 Number of Facilites: 19 Facilities SECTION #1 Sunk Costs

Item Number Description UOM Units Unit Price Extension 1 Pre-Mobilization Documentation (PWS Par. 4.2 & 4.3 specifically) LS 1 -$ 2 Pre-Demolition Building Assessment N/A 3 Mobilization/Site Setup (PWS Par. 3.3.1) LS 1 -$ 4 De-mobilization (PWS Par. 3.3.1) LS 1 -$ 5 Contractor Reporting (PWS Par. 4.5 thru EOF) LS 1 -$

Section #1 - Sunk Cost of Project: -$ SECTION #2 ACM Abatement and Demolition (by structure)

(PWS Par. 4.3.2., 4.3.3, 4.3.4, and 4.3.5 associated with Par. 4.4) Item Number RPID# Facility Number Facility Type UOM # of Units Extension

1 610-20 E-002 CAFETERIA / PHOTO LAB SF 28,200 -$

2 310-50 F-160 HEALTH/QUALITY VERIFICATION LAB /ENVIRONMENTAL BLD SF 22,300 -$

3 811-90 A-003 TAXIWAY LTG / SWITCHGEAR B SF 400 -$

4 610-90 A-131 SOURCE EVAL BD BUILDING SF 900 -$

5 740-43 D-010 GYMNASIUM/SPECIAL OPERATIONS SF 14,880 -$

6 610-90 E-007 ASB RCDS STOR/POST OFC/MAIL / FILE SF 8,000 -$

7 730-90 F-004 SF 13,731 -$

8 216-20 H-030 FOUR CAR GARAGE/WEMA SF 2,100 -$

9 610-90 J-093 VIC CONCESSION BUILDING SF 1,000 -$

10 610-90 N-133 CREDIT UNION ADMINISTRATIVE OFFICE BUILDING SF 1,500 -$

11 610-90 N-134 VA COMM SPACE FLIGHT AUTHORITY OFFICE SF 600 -$

12 442-90 X-036 UTILITY SHOPS STORAGE SHED SF 400 -$

13 381-20 X-086 METEOROLOGICAL INSTRU DEVELOP LAB SF 510 -$

14 140-10 Y-060 ISLAND RADAR CONTROL BUILDING (ICC SF 3,500 -$

15 381-50 Z-040 LAUNCH AREA "0" SERVICE BUILDING SF 2,575 -$

16 310-30 E-011 Groundwater Remediation FAC-Pump/Blower SF 195 -$ 17 442-90 F-163 Chemical Storage Building SF 120 -$

18 442-90 F-164 RAIN SIMULATION EQUIPMENT SHELTER SF 128 -$

19 442-30 N-218 Chemical Storage Building SF 69 -$

TOTALS Section #2 Cost: -$ SECTION #3 TOTAL SF 101,108 Aggregate Unit Cost: N/A

(PWS Par. 4.3.2., 4.3.3, 4.3.4, and 4.3.5 associated with Par. 4.4) Abatement Demolition Site Restoration Salvage Item Number RPID# Facility Number Facility Type UOM # of Units Unit Price Unit Price Unit Price Value Extension

1 -$ 2 -$ 3 -$ 4 -$ 5 -$ 6 -$ 7 -$ 8 -$ 9 -$

10 -$

TOTALS -$ -$ -$ -$

COUNT 0 Section #3 Cost: -$ GRAND TOTAL w/o Option 1: -$ GRAND TOTAL with Option 1: -$

Cost Proposal Notes:

Facilities Reduction Program - Proposal Estimate Worksheet Summary

Survey Unit Price

File details come from the government source that posted it. Updated .