Attachment 2- Cable Inspection Criteria NAVSEA INST.9404.1D.pdf

PDF 91 KB Posted

Attached to
5280023PR0001507- NAVSEA Cableway Training
Solicitation number
5280023PR0001507
Issued by

About this file

This document contains an electrical cableway inspection form and criteria for inspecting cables and cableways aboard U.S. Navy vessels. The inspection form requires documenting information such as the hull number, location, cable type, circuit, and description of cables to be inspected. The criteria outline potential hazards categorized from immediate to non-hazardous for issues such as minimum bend radii, slack, splices, banding, hanger spacing, penetrations and more. Relatedly, solicitation 5280023PR0001507 from the U.S. Coast Guard seeks cableway training, indicating need for educating personnel according to the inspection standards specified in the document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

7 of 11 ITEM NO: 009-73

FY-23

ATTACHMENT A

ELECTRICAL CABLEWAY INSPECTION FORM

DATE HULL NUMBER

INSPECTED BY INSPECTING ORGANIZATION

SER # COMPT DECK FRAME P/S POS CABLE

CIRCUIT

DESIG

CABLE

TYPE

*CAT *NAVSEA

DWG NO.

EQUIPMENT

DESCRIPTION

* SEE ATTACHMENT B FOR "CATEGORY" GUIDANCE

8 of 11 ITEM NO: 009-73

ATTACHMENT B

INSPECTION CRITERIA FOR ELECTRICAL CABLES AND CABLEWAYS

CATEGORY 1 - Immediate Hazard

CATEGORY 2 - Potential Hazard

CATEGORY 3 - Non-Hazardous

ITEM CRITERIA CATEGORY

I. CABLES

A. Installation

1.

Minimum bend radius exceeded, causing visual damage to cable.

2.

Minimum bend radius exceeded; No visual cable damage, cable rings out and meggers satisfactorily.

3.

Equipment connector supporting weight of cable

(more than 32 inches of cable from last support to end use equipment). (18 inches from shock mounted motors).

4.

Cables run on or near hot objects (steam or exhaust pipes, griddles, ovens, etc.

5. Cable run outside of hangers. 3

6. Lack of slack at expansion joints. 2

7.

Excess slack between hangers. (Minimum distance of 6 feet 4 inches between deck and cables.)

8. Excess cable slack stored in wireway. 3

B. Damaged

1.

Bulging, bubbling or discoloration of cable jacket

(evidence of overloading, overheating or hot spots.)

2.

Bulging, bubbling or discolored cable jacket; but cable rings out and meggers satisfactorily.

3. Cable chafed or cut through outer jacket only. 2

4.

Cable chafed or cut through, inner wire insulation damage.

5.

Cable pulled out of equipment/junction box penetrations and leads exposed

6.

Armored and unarmored cables in contact at an oblique angle causing chafing of unarmored jacket.

9 of 11 ITEM NO: 009-73

ITEM CRITERIA CATEGORY

7.

Fiber cable chafed or cut beyond the cable outer jacket to the Kevlar strength members

C. Dead-ended

1.

Cable dead-ended, not end sealed and labeled

(serialized) properly at both ends.

2.

Cable for future use not properly sealed on both ends and labeled at both ends for the specific use.

3.

Cable dead-ended, end sealed and labeled

(serialized) properly.

D. Spliced

1.

Improper materials/methods used for splicing, or evidence of loose joints.

2. Splice located in bend of cable. 2

II. BANDING

A. All Cable Runs

1. Banding cuts cable outer jacket (banding too tight). 1

2.

Banding compressing outer jacket (banding too tight but not cutting jacket).

3.

Plastic tie wraps used in place of banding straps

(metal banding strap required).

4. Cables secured to hanger with bailing wire or rope. 1

5. Bands cut and left in wireway. 2

6. Channel rubber not installed where required. 2

B. Horizontal Cable Runs

1.

Banding not installed at breakout hangers before and after penetrations or at change of direction of wireway.

C. Vertical Cable Runs

1.

No banding or loose banding (banding required on every hanger).

III.

A. Cableways

10 of 11 ITEM NO: 009-73

ITEM CRITERIA CATEGORY

1.

Cable hangers or hardware cutting into the cable jacket.

2.

Improper hanger spacing (Cable hangers are required at least every 32 inches except that hangers for multiple tier overhead aluminum decks must be spaced every 16 inches).

3.

Inadequate cableway support (hangers, hardware, tiers, or cable straps missing) or welds cracked.

4. Overload/Overcrowded cable hangers. 3

5. Maximum no. of tiers exceeded. 3

6. Inadequate fastener length. 3

7.

One-half inch clearance between cable run and hangers above or structure not provided.

IV. EQUIPMENT

A. Covers

1. Junction box or equipment covers loose or missing. 1

B. Mounting

1.

Cable supporting the weight of equipment (power junction boxes, lighting fixtures switch boxes, etc.)

2.

Missing loose or improperly installed mounting hardware on equipment.

C. Cable Entrance

1.

Watertight penetrators not utilized for entrance to watertight equipment enclosures.

2.

Drip loops, drip shields plastic sealer or bottom penetration not utilized for entrance to non-watertight drip proof equipment.

3.

Cable can be moved in and out of tube. Improperly packed or not packed.

4. Nylon tube base loose in enclosure. (O-ring missing) 1

V. DECK/BULKHEAD PENETRATION

A. Non-watertight Deck or Bulkhead Cable Penetration

1.

No plastic sealer around cables through collars where required.

11 of 11 ITEM NO: 009-73

ITEM CRITERIA CATEGORY

2.

Chafing protection not installed at non-watertight deck or bulkhead cableway penetrations.

3. Chafing ring overloaded. 3

4. Inadequate chafing protection and damage evidence. 1

B. Watertight Deck or Bulkhead Cable Penetration

1.

No plastic sealer around cable at stuffing tubes which are exposed to the weather. Note: If plastic sealer is installed at locations other than those exposed to the weather, it is not required to be removed.

2.

Stuffing tube or kickpipe not utilized (cable installed without tube).

3. Unused stuffing tube or kickpipe not plugged. 1

4.

Stuffing tube or kickpipe assembly incomplete

(missing gland nut, packing, or pipe connector).

5. Stuffing tube assembly incorrect (improper packing). 2

6. Stuffing tube or kickpipe too large for size of cable. 3

7. Multiple cables in a single stuffing tube or kickpipe. 2

8.

Stuffing tube or kickpipe damaged to point where complete assembly not possible (cracked welds, damaged threads, out-of-round, etc.) if firestop material is installed.

C. Watertight Deck or Bulkhead Penetrations Utilizing Multiple Cable Penetration

1.

Insert blocks, compression bolts or filler blocks missing.

2.

Improper size blocks used for size cable installed violating watertight integrity.

3.

Incorrect type of RTV used to seal armored cable through MCP blocks.

4. RISE type MCP not properly sealed. 1

009-73_FY23
009-73_FY23_ATTACHMENT_A
009-73_FY23_ATTACHMENT_B

File details come from the government source that posted it. Updated .