BILLINGS RETARDANT AIR TANKER BASE FOG SEAL PLAN3
GENERAL NOTES:
1. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN FOR
GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL PLAN
SHALL ADDRESS THIS REQUIREMENT.
2. CRACK SEAL ESTIMATED QUANTITIES ARE FOR INFORMATIONAL PURPOSES ONLY.
ACTUAL QUANTITIES MAY VARY. CONTRACTOR TO SWEEP ASPHALT AND EVALUATE
CRACKS. ALL CRACK SEAL LOCATIONS AND QUANTITIES ARE TO BE APPROVED BY THE
CONTRACTING OFFICER REPRESENTATIVE PRIOR TO BEGINNING CRACK SEAL WORK.
SEE SPECIFICATION MT-02878(1) CRACK SEAL.
3. CRACK SEAL JOINTS BETWEEN ASPHALT AND CONCRETE PAVEMENTS.
4. CONTRACTOR IS TO REMOVE ALL PINDOWN PARKING CURBS, PRIOR TO CLEANING
EXISTING PAVEMENT.
5. CONTRACTOR TO REPLACE ALL PINDOWN PARKING CURBS AT THEIR PRIOR LOCATIONS
AFTER APPLICATION OF FOG SEAL.
BILLINGS RETARDANT AIR TANKER BASE STRIPING PLAN4
1. STRIPING IS SCHEMATICALLY LAID OUT IN THIS DRAWING, AND DOES NOT CURRENTLY
EXIST AT THE SITE. IT IS THE CONTRACTOR'S RESPONSIBILITY TO LAY OUT AND
PERFORM STRIPING ACCORDING TO THIS SCHEMATIC. USE STRIPING DETAIL SHEET 11
AS A REFERENCE FOR STRIPING DIMENSIONS. ALL MARKINGS SHALL MEET ADA
STANDARDS.
2. STRIPE PLAN ESTIMATED QUANTITIES ARE FOR INFORMATIONAL PURPOSES ONLY.
ACTUAL QUANTITIES MAY VARY. SEE SPECIFICATION MT-02765(1) PAVEMENT MARKING
FOR PAY QUANTITY UNIT OF MEASUREMENT.
3. DO NOT APPLY PAVEMENT MARKING PAINT UNTIL LAYOUT, COLORS, AND PLACEMENT
HAVE BEEN VERIFIED AND APPROVED BY THE CONTRACTING OFFICER REPRESENTATIVE.
4. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN FOR
GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL PLAN SHALL
ADDRESS THIS REQUIREMENT.
1. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN FOR
GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL PLAN
SHALL ADDRESS THIS REQUIREMENT.
2. CRACK SEAL ESTIMATED QUANTITIES ARE FOR INFORMATIONAL PURPOSES ONLY.
ACTUAL QUANTITIES MAY VARY. CONTRACTOR TO SWEEP ASPHALT AND EVALUATE
CRACKS. ALL CRACK SEAL LOCATIONS AND QUANTITIES ARE TO BE APPROVED BY THE
CONTRACTING OFFICER REPRESENTATIVE PRIOR TO BEGINNING CRACK SEAL WORK.
SEE SPECIFICATION MT-02878(1) CRACK SEAL.
3. CRACK SEAL JOINTS BETWEEN ASPHALT AND CONCRETE PAVEMENTS.
4. CONTRACTOR IS TO REMOVE ALL PINDOWN PARKING CURBS, PRIOR TO CLEANING
EXISTING PAVEMENT.
5. CONTRACTOR TO REPLACE ALL PINDOWN PARKING CURBS AT THEIR PRIOR LOCATIONS
AFTER APPLICATION OF FOG SEAL.
6. CONTRACTOR IS RESPONSIBLE FOR REESTABLISHING STRIPING TO MATCH EXISTING
STRIPING.
POMPEYS PILLAR NATIONAL MONUMENT FOG SEAL PLAN5
POMPEYS PILLAR NATIONAL MONUMENT STRIPING PLAN6
1. STRIPING SHOWN IN THIS DRAWING IS FOR REFERENCE ONLY. CONTRACTOR IS
RESPONSIBLE FOR REESTABLISHING STRIPING TO MATCH EXISTING STRIPING.
CONTRACTOR MUST ESTABLISH THE LOCATION OF EACH PARKING STRIPE PRIOR TO
BEGINNING THE FOG SEAL. THE CONTRACTOR SHALL NOTE THE BEGINNING AND TAIL
END OF ALL EXISTING PARKING LANES. THE CONTRACTOR MAY USE FLEXIBLE,
TEMPORARY RAISED PAVEMENT MARKINGS.
2. STRIPE PLAN ESTIMATED QUANTITIES ARE FOR INFORMATIONAL PURPOSES ONLY.
ACTUAL QUANTITIES MAY VARY. SEE SPECIFICATION MT-02765(1) PAVEMENT
MARKING FOR PAY QUANTITY UNIT OF MEASUREMENT.
3. DO NOT APPLY PAVEMENT MARKING PAINT UNTIL LAYOUT, COLORS, AND PLACEMENT
HAVE BEEN VERIFIED AND APPROVED BY THE CONTRACTING OFFICER
REPRESENTATIVE.
4. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN
FOR GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL
PLAN SHALL ADDRESS THIS REQUIREMENT.
EASTERN MONTANA-DAKOTAS DISTRICT OFFICE FOG SEAL PLAN7
1. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN FOR
GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL PLAN
SHALL ADDRESS THIS REQUIREMENT.
2. CRACK SEAL ESTIMATED QUANTITIES ARE FOR INFORMATIONAL PURPOSES ONLY.
ACTUAL QUANTITIES MAY VARY. CONTRACTOR TO SWEEP ASPHALT AND EVALUATE
CRACKS. ALL CRACK SEAL LOCATIONS AND QUANTITIES ARE TO BE APPROVED BY THE
CONTRACTING OFFICER REPRESENTATIVE PRIOR TO BEGINNING CRACK SEAL WORK.
SEE SPECIFICATION MT-02878(1) CRACK SEAL.
3. CRACK SEAL JOINTS BETWEEN ASPHALT AND CONCRETE PAVEMENTS.
4. CONTRACTOR IS TO REMOVE ALL PINDOWN PARKING CURBS, PRIOR TO CLEANING
EXISTING PAVEMENT.
5. CONTRACTOR TO REPLACE ALL PINDOWN PARKING CURBS AT THEIR PRIOR LOCATIONS
AFTER APPLICATION OF FOG SEAL.
6. CONTRACTOR IS RESPONSIBLE FOR REESTABLISHING STRIPING TO MATCH EXISTING
STRIPING.
EASTERN MONTANA-DAKOTAS DISTRICT OFFICE FOG SEAL PLAN8
1. STRIPING SHOWN IN THIS DRAWING IS FOR REFERENCE ONLY. CONTRACTOR IS
RESPONSIBLE FOR REESTABLISHING STRIPING TO MATCH EXISTING STRIPING.
CONTRACTOR MUST ESTABLISH THE LOCATION OF EACH PARKING STRIPE PRIOR
TO BEGINNING THE FOG SEAL. THE CONTRACTOR SHALL NOTE THE BEGINNING
AND TAIL END OF ALL EXISTING PARKING LANES. THE CONTRACTOR MAY USE
FLEXIBLE, TEMPORARY RAISED PAVEMENT MARKINGS.
2. STRIPE PLAN ESTIMATED QUANTITIES ARE FOR INFORMATIONAL PURPOSES ONLY.
ACTUAL QUANTITIES MAY VARY. SEE SPECIFICATION MT-02765(1) PAVEMENT
MARKING FOR PAY QUANTITY UNIT OF MEASUREMENT.
3. DO NOT APPLY PAVEMENT MARKING PAINT UNTIL LAYOUT, COLORS, AND
PLACEMENT HAVE BEEN VERIFIED AND APPROVED BY THE CONTRACTING OFFICER
REPRESENTATIVE.
4. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN
FOR GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL
PLAN SHALL ADDRESS THIS REQUIREMENT.
1. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN
TO GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL
PLAN SHALL ADDRESS THIS REQUIREMENT.
2. CONTRACTOR IS RESPONSIBLE FOR ALL PUBLIC AND PRIVATE UTILITY LOCATES.
COORDINATE WITH MONTANA 811 AND ANY OTHER NECESSARY ENTITIES.
UTILITY PULL-BOX ENCLOSURE PLAN
NO SCALE9
1A
2% MAX2% MAX
1. CONTRACTOR TO FIELD VERIFY ELEVATIONS AND SLOPES OF THE EXISTING ASPHALT.
2. CONTRACTOR IS RESPONSIBLE FOR ALL PUBLIC AND PRIVATE UTILITY LOCATES. COORDINATE WITH
MONTANA 811 AND ANY OTHER NECESSARY ENTITIES.
3. CONTRACTOR TO INSTALL THE NEW UTILITY PULL-BOX ENCLOSURE AT AN ELEVATION THAT PREVENTS
WATER FROM POOLING ON IT AND ENTERING IT, BUT CREATES THE MOST MINIMUM GRADE OF ASPHALT
POSSIBLE AROUND IT.
4. CONTRACTOR TO COMPLETE INSTALLATION OF THE NEW UTILITY PULL-BOX ENCLOSURE ONLY AFTER
APPROVAL OF THE CONTRACTING OFFICER REPRESENTATIVE.
5. 3 4" MINUS AGGREGATE ROAD BASE COURSE SHALL BE COMPACTED TO 95% DENSITY PER ASTM D-698 OR
AASHTO T-99.
6. CONSTRUCTION SHALL BE STAGED TO ALLOW THE PARKING LOT TO REMAIN OPEN TO GOVERNMENT AND PUBLIC USE DURING CONSTRUCTION. TRAFFIC CONTROL PLAN SHALL ADDRESS THIS REQUIREMENT.
NEW UTILITY PULL-BOX ENCLOSURE TYPICAL CROSS SECTION
NO SCALE10
1A
STRIPING DETAILS11
1. CONTRACTOR MUST ESTABLISH THE LOCATION OF EACH PARKING STRIPE PRIOR TO
BEGINNING THE FOG SEAL. THE CONTRACTOR SHALL NOTE THE BEGINNING AND
TAIL END OF ALL EXISTING PARKING LANES. THE CONTRACTOR MAY USE FLEXIBLE,
TEMPORARY RAISED PAVEMENT MARKINGS.