Attachment 2-CUMMINGS Drydock PWS 2026_.pdf

PDF 484 KB Posted

Attached to
USACE Survey Vessel RANDY S. CUMMINGS Dry Dock Services
Solicitation number
W912P726QA008
Issued by

About this file

This is a Performance Work Statement for dry dock services of the USACE Survey Vessel RANDY S. CUMMINGS scheduled for 2026, not to exceed 120 days. The contract is firm-fixed-price and is a non-personnel services contract with the Government providing operation of vessel machinery, while the contractor furnishes all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other services necessary for completion.

Key work objectives include pre-dry-docking sea trials, docking and berthage activities with shore power provision (220V, 100Amp), dry docking and maintenance services, hull cleaning and painting with Intersleek anti-fouling coating system, renewal of zinc anodes per Military Specification Mil-A-18001H, inspection and replacement of through-hull sea water valves, shaft and rudder inspections, propeller removal and inspection, and non-destructive sonic survey of hull plating (minimum 200 ultrasonic tests). The scope encompasses main diesel engine and generator tune-ups, Twin Disk transmission maintenance, steering system overhaul with added redundancy, removal of deck-mounted crane and hydraulic capstans, main deck blasting and painting, installation of new cargo davit (1000 lbs minimum capacity), replacement of cabin locks, bow boarding redesign, installation of forward-looking sonar system, incline experiment and ballast installation (up to 15,000 pounds in aft steering gear compartment), new life raft installation, life ring relocation, MOB ladder installation, navigation lighting installation, and various electrical system upgrades including new main switch panel, isolation transformer replacement, and 24-volt DC system isolation. The contractor must provide certified welders, develop a Quality Control Program within 30 days of award, maintain continuous workforce availability, supply an initial list of E-Verify verified employees within three business days, and comply with security requirements including key control and physical security safeguards. All work must comply with Aluminum Structures Painting Counsel Specifications SSPC-SP-10 and applicable U.S. Coast Guard and ABS standards.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

USACE Survey Vessel RANDY S. CUMMINGS

Dry Dock Services

Part 1 General Information

1. General Information This is a non-personnel services contract to provide RANDY S. CUMMINGS Dry Dock Services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction

The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform RANDY S. CUMMINGS Dry Dock Services as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.2 Background

Dry Dock routine and planned maintenance, repair, and inspection services for the USACE Survey Vessel RANDY S. CUMMINGS.

Built in 1977.

Vessel Particulars:

Length Overall: 58”4” Breadth: 16’9”” Hull Depth: 5’ Displacement Hoisting condition 63,900 LBS (boat, full fuel and outfit, no crew or cargo)

Machinery:

Main Engines (2) Cummins X15-M 575 CON rated @1800 RPM, 575 HP each) Reduction Gears: (2) Twin Disc Marine Transmission Model #MGX5136A, 2.to 1.0 Ratio Steering: Wanger N250-1000.

Engine Controls: Quick Shift EC300 by Twin Disc Generator: Cummins ONAN Marine Generator Model # MDKDR-2027435 Propellers: (2) Columbian “Hydroflite” 3-Blade, 38” Diameter x 32” Pitch Shaft Seals: Tide Marine SureSeal dripless Windows: All windows are fixed anodized aluminum frames, Type K-15-f. Pilothouse front windows have 3/8” thick tempered glass and all other windows are fitted with ¼” thick tempered glass.

Doors: Kearfott Type KS-20013 and Kearfott Type KS-30001 Engine Room Ventilation: Forced Air and Natural Venting Electronics: Raymarine Axiom Plotter/RADAR, Auto Pilot Simrad, Radio’s Matrix GX2000 / ICON VHF Marine IC-M506, Loud Hailer Stand Horizon VLN-3000 Fuel Type: Diesel Fuel Capacity: 100% @ 960GAL, 95% (usable) @ 912 GAL

1.3 Objectives

• Pre-Dry-Docking Sea Trials

• Docking & Berthage Lay Activities

• Dry Docking & Services

• Cleaning, Hull Painting, Renew Zinc Anodes, Surface Treatments

• Inspections

• Replacement/Upgrade Installations

• Removal of crane and associated systems

• Install Ballast as per U.S. ARMY Marine Design Center specifications

1.4 Scope

Services include dry docking, scheduled maintenance, scheduled cleaning, planned repairs, vessel modificatins, scheduled inspections, and discovered repair needs.

1.5 Period of Performance Not to exceed 120 Days

1.6 General Information

1.6.1 Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s Quality Control Program (QCP) is the means by which he assures himself that his work complies with the requirement of the contract. The contractor’s QCP is to be delivered within 30 days after contract award. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.

1.6.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.6.3 Recognized Holidays: The contractor is not required to perform services on the following holidays.

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day

1.6.4 Hours of Operation: The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.6.5 Place of Performance: The work to be performed under this contract will be performed at the contractor’s facilities.

1.6.6 Type of Contract: The government will award a firm-fixed-price contract.

1.6.7 Security Requirements (Specific contractor security clearance levels are not required)

1.6.7.1 Pre-screen candidates using E-Verify Program: The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements.

The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.

1.6.7.2 Physical Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

1.6.7.3 Key Control: The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons.

NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.

1.6.7.3.1 Lost Keys: In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor.

1.6.7.3.2 Key Use: The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.

http://www.uscis.gov/e-verify

1.6.7.4 Lock Combinations (Not Applicable)

1.6.8 Special Qualifications

Contractor will provide certified welders as needed and ensure during the process of welding, no stray current negatively affects any of Randy S. Cummings electric or electronic equipment, initial electrical tag out process will be verified by Government Inspector.

1.6.9 Post Award Conference/Periodic Progress Meetings

The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced.

Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.6.10 Contracting Officer Representative (COR)

The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.11 Key Personnel

The follow personnel are considered key personnel by the government: Project Managers, Job Site Supervisors, Lead Journeymen and Office Personnel. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available for normal working hours, Monday through Friday. Qualifications for all key personnel are inherent to the job titles specified.

1.6.12 Identification of Contractor Employees

All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.6.13 Contractor Travel (Not Applicable)

1.6.14 Other Direct Costs (Not Applicable)

1.6.15 Data Rights (Not Applicable)

1.6.16 Organizational Conflict of Interest

Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.6.17 Phase In /Phase Out Period (Not Applicable)

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS:

2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government.

The term used in this contract refers to the prime.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7. GOVERNMENT INSPECTOR. USACE employee and subject matter expert who observes the contracted work being performed as part of the Quality Assurance Surveillance Plan.

2.1.8. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.9. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.10. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.11. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.12. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.13. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.14. WORK WEEK. Monday through Friday, unless specified otherwise.

2.2. ACRONYMS:

ACOR Alternate Contracting Officer's Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCE Contracting Center of Excellence CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative

COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation HIPAA Health Insurance Portability and Accountability Act of 1996 KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program STBD Starboard TE Technical Exhibit USACE United State Army Corps of Engineers

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1 Services: The Government will provide operation of any vessel machinery plant required during the performance of this contract. At no time during the execution of this specification will the contractor operate the machinery onboard the vessel without direct permission of the Government Inspector. When the Government operates any machinery plant as necessary for the successful completion of this contract, the contractor will be present for the duration.

3.2 Facilities: (Not Applicable)

3.3 Utilities: (Not Applicable)

3.4 Equipment: (Not Applicable)

3.5 Materials: (Not Applicable)

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 GENERAL: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.

4.2 SECRET FACILITY CLEARANCE: (Not Applicable)

4.3 MATERIALS: The Contractor shall furnish all supplies required to perform work under this contract that are not listed under Part 3 of this PWS.

4.4. EQUIPMENT: The Contractor shall furnish all equipment required to perform work under this contract that are not listed under Part 3 of this PWS.

PART 5

SPECIFIC TASKS

5 SPECIFIC TASKS

5.1 BASIC SERVICES (Laydays)

The contractor shall provide dry dock services for USACE Survey Vessel RANDY S. CUMMINGS, referred to as CUMMINGS.

Contractor will provide easy access to all Project Managers, Job Site Supervisors, Lead Journeymen and Office Personnel during the full extent of this contract. Contractor will protect the area affected by work and nearby areas from blasting, painting overspray, transit of goods and equipment, storage or staging associated with work being performed by yard personnel. The cutlass bearings, through hulls, shafts and transducers will also be well covered and protected during sandblasting portion of this specification.

5.1.1 No paint shall be sprayed in enclosed spaces unless an adequate ventilation system is in operation that will positively exchange the air in the space with fresh air at a rate of 5,000 CFM for each spray gun in operation. The ventilation system shall operate during the entire application and shall be continued after spraying is halted until the paint is no longer giving off appreciable vapors. The air in the enclosed painting space shall be safe at all times from fire and explosion hazards as determined by contractor furnished explosion meter manufactures by Mine Safety Appliance Company or competent replacement. Where spraying is being done in enclosed spaces not freely being swept by natural wind currents workman shall at all times where respirators under all circumstances. All painting with enamel or epoxy coatings shall be applied within strict accordance with manufactures instructions or specified by the Government.

5.1.2 Existing paint surfaces damaged in the execution of this contract shall be properly prepared and unless otherwise specified by paint systems manufacture, proper preparation to include two coats of an approved metal primer and two coats of an approved marine finish coat of the same color and/or texture as adjacent surfaces.

5.1.3 Contractor will repair any area or equipment adversely effected by work performed by yard personnel

5.1.4 Contractor shall use marine grade 6061-T6 aluminum for all pipes and marine grade 5086-H32 aluminum for all hull and deck plate repairs.

5.1.5 Contract will provide certified welders as needed and ensure during the process of welding no stray current negatively affects any of CUMMINGS electric or electronic equipment, initial electrical tag out process will be verified by Government Inspector.

5.1.6 All other appurtenances of the vessel which are removed or open shall not be reinstalled without the approval of the Government Inspector, ensuring they meet US Coast Guard requirements or other standards as they apply to the equipment.

5.2. PRE & POST DRY-DOCKING SEA TRIALS

5.2.1Before the initiation of any work on the CUMMINGS, Contractor and Government including the COTR will conduct delivery dock trials. The delivery dock trial will be performed on all equipment and systems that may or may not be affected by the work associated with the shipyard repair. The equipment and systems to be tested will be determined by the Government Inspector. The Contractor agrees to be present for the duration of these delivery dock tests, witness the results.

The Government Inspector and the Contractor shall concur as to the operational status of any piece of equipment or system being tested. The delivery dock trails shall be for a period of approximately four hours.

5.2.2 Prior to the completion date of the contract the Contractor shall conduct completion dock and sea trials to prove the work of the contract. All work or not work items that do not operate as the contract states or were damaged by the contractor will be accessed and repaired at no additional cost to the Government. Completion dock and sea trials shall be for the period of approximately eight hours. Additional time to correct deficiencies may be approved by the COTR. The Government will operate and vessel machinery plant required during the performance of this contract. At no time during the execution of this specification will the contractor operate the machinery onboard the vessel without direct permission of the Government Inspector. When the Government operates any machinery plant as necessary for the successful completion of this contract, the contractor will be present for the duration.

5.3 DOCKING & BERTHAGE (Electricity & Fire Protection)

The contactor shall provide electrical shore power (220V, 100Amp) to the vessel during the entire shipyard contract performance, including pier side awaiting dry dock. Contractor will provide suitable gangway and pier or dock lighting. Government will provide mooring lines and fendering for the duration of the contract. The vessel will be unmanned in regards to personnel remaining overnight.

CUMMINGS will be secured while the vessel is not being worked on. Vessels will not be tied up alongside, outboard or stern of

CUMMINGS.

5.4 DRY DOCKING

Contractor will dry dock CUMMINGS. Dry docking blocks will be arranged to enable the blocks to be moved and relocated to ensure full coverage for pressure washing, renewing zincs, and anti-fouling coating system. CUMMINGS will be operated into and out of the dry dock facilities by a USACE qualified vessel operator. All underwater blocking location and placement will be completed and verified by a diver provided by Contractor prior to lifting of the vessel.

5.5 HULL

5.5.1 PRESSURE WASH UNDERWATER HULL

Contractor will pressure wash to remove all sea growth to expose the existing hull protection coating system for inspection.

Pressure wash system pressure will not exceed 500psi as per the manufactures requirements and all debris and sea growth will be discharge in accordance with all Federal, State and Local laws and requirements. This is designated as a Government inspection point, Government Inspector will inspect all work up to this point before contractual work continues.

5.5.2 SONIC SURVEY UNDERWATER HULL PLATING

A non-destructive hull survey will be performed by a certified metal testing agency approved by the American Bureau of Shipping. The contractor will coordinate with the metal testing agency for this inspection. This survey shall be performed immediately upon dry-docking and hull washing. The Government Inspector shall witness all soundings. This survey will utilize high frequency sound to measure the hull thickness at specific locations on the hull; at a minimum 200 ultrasonic tests will be performed. A micrometer depth gauge shall be used in conjunction with ultrasonic tests to determine the depth readings including location of each test and existing thickness, results shall be furnished the Government Inspector. Final test results shall be submitted to the COTR within five working days of the completion of the testing. Shipyard shall provide labor to move obstructions inside the hull which may interfere with readings and grind the hull surface for readings as needed. This is designated as a government inspection point; Government Inspector will inspect all work up to this point before contractual work continues.

5.5.3 CLEANING UNDERWATER HULL

Contractor will bead blast clean all corrosion and all fouled paint leaving a near-white blast cleaned surface free of any remaining paint throughout the exterior hull plate surface and appendages (excluding propellers, rudders and propeller shafts) from the keel up to the top of the waterline or boot strip. Blasting and cleaning shall be in accordance with Aluminum Structures Painting Counsel Specifications SSPC-SP-10. Propellers, rudder and propeller shafts will be cleaned as needed to remove rust, corrosion and sea growth as necessary to ensure they can be completely inspected. All spent abrasive, oil, grease, foreign matter, etc. will be completely removed prior to the application of the first coat. No oxidation will be evident on the metal surface, prior to application of coating. This is designated as a government inspection point; Government Inspector will inspect all work up to this point before contractual work continues.

5.5.4 RENEW ANTIFOULING PAINT

Contractor will use anti-fouling paint; “Intersleek coating system”. And shall use application guidance from the manufacture of Intersleek. Once the aluminum surface is properly prepared as per the Intersleek coating guidance (provided by the Contractor’s shipyard paint rep) the Contractor will apply a first coat apply a tie coat of Intersleek 700 series (dry average equals of 3-5mils) and topcoat with black Intersleek 700 series (dry average equals 6mils). Draft designation numbers will be prepped, primed and painted with Intersleek coating system (coating will of a contracting color as pre the hull). This is designated as a government inspection point; Government Inspector will inspect all work up to this point before contractual work continues. Final topcoat will be 100% inspected by both the Contractor and Government.

5.5.5 RENEW ZINC ANODES ON HULLS, SEA CHESTS, SHAFTS & STERN

All existing zinc anodes will be removed, prior to blasting and replaced with new zincs after blasting or hull painting is complete, type ZSS Military Specification Mil-A-18001H, Amendment 1 Nov 1972, as directed by COTR. This is designated as a government inspection point; Government Inspector will inspect all work up to this point before contractual work continues.

5.5.6 INSPECT OR REPLACE THROUGH HULL SEA WATER VALVES

Inspect through hulls, and associated piping in preparation of removing all sea water valves and identify valves for inspection

vs. replacement based on condition and cost efficiency. Remove, disassemble, and clean reconditionable sea valves to insure they are free of damage, corrosion, scale and foreign matter. Contractor shall grind in, lap, repack, reset, test and otherwise service or replace all valves as required to meet all applicable U.S. Coast Guard Requirements. Reconditioned valves will be hydrostatically tested to 50 PSI for a period of 10 minutes. This is designated as a government inspection point; Government Inspector will inspect all work up to this point before contractual work continues. Contractor shall verify the condition of the sea, valves, fasteners, and plumbing prior to their biddings.

Valves Main Engine (2) 2 ½" Butterfly Generator (2) ¾" Ball

Air Conditioner (1) ¾" Ball Vent (1) ¾" Ball

5.5.7 INSPECT PORT/STBD SHAFTS STERN/STRUT BEARINGS

Contractor shall measure and record shaft-wear down as directed immediately after shafts are disconnected from the transmission using a dial indicator and furnish to the Government Inspector the wear down recordings and overall condition in writing within two working days after dry-docking the vessel. Strut bearings shall be removed and replaced with new if found out of specs. Government Inspector will inspect all work up to this point before contractual work continues.

5.5.8 INSPECT PORT/STBD RUDDERS & STOCK & STUFFING BOXES

Remove and sand blast Stainless Steel Rudders. Repaint in conjunction with line-item 5.5.4. Contractor shall measure and record shaft wear down as directed using a dial indicator and furnish to the Government Inspector the wear down recordings and overall condition in writing within two working days after dry-docking the vessel. All rudder stocks shall be re-packed, re-installed and inspected in the presence of the Government Inspector.

5.5.9 PROPS

5.5.9.1 Contractor will remove the vessel’s 3 blade propellers, 38” diameter x 32” pitch for inspection. Inspect both propellers and provide reports to customer of “As Found” and “As Release” readings covering at minimum:

• Propeller Pitch Reports

• Propeller Damage Chart

• Propeller NDT Chart

• Propeller NDT Report For the purpose of having the repair shop prepare the detailed bid required above the Contractor shall assume that both propellers will be reconditioned in accordance with ISO R484 Class II tolerances for blade pitch, diameter, blade track, and balancing. Note - The actual cost of reconditioning is NOT included and will be covered by Contract modification once the detailed bid from the propeller repair shop is provided to the Government. All work required under these specifications shall be performed by a machine shop certified for propeller fabrication, rehabilitation and repair by USCG and/or ABS. Contractor shall coordinate all inspections with the COR.

5.5.9.2 For final assembly, Check the propeller hub bore to the shaft taper by applying Prussian blue to the shaft taper, with a slightly heavier fit on the larger end. Do not heat the shaft taper to compensate for poor fit. If the fit is less than 60 percent, hand grind/stone the propeller hub bore to achieve the required fit. Do not machine the shaft taper. When 60 percent fit has been obtained, make a small inscription on the shaft to mark the propeller location.

Use this mark as a reference for final assembly. For final assembly, the propeller bore and shaft taper surfaces shall be clean and free of bluing, lubricants, dirt, foreign particles, or any other substance, which would hinder moving the propeller along the taper. Install the propeller with dry metal to metal contact to obtain the maximum frictional force for torque transmission. With the propeller installed on the taper in the same position as when fitted, install the propeller nut and drive up the propeller until it is advanced forward approximately 1/16'' beyond the inscribed mark.

Lock the nut in place with an appropriate locking device. It is prohibited to use grease oil or other substances on the taper to help drive the propeller. Secure propeller nut(s) without lubrication. Do not use a hammer or driving tool to tighten studs and nuts. Customer to witness ringing of propeller nuts. Upon installation propellers will be polished and top coated with Prop Speed as per the manufacturer’s instructions.

5.5.10 BALANCE/NON-DESTRUCTIVE TEST PORT/STBD SHAFTS/ STERN TUBE BEARINGS &

STRUTS.

5.5.10.1 Non-destructive shaft balance test will be performed by a certified agent approved by the American Bureau of Shipping. (STBD shaft new 2012, PORT shaft repaired 2012). Tests shall be performed immediately upon dry-docking and hull washing. The Contractor shall remove the port and starboard shafts from the vessel and visually inspect the following components, as applicable, for excessive wear and other mechanical defects such as nicks, cracks, and corrosion:

• Shaft surfaces

• Strut and stern tube bearing and bearing journal surfaces

• Strut and stern tube bearing housing surfaces

• All shaft and propeller associated fasteners

• Couplings

• Coupling pins (as applicable)

• Stern tube/shaft sealing systems

• Shaft zincs (as applicable)

Contractor shall reinstall the proper shaft to its original configuration after inspection.

5.5.10.2 The inspection shall include the following measurements:

• Keys and keyways and/or shear pins

• All strut and stern tube bearing and internal diameters at forward, middle, and aft locations

• All bearing journal diameters on the shaft at forward middle, and aft locations

• Runouts for shaft taper, shaft straightness, and coupling end diameters

• With coupling fit to shaft and key in-place or pin in place, measure the coupling face and bore runouts.

The maximum face or bore runout shall be no more than 0.002'' TIR

5.5.10.3 The Contractor shall Perform NDI (Non Destructive Inspection) of all bearings sleeves, shaft tapers, coupling bolts, keyways, and welded repair surfaces, in accordance with SFLC STD Spec 0740, AppendixC.

5.5.10.4 The Contractor shall perform a straightness inspection of the shaft via a lathe mounting. Conduct a dial indicator run-out survey at every 20 inches of the shaft. Plot the run-out readings on an appropriate scale to detect and shaft bending.

5.5.10.5 Shafts shall be top coated where appropriate with Prop Speed as per the manufacturer’s instructions.

5.6 ABOVE WATER LINE HULL BLASTING & LETTERING

5.6.1 Contractor will remove all rubber fending system on hull, inspect fastening system and hull’s mounting surfaces behind removed fendering. This is a government inspection point.

5.6.2 Remove three unused bent pad-eyes from the transom. No gas cutting. Cutting wheel and grinding wheel to a clean snag free finish.

5.6.3 Contractor will bead blast clean all corrosion and all paint leaving a near-white blasted cleaned surface free of any remaining paint throughout the exterior hull plate from boot top to gunnel. Above waterline hull will remain a nude, no paint finish. This is a government inspection point.

5.6.4 All fendering will be re-installed with new fasteners after hull bead blasting, inspections and repairs are complete.

5.6.5 Reapply vessel name RANDY S. CUMMINGS on the stern and forward port bow and starboard bow. Replace vessel’s name in original place with 10-inch black lettering on the stern and port and starboard sides of bow along with 3 ½ inch lettering of the words U.S. Army Corp of Engineers on the stern under the vessels name. In approximately 20” x 120” black block letters the word “SURVEY” will be added to port and starboard hull, just forward of the fendering. All lettering and images should be of high quality self-adhering heavy-duty non-reflective vinyl. This is a government Inspection point.

5.7 MAIN DECK WORK

5.7.1 REMOVAL OF DECK MOUNTED CRANE & DECK MOUNTED HYDRAULIC CAPSTANS

5.7.1.1 Remove crane and all associated hydraulic lines and hydraulic tank located on the port bulkhead in the engine room.

5.7.1.2 Remove port and starboard capstans and all associated hydraulic lines. Patch weld closed any through deck holes left from capstans removal and vacuum test welds for watertightness.

5.7.1.3 Remove all associate crane and capstan hydraulic lines and controls from the aft helm station. Patch open area left by the removal of crane / capstan control leavers. Clean up any spilled hydraulic fluid. This will be a government inspection point. See 5.27 for re-ballasting requirements.

5.7.2 MAIN DECK: AFT CONTROL STATION

5.7.2.1 Post removal of hydraulics and patchwork from line 5.7.1.1 - 5.7.1.3, repair fasteners, replace any missing fasteners on after access panel on aft helm station and install new panel gaskets.

5.7.2.2 Remove Oxygen and Acetylene Cylinder retaining rings IVO the aft steering station. Feather finish smooth the bulkhead where welds existed. No gas cutting. Cutting wheel and grinding wheel to a clean snag free finish. This will be the relocation point of a life ring from line 5.20.

5.7.2.3 Repair / Replace steering jog lever on control station. This is designated as a government inspection point.

5.7.3 MAIN DECK: BLASTING AND PAINTING

5.7.3.1 Contractor will remove fiberglass deck plates and bead blast main deck, from bow to stern (including deck gear boxes, cleats, bollards, tie down, stanchions, hand railings and engine room vents), leaving a near white blast cleaned surface free of any remaining paint. The mechanics of the Yellow Fuel Vents and Fill Pipe should be protected from bead blasting and dust intrusion and repainted yellow. Blasting and cleaning shall be in accordance with Aluminum Structures Painting Counsel Specifications SSPC-SP-10. This is designated as a government inspection point. Once after deck blasting and inspection is completed, the fiberglass nonslip deck plates will be reinstalled with new fasteners and replacing where some fasteners are missing/needed. Additional Fiberglass platting will be required in areas where deck gear has been removed in scope 5.7.1.1 -5.7.1.4.

5.7.3.2 Once main deck blasting is complete contractor will apply fresh non-skid to engine room hatches and engine room and lazaret skuttles and any other horizontal walking surfaces from bow to stern that are not covered by a non-skid fiberglass deck plate. Situate waterways around welded seams and deck hatches and stanchions, following the original paint / nonskid scheme. This is a designated as a government inspection point

5.7.4 MAIN DECK: HATCHES, SCUTTLES & DECK LOCKERS

5.7.4.1 Inspect all scuttles, anchor locker, engine room egress scuttles and swim deck inspection scuttles for proper operation and gasket sealing.

5.7.4.2 Repair hinges and dogs on main deck engine room hatches and replace gaskets, check for water leakage.

5.7.4.3 Install gas assist struts of appropriate size and dimensions to aid in one-man razing and lowering of main deck engine room hatches.

5.7.4.4 Install a safety locking device for one man operation of both main deck engine room hatches that keep the hatches secured in the open position.

5.7.4.5 Repair port and starboard sprung gear locker top hatches.

5.7.5 MAIN DECK: NEW CARGO RAIDIAL DAVIT

Install new cargo davit (or Jib Crane) at customers identified location IVO port rail boarding area to aid in the loading of gear / equipment. Davit should be mechanical (non-manual) in nature, stowable to keep a minimal footprint and have a SWL greater than or equal to1000lbs. Davit should have a wire and hook and sheaves to match. Wire may be synthetic in nature or stainless steel and meet the min. SWL rates to the davit. Davit must rotate 360 degrees, limited only to the location of the pilot house. Davit should meet to at least the center point of the aft deck (point to be identified by the government) at the maximum 1000lb load. Davit should have at least one folding boom to meet the min footprint in the storage position.

Hydraulic or Electric or Hydraulic Over Electric proposal must be self-contained and run off power from the vessels generator (AC) or inverter (DC) off vessels generator.

5.7.6 MAIN DECK: CABIN LOCKS

Replace all locks on 3 cabin doors, key alike and supply government with keys.

5.7.7 MAIN DECK: BOW BOARDING RE-DESIGN

Redesign bow area, deck and railing, to facilitate the boarding / disembarkation of personnel at a pierhead (single person capacity). Design must be robust enough to facilitate the vessel being clutched in on both engines on a flat bulkhead or pier and be permanent in nature and be safe for vessel and crew to utilize. A removable man pole situated to aid both left-handed and right-handed personnel in boarding shall be included, along with a secure storage location for man pole when not in use.

5.8 NEW TRANSDUCER (Forward Looking Sonar)

5.8.1 Install a forward-looking sonar and side scanning sonar system with display capabilities at cabin helm station on a color unit of about 14”. Display unit should be powerful enough to run the transducer drivers without the addition of supplemental driver power. Install a weatherproof repeater for basic depth at after helm station.

5.8.2 Ensure FWS will fully integrate with current navigation equipment and depth sounder already on-board vessel.

5.8.3 Install a power switch, IVO the main helm, that isolates power to all sounders (3) so as to eliminate crossover transmission to the survey equipment when in use.

5.9 EXTERIOR CABIN

5.9.1 Contractor will bead blast the exterior of the house/cabin, top-deck, railings and mast, clean all corrosion and all paint leaving a near-white blast clean surface free of any remaining paint throughout the exterior cabin surface and appendages from the main deck to the cabin top and mast, to include mast in its entirety. Blasting and cleaning shall be in accordance with Aluminum Structures Painting Counsel Specifications SSPC-SP-10. Window will be protected from bead blasting and any damage to windows result in windows being replaced at contractor’s expense. This is a government inspection point.

5.9.2 Cabin top will be left nude with the exception of non-skid adhesive strips in strategic areas for personnel. No rust or oxidation will be evident on the metal surface, prior to application of non-slip strips. Situate waterways around welded seams and deck hatches following the original waterway pattern prior to bead blasting. This is designated as a government inspection point; Government Inspector will inspect all work up to this point before contractual work continues. Cabin and decks will otherwise be clean aluminum.

5.9.3 Mast and radar stand to be left bear metal.

5.9.4 Apply a 19-inch black 5-point star along with the work ARMY in 10 inch black lettering on the port and starboard house. Position and location to be indicated by Government. Install 16” x 23” Army Corps Logo Red Castle centered on the outside (seaward) of the storage deck boxes. All lettering and images should be of high quality self-adhering heavy-duty non-reflective vinyl. Logo’s will be supplied to contractor via PDF. Supply government with three copy sets of “decals”. This is a government inspection point.

5.10 INCLINE EXPERIMENT & PLACING OF BALLAST

5.10.1 BALLAST

Due to changes in the vessel’s lightship and operational displacement, the Government requires up to 15,000-pounds of ballast to be installed in the aft steering gear compartment. Acceptable materials for ballast include lead plate, lead ingots/bars, and/or lead shot. The ballast shall be located to allow full access to all equipment, valves, switches and controls in the space, and maintenance access for inspection and painting to the bilges, bottom plating, and side shell plating. Ingress and egress from the space shall not be obstructed. The ballast shall be installed with the overall transverse center of gravity located on the vessel’s centerline. The ballast shall be installed in ballast boxes that are designed to keep the ballast from shifting. The ballast nor ballast boxes shall not be installed in the bilge with direct contact with the bottom plating.

The contractor shall develop drawings and details for the proposed ballast and installation. The drawings shall include details on the ballast location(s), type, quantity, ballast boxes/containment structures, and foundations. The drawings shall be submitted to USACE for review and approval prior to work commencing work. Once the drawings are approved, the contractor shall install the ballast boxes, but the ballast will not be loaded onboard until after the incline experiment is complete and the results evaluated. USACE will inform the contractor on the final quantity of ballast to install. All installed ballast shall be secured in the ballast boxes to prevent shifting during vessel operations. This is a government inspection point.

5.10.2 INCLINE EXPEREMENT

Due to changes in the vessel’s lightship displacement and the requirement addition of permanent ballast, an incline experiment is necessary to document the new lightship displacement and centers of gravity for the vessel. The contractor shall develop an incline experiment plan and submit to USACE for review and approval. The plan shall be prepared by a Registered Professional Engineer and submitted to USACE for review and approval. The incline experiment plan shall be submitted at least 45 days prior to the scheduled incline experiment. The incline experiment shall be in accordance with ASTM F1321. Following the completion of all work and the vessel refloated (without ballast), the contractor shall carryout an incline experiment to determine the lightship weight and centers of gravity. The experiment shall be directed by a Registered Professional Engineer and the results provided to USACE for review and approval. Following the approval of the incline experiment results, USACE will be responsible for updating all stability related documents with the new lightship characteristics and installed ballast. Within seven days of the incline experiment results approval, USACE will inform the contractor on the final quantity of ballast (not to exceed 15,000-pounds) to install. This is a government inspection point.

5.11 DIESEL ENGINES, GENERATOR & TRANSMISSIONS

5.11.1 MAIN ENGINES

Contractor shall perform main diesel engine tune up in accordance with manufacture’s procedures for the appropriate hours schedule. At a minimum, the service should also include work items listed below in 5.11.2 through 5.11.5. Contractor shall take engine coolant, transmission oil and engine oil lubricating samples and have tested by third party. All work will be performed per manufacturer recommended procedures and specifications.

5.11.2 Conduct the following for both port and starboard engines:

• Change suction and pressure side fuel filters.

• Change Oil and oil filters

• Replace zincs on cooler and heat exchangers

• Flush coolant system and replace with fresh coolant.

• Replace thermostats after flush of coolant system.

• Inspect for fuel leaks and replace any suspect soft fuel lines.

• Replace drive belts.

• Replace impellers

• Replace coolant filters

5.11.3 Inspect and replace if needed the following main diesel engine items:

• Sea water hoses

• Heat exchange pressure cap

• Check for air leaks intake and exhaust system

• After cooler inlet pipe

• Engine mounts and mounting bolts, check mounting bolts torque

• Marine vibration isolator

• Fiberglass Exhaust Line (pressure test checking for exhaust burn through in the glass tubing)

5.11.4 Flush and clean the following items

• Heat exchanger

• After cooler assembly

• Air filters washed and re-oiled

5.11.5 Battery Replacement

• Inspect wires and replace all batteries.

Contractor shall perform an operational performance test on the main diesel engines after tune up. Present operational testing results and main engine tune-up summary via submittal in electronic (Microsoft Word or PDF) and hard copy formats.

5.11.6 TWIN DISK TRANSMISSIONS

Contractor will perform scheduled maintenance as per manufacture’s procedures. Inspect, gear boxes, for any lubricating oil or coolant leaks. Take transmission lubricating oil samples, have tested and present results.

• Change oil and filters

• Clean suction strainer

• Replace heat exchanger zincs

• Inspect the input coupling

• Grease the oil seals and output shaft

5.11.7 ONAN GENERATOR

Contractor shall drain and flush coolant system and inspect and replace thermostats, as well as any damaged, worn or corroded parts. Contractor shall also replace coolant, exhaust and raw water flexible hoses, belts and raw water pump impeller on generator. Contractor shall inspect exhaust gaskets and replace if needed. Work will be performed per manufacturer recommended procedures and specifications.

• Change oil and oil filter

• Change fuel filter

• Replace zincs

• Replace impeller

• Replace coolant pressure cap and thermostat

• Adjust value lash

Present operational testing results and generator tune up summary via submittal in electronic (Microsoft Word or PDF) and hard copy formats.

5.12 STEERIN SYSTEM

5.12.1 Sterring Overhaul

Hot wash steering system hydraulic steering system hydraulic tank. Change hydraulic steering filters. Replace all flexible steering system hoses. Replace steering system hydraulic fluid with new hydraulic fluid. Inspect system for leaks.

5.12.2 Sterring Added Redundancy

Duplicate the steering pump on the starboard main engine to the port main engine for redundancies. Conduct hot wash from

5.12.1 after complete installation.

5.13 ENGINE / TRANSMISSIONA & SHAFT ALIGNMENT

Third Party Laser Alignment- Provide two degreed engineers with 20+ years experience specific to marine industry engine/gearbox/propeller shafting for laser alignment services. Correct alignments to minimum acceptable tolerances.

5.14 ROTATING MASS VIBRATIN ANALYSIS

A third-party Vibration Analysis will be provided by a degreed engineer with Vibration level II certification, and 20+ years vibration analysis services in the marine industry. This analysis will be completed post running gear alignments and compared to baseline analysis from Sept ’25 reports.

5.15 ENGINE ROOM INTERIOR LIGHTING

Add one light to the forward centerline overhead of the engine room. Should be of low-profile LED duplicating the light that is in the steering gear room.

5.16 BILGE PUMPS

5.16.1 Replace all Rule-type bilge pumps and floats in kind with new bilge pumps and overboard discharge hoses in the anchor locker, berthing area, workshop, engine room and Lazaret.

5.16.2 Inspect bilge pump and bilge alarm wiring and replace any found spliced or worn.

5.16.3 Replace all check-valves at overboard discharge through-ports.

5.16.4 Repair audible bilge alarm system with the addition of an alarm panel.

5.17 INSTALL TANK MONITORING SYSTEMS

Install a NEMA 2000 compliant electronic tank level monitoring system for black water tank, freshwater tanks and fuel tanks.

This is the start of the file's text. The full file is on GovTribe.