Attachment 2.pdf

PDF 175 KB Posted

Attached to
Pump & Treat Services of Contaminated Groundwater
Solicitation number
300000275288343
Issued by
Missouri

About this file

This is a system monitoring form for the Valley Park TCE Site Groundwater Extraction System, documenting inspection procedures and operational parameters for a contaminated groundwater remediation facility. The form captures real-time operational data for the extraction well, antiscalant metering system, sediment bag filters, and air stripper blower components. Inspections are conducted to verify that system components operate within established ranges, including flow rates (178-182 gpm), extraction well water levels (35-50 feet below top of casing), pressure gauges (8-15 psi), and air stripper pressure (35-42 inches of water). The form includes checkpoints for routine monthly maintenance tasks such as antiscalant level verification, air stripper tray inspection and drainage, Fernco fitting adjustments, and monitoring well gauging at designated locations (MW-55 and MW-56). System status is documented both upon arrival and departure, with operators required to record all readings, verify control panel illumination patterns, and confirm proper switch positions on automated equipment.

The monitoring form establishes operational setpoints and control parameters managed through SiteLink Controls, including water level controls, dosing pump setpoints at manual (50 percent) and automatic (200 gpm) modes, and variable frequency drive settings (37-42 Hz). Runtime hours are tracked for the SVE and fan systems, ASP-10 blower, P-10 well pump, and DP-VLS pump to monitor equipment utilization and maintenance schedules. The form includes verification checkboxes requiring operators to confirm that all indicator lights and switch positions match required configurations, with notation space for any deviations or issues encountered. This standardized inspection document was revised on March 13, 2020, and serves as both an operational record and compliance documentation for ongoing groundwater remediation activities at the site.

View the file

Other files

File Type Posted
Site Tour - Sign in Sheet - Pump & Treat.pdf PDF
STATE 0000000524SL-03.docx DOCX document
STATE 0000000524SL.docx DOCX document
STATE 0000000524SL-01.docx DOCX document
Attachment 1.pdf PDF
REVISED Attachment 1.pdf PDF
STATE 0000000524SL-02.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Inspected: ___________________ System Status At Arrival: [ ] running [ ] stopped [ ] alarmed

Time Inspected: ___________________ [ ] running [ ] stopped [ ] alarmed

Inspected By: ______________________

Check Physical Components

Component Reading Units (typical operating range)

Extraction Well and Flow Meter

E+H Flow Meter gpm (178 to 182 gpm)

E+H Flow Meter Kgl

E+H Flow Meter gal (use the plus sign only)

Extraction Well Water Level ft below TOC (35 to 50 ft.)

Extraction Well Pressure Gauge psi (8 to 15 psi)

Antiscalant and Metering Pump

Metering Rate gal/day (~0.03 gal/day)

Pump Pressure bar (~3.5 bar)

50:50 Antiscalant Volume gal

Undiluted Antiscalant Onhand drums

Sediment Bag Filters

Pre Bag Filter Pressure psi (5 to 9 psi)

6591A-pre psi (3 to 9 psi)

6591A-post psi (2.5 to 7 psi)

6591A-pre psi (3 to 9 psi)

6591B-post psi (2.5 to 7 psi)

Post Bag Filter Pressure psi (5 to 7 psi)

Capsu-Photohelic Reading (black) (DP-10) in H2O

Capsu-Photohelic Gauge Setpoint (red) (DP-10) ~ 300 in H2O Note: 300 in H2O = 11 psi

Air Stripper Blower

Air Stripper Pressure in H2O (35 to 42 in H2O)

Air Stripper Input Flow cfm x 10 (350 - 450 cfm x10)

TECO-Westinghouse Variable Frequency Drive (VFD)

VFD Freq. Cmd Hz (37 to 42)

VALLEY PARK TCE SITE

GROUNDWATER EXTRACTION SYSTEM MONITORING

System Status When Leaving:

Form Revised 3/13/2020

Control Panel and PLC

Site Walk-Around, Well Gauging, and Other Items

Check Each Visit Check Monthly (first week of month)

[ ] Site walk-around [ ] Check antiscalant level

[ ] Check outfall in storm grate [ ] Check air stripper trays

[ ] Drain air stripper stack [ ] Tighten Fernco fittings on air stripper trays

[ ] Gauge monitoring wells

MW-55

MW-56

SiteLink Controls (https://sitelink.newterra.com/)

Flow Meter Readings

FM-10 Flowrate gpm (178 to 182 gpm)

FM-10 Total Volume gal.

Water Level (LC-10) Control

Water over LC-10 ft.

Water Level ft. below TOC

LC-10 Position ft. below TOC (58 ft)

Low Water Well (Low SP) ft. below TOC (56 ft)

Pump On Level (ON SP) ft. below TOC (50 ft)

Dosing Pump (DP-CH) Setpoints

Manual SP % (50 %)

Automatic SP gpm (200 gpm)

Runtimes

VB-SVE & FAN HRS 0 hrs

ASP-10 Blower HRS hrs

P-10 WELL HRS hrs

DP-VLS PUMP HRS 0 hrs

Notes

Depth to Water

(ft btoc)

Total Depth

(ft btoc)

Verify: Are ASP-10 BLOWER-ON and VFD P-10 ON lights illuminated red and all others are off?

[ ] yes [ ] no, explain:

Verify: Are switch positions: AUTO, OFF, OFF, OFF, AUTO [ ] yes [ ] no, explain:

Form Revised 3/13/2020