Attachment 2 -Fenn Schedule of items.pdf
PDF 106 KB Posted
- Attached to
- Fenn Ranger Station roofing replacement
- Solicitation number
- 1240LU26Q0130
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items pricing template for a USDA Forest Service, Region 1 roofing project at the Nez Perce-Clearwater National Forests in Idaho County, Idaho. The contract involves roof replacement and related carpentry work at two structures: the Fenn Bunkhouse and Cook House, with an optional gutter work item for the Cook House.
The Fenn Bunkhouse base section includes five line items: mobilization (lump sum), selective demolition (lump sum), roof replacement (lump sum), rough carpentry (3.15 squares), and galvanized gutters and down spouts (lump sum). The Cook House base section contains four line items: mobilization (lump sum), selective demolition (lump sum), roof replacement (lump sum), and rough carpentry (3.45 squares). An optional item (B-3) allows for galvanized gutters and down spouts at the Cook House (1 lump sum). Bidders must quote all items to the nearest cent, and the contractor is responsible for confirming actual quantities for construction purposes. The estimated square foot areas are provided for bidding reference only. Critical constraint: no payment is guaranteed for rough carpentry work (item 074113-2); payment requires written approval from the Contracting Officer prior to work performance. The estimated quantities assume 15% of total sheathing and sub-roof repairs may be necessary. Bidders must provide their name, phone number, email, and UEI with their quotation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
USDA FOREST SERVICE, R-1
FENN ROOFING
Nez Perce-Clearwater National Forests Idaho County, Idaho
Schedule of Items: Fenn Bunkhouse - Base
Pay Item
Item Description
MM* Estimated Quantity
Pay Unit
Unit Price
Amount
001900
MOBILIZATION
LSQ
LS
24119
SELECTIVE DEMOLITION
074113-1
ROOF REPLACEMENT FENN
BUNKHOUSE
074113-2
ROUGH CARPENTRY FENN
BUNKHOUSE
AQ
3.15
SQ
074113-3
GALVANIZED GUTTERS AND
DOWN SPOUTS.
AMOUNT QUOTED (All Items) $________
B - 2 - Schedule of Items: Cook house – Base
Pay Item
Item Description
MM* Estimated Quantity
Pay Unit
Unit Price
Amount
001900
MOBILIZATION
24119
SELECTIVE DEMOLITION
074113-1
ROOF REPLACEMENT FENN
COOK HOUSE
074113-2
ROUGH CARPENTRY FENN
COOKHOUSE
AQ
3.45
SQ
B - 3- Schedule of Items: Cook house Gutters – Optional Item
074113-3 GALVANIZED GUTTERS AND
DOWN SPOUTS.
TOTAL AMOUNT QUOTED (All Items) $________
*MM = Method of Measurement LSQ - Lump Sum Quantity AQ – Actual Quantity SQ - Square
Quote on all items. Only quotes to the nearest cent will be accepted. Estimated square foot areas are provided for bidding purposes, it is the Contractor’s responsibility to confirm actual qualities for construction purposes.
No payment will be guaranteed for work item number 074113-2 under this section. Payment for this work must be approved by the CO in writing prior to any work performed. These quantities are using an assumed value of 15% of the total sheathing/sub-roof maybe necessary to be repaired/replaced.
Price Quotation Furnished By:
Name: _____________________________________Phone: _____________________________
E-mail: ________________________________________
UEI: ___________________________________
File details come from the government source that posted it. Updated .