This document is the Schedule of Items for a construction contract solicitation to replace the roof at the Descanso Fire Station Prevention Office in the Cleveland National Forest. The solicitation includes a Base Bid with items for mobilization, demolition and hazardous materials removal, and new asphalt shingle roofing installation. Two optional add-on items are included - Option 1 for replacement of roof decking material, and Option 2 for replacement of wood support components. Quantities are estimated and the contractor is required to field verify. The total contract value, including the base bid and both options, is estimated to be between $25,000 and $100,000. This is a Total Small Business Set-Aside solicitation with a pre-proposal site visit scheduled for April 16, 2024. All requests for information (RFIs) must be submitted by April 18, 2024. Award will be made by the USDA Forest Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1SCHEDULE OF ITEMS (BASE CONSTRUCTION)
Item
Construction Items
Qty
UOI
Unit Price
Total Price
01 71 13
Mobilization for All Work Items
1
Lump Sum
$______________
$_______________
02 41 00
Demolition

A - Demolition and Hazmat Removal and Disposal

1
Lump Sum
$______________
$_______________
07 31 13
Asphalt Shingles Roofing

A - Remove Existing and Install all New Shingles, Underlayment, Flashing, Drip Edge, Fascia, Soffit, Vents, Sleeves and Collars, Moisture Protection Material, Incidentals and Appurtenances.

1
Lump Sum
$______________
$_______________
BASE TOTAL:
$_______________

B.1 SCHEDULE OF ITEMS - (OPTION 1)

Item
Construction Items
Qty
UOI
Unit Price
Total Price
06 10 00
Rough Carpentry

A - Remove Existing and Replace Roof Substrate Decking Material

SF
400
$___________
$___________
OPTION 1 TOTAL:
$___________

B.1 SCHEDULE OF ITEMS - (OPTION 2)

Item
Construction Items
Qty
UOI
Unit Price
Total Price
06 10 00
Rough Carpentry

A - Remove Existing and Replace Wood Support Components

Lump Sum
1
$___________
$___________
OPTION 2 TOTAL:
$___________
BASE + OPTION 1 + OPTION 2 TOTAL:
$___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Company Name:
POC & Title:
Email:
Phone Number:
UEI Number:
Tax ID:

Solicitation No: 127EAW24R0014 Project Name: Descanso Fire Station Prevention Office Roof Replacement