Attachment 2 - CDRL June 2025.pdf
PDF 99 KB Posted
- Solicitation number
- FA860126R0009
About this file
This is a Contract Data Requirements List (CDRL) dated 23 June 2025, specifying 12 deliverables that the contractor must submit throughout the contract performance period. The deliverables encompass environmental compliance reporting, inventory management, security documentation, quality assurance, and project management activities, with distribution required to both 88 CEG/CEIEC and AFLCMC/PZICC.
The deliverables include monthly submissions of Container Pickup Logs and Contractor's Progress, Status, and Management Reports (both due on the 5th of each month), annual End of Year Inventory reports and Quality Management Plans (due January 14th and January 31st respectively), semi-annual AF Data Call reports (due April 10th and October 10th), biennial reports (due January 14th), waste-related documentation including Waste Accumulation Period Spreadsheets (due day 50 of each WAP), Polychlorinated Biphenyl reports (due at end of each WAP), Universal Waste Lamp reports (as required), and as-needed submissions including Spill Reports (within 24 hours of verbal notification), Security Reports for personnel changes, and Meeting Minutes (within 5 calendar days of meetings). All deliverables are distributed to both listed organizations, ensuring comprehensive oversight of contractor performance and compliance with Air Force environmental and operational requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
23 JUNE 2025
EXHIBIT A
CONTRACT DATA REQUIREMENTS LIST (CDRL)
CDRL
PWS Para Deliverable Title Date of Submission Frequency
Distribution
CEG/CEIEC AFLCMC/PZICC
A001 1.1.1.1.6 Container Pickup Log On the 5th of every month
Monthly Y Y
A002 1.1.1.2.5 End of Year Inventory January 14th Annually Y Y A003 1.1.1.2.7 AF Data Call reports On the 10th of April and
October Semi-Annually Y Y
A004 1.1.1.2.7 Biennial Reports January 14th Biennially Y Y A005 1.1.1.5.1 Waste Accumulation
Period (WAP) Spreadsheet
On day 50 of each WAP As required Y Y
A006 1.1.1.5.3 Polychlorinated Biphenyl (PCB) report
At the end of each WAP As required Y Y
A007 1.1.1.5.4 Universal Waste (UW) Lamp report
As required As required Y Y
A008 1.1.1.8 Spill Report Within 24 hours of verbal notification
As required Y Y
A009 1.4.1 Security Report-personnel change
As required As required/ Annually
Y Y
A010 2.2 Meeting Minutes 5 Calendar days after meeting
As required/ Monthly
Y Y
A011 2.5 Quality Management Plan
Within 30 calendar days of contract start, every
January 31st
Annually Y Y
A012 2.7 Contractor’s Progress, Status, and Management Report
(CPSMR)
On the 5th of every month
Monthly Y Y
File details come from the government source that posted it. Updated .