The provided document is a set of construction drawings for an ADA-compliant ramp installation project at the Federal Aviation Administration's (FAA) Air Route Traffic Control Center (ARTCC) in Auburn, Washington. The drawings detail the scope of work, including relocating an exterior door, constructing a handicap ramp with concrete walkway, stairs, and handrails, installing exterior lighting and access controls, an architectural awning, and landscaping features. The related federal contract opportunity is a solicitation (Solicitation Number: 697DCK-24-R-00305) seeking qualified small business contractors to perform this construction project, which is estimated to be between $250,000 and $500,000 in value. Key dates include a mandatory site visit on April 17, 2024, question submissions due by April 29, 2024, and offers due by May 20, 2024. The procurement is set aside for small businesses under NAICS code 236220 - Commercial and Institutional Building Construction.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAWING NUMBER DESCRIPTION
ZSE 1402263 G001 COVER SHEET
ZSE 1402263 G002 DRAWING INDEX AND VICINITY MAP
ZSE 1402263 G003 CONSTRUCTION STAGING PLAN
ZSE 1402263 C101 CIVIL GRADING PLAN
ZSE 1402263 C201 CONCRETE PLAN
ZSE 1402263 C501 SECTIONS AND DETAILS
ZSE 1402263 A101 FIRST FLOOR ARCHITECTURAL DEMO PLAN
ZSE 1402263 A201 FIRST FLOOR PLAN
ZSE 1402263 A401 RAMP/AWNING SECTIONS
ZSE 1402263 A402 RAMP ELEVATIONS
ZSE 1402263 E202 ELECTRICAL PLAN
ZSE 1402263 E701 PANEL AND LIGHTING SCHEDULES
ZSE 1402263 L001 LANDSCAPE PLAN
DRAWING INDEX
TYPE QTY DESCRIPTION MANUFACTURER CATALOG NUMBER1 LAMPS VOLTS FIXTURE MOUNTING FINISH COMMENTS
SL-1 1 LED SURFACE MOUNTED UNDER AWNING GKOLED GKOCP0330W27V40KWMLBB LED 120 SURFACE BLACK Surface Mount Above Door Under Awning Structure
LIGHTING FIXTURE SCHEDULE
NOTES: Contractor field verify mounting method to ensure compatibility. Different catalog number than is specified may be required for LP fixtures to suit existing circuit conditions; furnish appropriate part to suit circuit voltage.