Attachment 15 - Delivery Order N6523625FXXXX Performance Based Payment Schedule.docx

DOCX document 25 KB Posted

Attached to
Relocatable Modular Buildings
Solicitation number
N6523625R3800
Issued by

About this file

This document is a Performance Based Payment Schedule for a Navy contract (Delivery Order N6523625FXXXX) for relocatable modular buildings. The payment schedule includes five key milestones: (1) Building Design and Drawings, (2) Fabrication, (3) Delivery and Site Preparation, (4) Modular Installation, and (5) Installation Closeout. Each milestone has specific deliverable requirements and exit criteria, with payment terms to be proposed by the offeror.

A notable contract feature is that 15% of the total price will be withheld until the building passes ICD-705 testing satisfactorily and the Contractor submits the Installation Closeout CDRL A014. The associated solicitation (N6523625R3800) is a 100% small business set-aside for up to eight relocatable modular, prefabricated temporary facilities that are Intelligence Community Directive (ICD) 705 compliant. The solicitation was issued on 3 June 2025, with responses due by 18 June 2025, and is being managed by the Naval Information Warfare Center (NIWC) Atlantic.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 15 – Delivery Order N6523625FXXXX Performance Based Payment Schedule

Payable Milestones

Milestone
Description
Deliverable / Exit Criteria
Due on or before
Payout Schedule
1
Building Design and Drawings
Deliverables:

Complete Final Design and Drawings per specifications (CDRL A004)

Exit Criteria:

Government acceptance of Completed Design

To be proposed
To be proposed
2
Fabrication
Deliverables:

Mid-Point Contractor Site Visit Ready-To-Ship Notification (CDRL A012)

Exit Criteria:

Completion of fabrication, ready to ship to customer

To be proposed
To be proposed
3
Delivery and Site Preparation
Deliverables:

Modular on-site Site Prep complete walk-through with NIWC Atlantic Project Manager (PM) and Facilities Rep, and Contractor PM.

Exit Criteria:

Site Prep complete for installation and modular building on-site ready for installation.

To be proposed
To be proposed
4
Modular Installation
Deliverables:

Inspection Punch List (CDRL A013)

Exit Criteria:

Completed Government Punch List and Government acceptance of completed building.

To be proposed
To be proposed
5
Installation Closeout
Exit Criteria:

Installation Closeout (A014)

To be proposed
To be proposed*
Payment Total*
$

Note* - Offeror shall propose 15% of the total price to be withheld until building passes the ICD-705 testing satisfactorily and Contractor submits Installation Closeout CDRL A014.