Attachment 2 - Construction Staging Plan.pdf
PDF 4 MB Posted
- Solicitation number
- 697DCK-24-R-00305
About this file
This document is an Attachment 2 - Construction Staging Plan related to a federal contract opportunity issued by the Department of Transportation Federal Aviation Administration (FAA) for the installation of an Americans with Disabilities Act (ADA) compliant exterior ramp at their Air Route Traffic Control Center (ARTCC) in Auburn, Washington.
The FAA is seeking contractors to submit offers for this construction project, which is estimated to be between $250,000 and $500,000 in value. The work includes relocating a door, replacing adjacent finishes, constructing a handicap ramp with concrete walkway and stairs, installing lighting and access controls, an architectural awning, and landscaping features. The solicitation is set aside for a small business under NAICS code 236220 - Commercial and Institutional Building Construction. Key dates include a mandatory site visit on April 17, 2024, questions due on April 29, 2024, and offers due on May 20, 2024.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
H
G
F
E
D
C
B
A
SERVICE GATE
7 6
AUBURN WAY (TO STATE HIGHWAY 164)
OPERATIONS
SUPPORT
WING
c:::::::) c:::::::)
PARKING
STORAGE
r-x-=x-x-x-x-x-=x-x-x-x-x-=x-~
I I 1 <.µ."-4-'-,,,,_,,,,_,,,...,,..',L-4'-4£"""4"-4-'-¥-4.L..4L~~.,, CONSTRUCTION 1 l <-+-+-+-<--+--+--<-+-+-f--+-" STAGING AREA
1 ~~~ I <?' X I
J'UL.....JV'f' ~ 0( <( <(@ I I
I
I
I
CONTROL
WING
FREIGHT
ELEVATOR
fW',40---PROJECT LOCATION FOR
PANEL B-3003A
GARAGE & ENGINE GENERATOR BLDG
rRRR 1~~~1
TMS&MWP
SATELLITE
ANTENNAS
POWER SERVICE
BLDG
D
I I
I
I
I I
I
I
I I
I
I
SECURITY FENCE l -=~--~X X X X
PROPERTY LINE PUMP HOUSE
CONSTRUCTION STAGING PLAN
NOTTO SCALE
PROJECT
NORTH
RETAINING WALL
PROPERTY LINE
f-w w
"' f-
"' " '-' g w I
5 4
CONSTRUCTION STAGING PLAN NOTES:
THE FOLLOWING NOTES AND ACCOMPANYING "CONSTRUCTION STAGING PLAN" REPRESENT
MANY OF THE MAJOR REQUIREMENTS STATED IN "DIVISION I - GENERAL REQUIREMENTS"
OF THE SPECIFICATIONS. THESE NOTES PARAPHRASE DIVISION I REQUIREMENTS AND ARE NOT
INTENDED TO MODIFY OR REPLACE ANY DIVISION I REQUIREMENTS.
CONSTRUCTION ACCESS, CONTRACTORS PARKING, CONSTRUCTION OFFICES AND THE EXTENT/SIZE
OF THE CONSTRUCTION STAGING AREA MUST BE COORDINATED WITH COR.
A. CONSTRUCTION ACCESS
A.1 CONTRACTOR'S VEHICLES, PEDESTRIANS AND ALL DELIVERIES TO THE SITE SHALL BE
THROUGH THE MAIN FAA SECURITY GATE. THIS GATE IS MANNED 24 HOURS A DAY.
A.2 ALL DELIVERIES SHALL BE SCHEDULED IN ADVANCE WITH COR AND AT TIMES OTHER THAN
THE FAA EMPLOYEE SHIFT CHANGES TO AVOID CONGESTION. FAA SHIFT CHANGES OCCUR
FROM 6:30 AM TO 9:00 AM AND FROM 2:30 PM TO 4:00 PM.
A.3 THE CONTRACTOR SHALL PROVIDE SIGNAGE TO INDICATE THE ACCESS ROUTE FOR CONSTRUCTION EMPLOYEES AND DELIVERIES ON THE SITE. PROVIDE NECESSARY BARRICADES, LIGHTS, SIGNAGE
AND FENCING TO PROTECT, WARN AND DIRECT ALL PERSONS NEAR THE CONSTRUCTION AREAS.
A.4 CONTRACTOR'S ACCESS TO THE BUILDING SHALL BE LIMITED TO THE FOLLOWING LOCATIONS:
1). LOADING DOCK; 2). FREIGHT ELEVATOR WILL BE USED ONLY WITH COR APPROVAL FOR LARGE OR HEAVY
EQUIPMENT.
A.5 CONTRACTOR SHALL KEEP LOADING DOCK AND CAFETERIA ACCESSIBLE AT ALL TIMES FOR
FAA DELIVERIES.
B. CONTRACTOR PARKING
B.1 ALL CONTRACTOR PARKING SHALL BE LIMITED TO CONSTRUCTION STAGING AREA. ADDITIONAL
PARKING MAY BE PROVIDED (IF AVAILABLE) BY WRITTEN REQUEST TO THE COR.
B.2
8.3 c.
C.1
C.2
C.3
C.4
ADDITIONAL PARKING, IF NECESSARY SHALL BE OFF SITE AND COORDINATED BY THE CONTRACTOR
PROVIDE SIGNAGE AS NECESSARY TO RESERVE THIS AREA FOR CONTRACTOR PARKING ONLY.
FAA SECURITY REQUIREMENTS
AN ADVANCE LIST OF CONSTRUCTION PERSONNEL SHALL BE PROVIDED TO THE COR.
TEMPORARY SECURITY BADGES WILL BE ISSUED TO CONSTRUCTION PERSONNEL. EACH
CONSTRUCTION EMPLOYEE SHALL CHECK IN AND OUT AT THE MAIN GATE. THE
CONTRACTOR SUPERVISORY PERSONNEL SHALL BE RESPONSIBLE FOR THE CONDUCT OF
THEIR PERSONNEL WHILE ON SITE. ALL CONTRACTORS' VEHICLES SHALL BE MARKED AS
SUCH.
THE SITE IS A SECURE AREA. ACCESS FOR ALL CONSTRUCTION PERSONNEL IS LIMITED
TO THE CONSTRUCTION AREA AND DESIGNATED ACCESS ROUTES AT ALL TIMES.
FAA ESCORTS MAY BE REQUIRED FOR CONSTRUCTION PERSONNEL WORKING WITHIN THE
BUILDING. COORDINATE ALL WORK OUTSIDE THE DESIGNATED AREAS WITH COR. ESCORTS
OUTSIDE THE BUILDING WILL NOT BE REQUIRED.
THE CONTRACTOR SHALL USE GREAT CARE AND CAUTION WHILE WORKING INSIDE THE
FACILITY. ALL WORK MUST BE COORDINATED WITH COR. DISRUPTION OF THE
SERVICES OF THIS FACILITY WILL NOT BE PERMITTED.
D. CONSTRUCTION MATERIAL STORAGE
D.1 STORAGE OF CONSTRUCTION MATERIALS AND TRAILERS ON THE SITE SHALL BE LIMITED TO
THE CONSTRUCTION STAGING AREAS. MATERIALS SHALL BE NEATLY STORED AND PROTECTED
AT ALL TIMES. A CONSTRUCTION FENCE SHALL BE INSTALLED AT THE DIRECTION OF THE
D.2
COR. CONSTRUCTION MATERIALS, FENCING, VEHICLES, AND THE TRAILER SHALL BE LOCATED A MINIMUM OF 20'-0" FROM THE PERIMffiR FENCE. CONTRACTOR SHALL NOT DIG WITHOUT PERMISSION FROM COR. BURIED CABLES (UNDERGROUND UTILITIES) RUN THROUGH THE STAGING
AREA AND ELSEWHERE.
THE CONSTRUCTION STAGING AREA'S EXACT SIZE AND LOCATION SHALL BE DETERMINED AT
THE PRECONSTRUCTION CONFERENCE BY THE FAA. REFER TO CONSTRUCTION STAGING PLAN
FOR APPROXIMATE INFORMATION.
D.3 CONSTRUCTION LIGHTING SHALL BE PROVIDED AS REQUIRED BY OSHA REGULATIONS IN THE CONSTRUCTION STAGING AREA TO ILLUMINATE ADEQUATELY THE AREA FOR SAFE WORK. ALL LIGHTING SHALL BE APPROVED BY THE CONTRACTING
OFFICER REPRESENTATIVE BEFORE
E.
E.1
F.
F.1
USE. UPON COMPLETION OF CONSTRUCTION, REMOVE ALL CONSTRUCTION LIGHTING.
ALL AREAS AND SURFACES DISTURBED SHALL BE REPAIRED AND/OR REPLACED BY THE
CONTRACTOR.
CONSTRUCTION DEBRIS
ENCLOSED DUMPSTERS FOR DISPOSAL OF CONSTRUCTION DEBRIS SHALL BE PROVIDED BY THE
CONTRACTOR WITHIN THE STAGING AREA. THE AREAS AROUND THE DUMPSTERS SHALL BE
KEPT CLEAN AND FREE OF EXCESS DEBRIS AND DUST DURING CONSTRUCTION. ALL DEBRIS
SHALL BE REMOVED BY CONTRACTOR.
CONSTRUCTION OFFICE
CONTRACTOR TRAILER SHALL BE LOCATED IN THE CONSTRUCTION STAGING AREA. THE CONTRACTOR MAY PROVIDE TELEPHONE AT HIS COST FOR HIS USE. CONSTRUCTION MATERIALS, FENCING, VEHICLES, AND THE TRAILER SHALL BE LOCATED A MINIMUM OF 20'-0" FROM THE PERIMETER FENCE. THE CONTRACTOR SHALL PROVIDE ALL NECESSARY POWER AND WATER FOR THE OFFICE TRAILER AND COR TRAILER.
5 4 3
G. CONSTRUCTION TOILET FACILITIES
G.1 PORTABLE CHEMICAL TOILETS SHALL BE PROVIDED BY THE CONTRACTOR AS REQUIRED
WITHIN THE CONSTRUCTION STAGING AREA AT THE CONTRACTOR'S EXPENSE.
H. DEMOLITION AND CONSTRUCTION HOURS
H.1 THE CONTRACTOR SHALL NOT INTERFERE WITH THE AIR TRAFFIC CONTROL FUNCTION OF
THE FACILITY. DEMOLITION AND CONSTRUCTION NOISE MUST BE MINIMIZED BETWEEN
5:00 AM AND 8:30 PM.
H.2 NOT USED.
H.3 SCHEDULE ALL NOISY DEMOLITION A MINIMUM OF 10 DAYS IN ADVANCE WITH THE COR.
H.4 CONCRETE SAWING, CORE DRILLING, CONCRETE DEMOLITION AND ANCHOR DRILLING
WILL BE PERFORMED IN A DUST FREE MANNER BETWEEN THE HOURS OF 1 :00 AM AND
5:00 AM ONLY AT PREARRANGED TIMES APPROVED BYTHE COR.
PARKING LOT DRIVEWAY AND LAWN AREA REPAIR
1.1 UPON COMPLETION OF WORK THE CONTRACTOR SHALL REPAIR ALL PAVED SURFACES,
DAMAGED BY CONSTRUCTION ACTIVITIES, TO ORIGINAL CONDITION.
1.2 LAWN AREAS DISTURBED BY CONSTRUCTION ACTIVITY SHALL BE RESTORED TO ORIGINAL
CONDITION. DISTURBED LAWN SHALL BE REPAIRED WITH SOD, SEEDING IS UNACCEPTABLE.
J. HAZARDOUS MATERIAL:
J.1 CONTRACTOR SHALL DISPOSE OF ALL HAZARDOUS MATERIALS ACCORDING TO FEDERAL AND/OR LOCAL
REGULATIONS, WHICHEVER IS MORE STRINGENT.
K. EQUIPMENT PROTECTION
K.1 IT IS ABSOLUTELY MANDATORYTHATTHE CONTRACTOR PROTECT ALL NEW AND EXISTING
FAA COMMUNICATION, ELECTRICAL AND MECHANICAL EQUIPMENT, BOTH INSIDE AND OUTSIDE
THE BUILDING FROM DAMAGE CAUSED BY IMPACT, WATER, DEBRIS OR DUST. THE FAA SHALL
HAVE 24 HOUR ACCESS TO THE PROTECTED EQUIPMENT.
K.2 SHUTDOWN AND CUTOVERS OF ELECTRICAL AND MECHANICAL SYSTEMS SHALL BE ACCOMPLISHED BETWEEN THE HOURS OF 1 :00 AM AND 5:00 AM. ALL PREPARATORY WORK SHALL BE COMPLETED PRIOR TO SHUTDOWN, AND CUTOVER SHALL BE SCHEDULED AND COORDINATED WITH THE CORA MINIMUM OF 10 DAYS IN ADVANCE OF THE SHUTDOWN AND CUTOVER. FAA REQUIRES CONTRACTOR TO
SUBMIT IN WRITING THE CUT OVER REQUEST WITH A MINIMUM OF 10 DAYS ADVANCE NOTICE.
K.3 THE ARTCC IS A 24 HOUR A DAY, 7 DAY PER WEEK OPERATING FACILITY. IT WILL BE
NECESSARY TO COORDINATE ALL CONSTRUCTION ACTIVITY SO AS NOT TO INTERFERE
WITH THE FUNCTIONS OF THE ARTCC.
K.4 NO WELDING AND TORCH CUTTING EQUIPMENT SHALL BE POWERED BY THE FACIWY ELECTRICAL SYSTEM.
WELDING AND TORCH CUTTING SHALL BE CONDUCTED WITH SMOKE MINIMIZING METHODS. COR APPROVAL
SHALL BE GAINED BEFORE WELDING AND TORCH CUTTING.
K.5 CONTRACTOR SHALL RECEIVE PERMISSION FROM COR/RESIDENT ENGINEER BEFORE USING
POWER SUPPLIES DURING THE WORK.
FOR OFFICIAL USE ONLY
PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552
REV
APPROVED
DATE DESCRIPTION JCN
DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
REDLINE
DATE PVD
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
ARTCC
CONTROL WING
ADA RAMP
CONSTRUCTION STAGING PLAN
SEATTLE AUBURN WA
PROJECT ENGINEER MGR: ENGINEERING - SEATTLE
DESIGNED ISSUED BY DATE 09/15/2023 JCN 1402263
ENGINEERING SERVICES DRAWING NO
1---1---f-=c=He=cK=eo-------j ENROUTE/FSS ZSE-1402263-G003
H
G
Di 5' " w f/l
F
E
D
C
B
DRAWltG PRODUCED ON WSA MICROSTAllON SYSTEM
Jon Orr Highlight
Jon Orr Highlight
File details come from the government source that posted it. Updated .