This document is Attachment 2 to a federal contract solicitation, containing a Contract Data Requirements List (CDRL) comprised of multiple DD Form 1423s that specify data submission requirements for the contractor.

The CDRL establishes six primary data requirements, all directed to the Department of the Army at Watervliet Arsenal (TAWV-CQD-E), Bldg. 35-E, Watervliet NY 12189-4000. The first requirement mandates submission of Test/Inspection Reports documenting inspection records for production components (CN12) with authority DI-NDTI-80809B, submitted with each shipment with one final copy required. The second requires Certification/Data Reports for Certificate of Conformance (COC) for nondestructive testing applications (CN 9) per authority DI-MISC-80678, including detailed technique sheets specifying magnetizing current methods, amperages, part sketches, gauss reading locations, and inspection medium types. The third requirement calls for Test/Inspection Reports for First Article Samples using WVA Form 702-61-R-E and DD Form 1222, submitted once upon first article delivery per DI-NDTI-80809B. The fourth requires Chemical and Physical Properties Analysis Reports for major forgings/castings (CN1) submitted as SMCWV Form 1155 with each shipment per authority DI-FORG-81196. The fifth mandates Test Procedures for Magnetic Particle Inspection (CN 23) per DI-NDTI-80603 and ASTM-E1444, requiring written procedures submitted with first article or no later than 30 days prior to first production shipment, allowing 15 days for government review and approval. All data items carry Distribution Statement B (Test and Evaluation), with no DD250 forms required except as specified in the first article requirement. The forms were prepared by J. Cannon and approved by William Potter, TAWV-CQD-E, on March 3, 2025.

View the file

Other files

File Type Posted
W911PT26QA087.pdf PDF
ATTACHMENT 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 2- CDRLS

CONTRACT DATA REQUIREMENT LIST – DD Form 1423

Form Approval OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis

Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction

Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.:

B. EXHIBIT

C. CATEGORY

D. SYSTEM/ITEM

E. CONTRACT/PR NO.:

F. CONTRACTOR

1. DATA ITEM NO:

2. TITLE OF DATA ITEM: Test/Inspection Report

3. SUBTITLE: Inspection Records, Production Components (CN12)

4. AUTHORITY: DI-NDTI-80809B

5. CONTRACT REFERENCE: QAP-APPX-WVA

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: With Each Submission

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Shipment

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Shipment

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn: TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1

Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Delete paragraph 10.2 through 10.2.8 of referenced DID (Block 4).

Submit all records for production components. See QAP-APPX-WVA paragraph 4.2 and 4.5 for the requirement.

Data Item Description (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

17. PRICE GROUP:

18. ESTIMATED TOTAL PRICE:

G. PREPARED BY: J. Cannon

H. DATE: March 3, 2025

I. APPROVED BY: William Potter, TAWV-CQD-E

J. DATE: March 3, 2025

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis

Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction

Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY

D. SYSTEM/ITEM

2. TITLE OF DATA ITEM: Certification/Data Report

3. SUBTITLE: Certificate of Conformance (COC), NDT Applications (CN 9)

4. AUTHORITY: DI-MISC-80678

5. CONTRACT REFERENCE: QAP-APPX-WVA and applicable drawing or material specification

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: With Each Submission

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Shipment

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Shipment

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn: TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1

Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS:

a. Paragraph 10.3, 10.4 of referenced DID (Block 4) is not applicable. See QAP-APPX-WVA paragraph

4.6 and 9 for the general requirements. The COC will also contain specific references to a specification or drawing for the acceptance standards, procedure and personnel qualifications. Data Item Description (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

b. The required Technique Sheet is specific to the part and gives details of the process on that part, for example:

1. Method of establishing the magnetizing current (Head Shot, Coil. Prods, Yoke Cable wrap etc.); 2. Amperages used in the inspection on both fields, sequencing included. (Head shot first at 500amps/Coil shot second 800 amps);

3. Pictures/Sketches of the part and its orientation; 4. Where on the part are they checking for proper minimum gauss readings (30- 60); what are they using to check this reading, QQI, Hall Effect Probe; 5. Type of Inspection Medium

(Wet Fluorescent/Dry Particles, Continuous Method/Residual)

G. PREPARED BY: J. Cannon

H. DATE: March 3, 2025

J. DATE: March 3, 2025

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis

Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction

Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY

D. SYSTEM/ITEM

2. TITLE OF DATA ITEM: Test/Inspection Report

3. SUBTITLE: Inspection Records – First Article Sample WVA FORM 702-61-R-E, 16 March 2016 702-CQD-E

61 8 Jan 2025(CN 3)

4. AUTHORITY: DI-NDTI-80809B

5. CONTRACT REFERENCE: First Article Clause

6. REQUIRING OFFICE: TAWV-CQD-C CQD-E

7. DD250 REQUIRED: *See Block 16

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: ONE/P

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Article

13. DATE OF SUBSEQUENT SUBMISSIONS: With First Article

14. DISTRIBUTION:

A. ADDRESSEES: As specified in contract or purchase order

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Delete paragraph 10.2 of referenced DID (Block 4). Submit WVA Form 702-61-R-E showing results of inspections. Also submit DD Form 1222. Computerized versions of these forms may be used with prior approval of the procuring office. See QAP-APPX-WVA paragraph 10 for requirements. * Inspection/acceptance requirements specified in the contract. Data Item Description (DID) referenced in block 4 can be accessed at:

http//assist.daps.mil.

G. PREPARED BY: J Cannon

H. DATE: 3 Mar 2025

J. DATE: 3 March 2025

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis

Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction

Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY

D. SYSTEM/ITEM

2. TITLE OF DATA ITEM: Chemical and Physical Properties for Forging or Casting Analysis Report

3. SUBTITLE: Record of Treatment and Test, Major Forgings/Castings (CN1)

4. AUTHORITY: DI-FORG-81196

5. CONTRACT REFERENCE: Applicable Drawing or Material Specification

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE:

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: With Each Submission

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: With First Shipment

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Shipment

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1

Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Submit SMCWV Form 1155 for each component or lot. A computerized version of SMCWV

Form 1155 may be used with prior approval of the procuring office. Data Item Descriptions (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

G. PREPARED BY: Julie Cannon

H. DATE: 6Mar 2025

I. APPROVED BY: William Potter, TAWV- CQD-E

J. DATE: 10 Mar 2025

Public reporting burden for this collection of information is estimated to average 440 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis

Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction

Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY

D. SYSTEM/ITEM

2. TITLE OF DATA ITEM: Test Procedure

3. SUBTITLE: Magnetic Particle Inspection Procedures (CN 23)

4. AUTHORITY: DI-NDTI-80603

5. CONTRACT REFERENCE: QAP-APPX-WVA and ASTM-E1444

6. REQUIRING OFFICE: TAWV-CQD-E

7. DD250 REQUIRED: No

8. APP CODE: A

9. DISTRIBUTION STATEMENT REQUIRED: B Test and Evaluation

10. FREQUENCY: ONE/R

11. AS OF DATE:

12. DATE OF FIRST SUBMISSION: *See Block 16

13. DATE OF SUBSEQUENT SUBMISSIONS: With Each Revision

14. DISTRIBUTION:

A. ADDRESSEES: DEPARTMENT OF THE ARMY, Attn: TAWV-CQD-E Bldg. 35-E, Watervliet Arsenal, 1

Buffington Street, Watervliet NY 12189-4000

B. COPIES:

DRAFT: 0

FINAL: 1

15. TOTAL: 1

16. REMARKS: Delete paragraph 10.2 through 10.2.2.8 of referenced DID (Block 4). Submit written procedures for review and approval by the procuring office. The minimum elements of the procedure are detailed in paragraphs

5.3 thru 5.3.1.15 of ASTM-E1444. Specific heat treatment requirements will be per QAP-APPX-WVA paragraph

9.1. *With First Article or no later than 30 days prior to first production shipment when First Article is not required.

Government requires 15 days to review/approve. Data Item Description (DID) referenced in block 4 can be accessed at: http//assist.daps.mil.

G. PREPARED BY: J Cannon

H. DATE: 3 Mar 2025

J. DATE: 3 March 2025