Attachment 2.pdf

PDF 175 KB Posted

Attached to
Pump & Treat Services of Contaminated Groundwater
Solicitation number
300000276688711
Issued by
Missouri

About this file

This is a groundwater extraction system monitoring form for the Valley Park TCE (trichloroethylene) Site, used by the responsible environmental agency or contractor to document operational status and performance metrics during routine inspections and maintenance visits. The form captures physical component readings, system status upon arrival and departure, and operational parameters for the extraction well, antiscalant metering system, sediment bag filters, and air stripper blower. Key monitored components include the E+H flow meter (178-182 gpm typical operating range), extraction well water level (35-50 feet below top of casing), pump pressure (8-15 psi), antiscalant metering rate (~0.03 gal/day), bag filter pressure differentials across multiple stages (3-9 psi pre-filter to 2.5-7 psi post-filter), and air stripper pressure (35-42 inches of water). The form includes both daily inspection checkpoints and monthly maintenance tasks such as antiscalant level verification, air stripper tray inspection, drain procedures, and monitoring well gauging for wells MW-55 and MW-56.

The form integrates data from the SiteLink Controls remote monitoring system (https://sitelink.newterra.com/), which tracks flow meter readings, water level control setpoints, dosing pump settings, and equipment runtimes for the blower and extraction well pump. Standard operational setpoints include water level control at 58 feet below top of casing (LC-10), pump activation at 50 feet, and automatic dosing pump settings at 200 gpm. The monitoring protocol requires documentation of system verification checkpoints, such as confirming that ASP-10 blower and VFD pump status lights are properly illuminated and switch positions are set to specified configurations (AUTO, OFF, OFF, OFF, AUTO). This systematic inspection and data collection process supports ongoing groundwater remediation operations and ensures the extraction system maintains optimal performance within established operational parameters.

View the file

Other files

File Type Posted
STATE 0000000524SL-04.docx DOCX document
REVISED Attachment 1.pdf PDF
Attachment 1.pdf PDF
STATE 0000000524SL-01.docx DOCX document
STATE 0000000524SL.docx DOCX document
STATE 0000000524SL-03.docx DOCX document
STATE 0000000524SL-02.docx DOCX document
Site Tour - Sign in Sheet - Pump & Treat.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Inspected: ___________________ System Status At Arrival: [ ] running [ ] stopped [ ] alarmed

Time Inspected: ___________________ [ ] running [ ] stopped [ ] alarmed

Inspected By: ______________________

Check Physical Components

Component Reading Units (typical operating range)

Extraction Well and Flow Meter

E+H Flow Meter gpm (178 to 182 gpm)

E+H Flow Meter Kgl

E+H Flow Meter gal (use the plus sign only)

Extraction Well Water Level ft below TOC (35 to 50 ft.)

Extraction Well Pressure Gauge psi (8 to 15 psi)

Antiscalant and Metering Pump

Metering Rate gal/day (~0.03 gal/day)

Pump Pressure bar (~3.5 bar)

50:50 Antiscalant Volume gal

Undiluted Antiscalant Onhand drums

Sediment Bag Filters

Pre Bag Filter Pressure psi (5 to 9 psi)

6591A-pre psi (3 to 9 psi)

6591A-post psi (2.5 to 7 psi)

6591A-pre psi (3 to 9 psi)

6591B-post psi (2.5 to 7 psi)

Post Bag Filter Pressure psi (5 to 7 psi)

Capsu-Photohelic Reading (black) (DP-10) in H2O

Capsu-Photohelic Gauge Setpoint (red) (DP-10) ~ 300 in H2O Note: 300 in H2O = 11 psi

Air Stripper Blower

Air Stripper Pressure in H2O (35 to 42 in H2O)

Air Stripper Input Flow cfm x 10 (350 - 450 cfm x10)

TECO-Westinghouse Variable Frequency Drive (VFD)

VFD Freq. Cmd Hz (37 to 42)

VALLEY PARK TCE SITE

GROUNDWATER EXTRACTION SYSTEM MONITORING

System Status When Leaving:

Form Revised 3/13/2020

Control Panel and PLC

Site Walk-Around, Well Gauging, and Other Items

Check Each Visit Check Monthly (first week of month)

[ ] Site walk-around [ ] Check antiscalant level

[ ] Check outfall in storm grate [ ] Check air stripper trays

[ ] Drain air stripper stack [ ] Tighten Fernco fittings on air stripper trays

[ ] Gauge monitoring wells

MW-55

MW-56

SiteLink Controls (https://sitelink.newterra.com/)

Flow Meter Readings

FM-10 Flowrate gpm (178 to 182 gpm)

FM-10 Total Volume gal.

Water Level (LC-10) Control

Water over LC-10 ft.

Water Level ft. below TOC

LC-10 Position ft. below TOC (58 ft)

Low Water Well (Low SP) ft. below TOC (56 ft)

Pump On Level (ON SP) ft. below TOC (50 ft)

Dosing Pump (DP-CH) Setpoints

Manual SP % (50 %)

Automatic SP gpm (200 gpm)

Runtimes

VB-SVE & FAN HRS 0 hrs

ASP-10 Blower HRS hrs

P-10 WELL HRS hrs

DP-VLS PUMP HRS 0 hrs

Notes

Depth to Water

(ft btoc)

Total Depth

(ft btoc)

Verify: Are ASP-10 BLOWER-ON and VFD P-10 ON lights illuminated red and all others are off?

[ ] yes [ ] no, explain:

Verify: Are switch positions: AUTO, OFF, OFF, OFF, AUTO [ ] yes [ ] no, explain: