This document contains a pre-solicitation notice and related federal contract opportunity. The pre-solicitation notice is to clarify that the upcoming solicitation for the Upgrade Overhead Page and Nurse Call System Design-Build project at the Fort Meade VAMC will use Trade Off source selection procedures. The solicitation is expected to be issued on October 12, 2020 as a Request for Proposal set aside for Service-Disabled Veteran-Owned Small Businesses. The period of performance will be approximately 335 calendar days with a magnitude of construction between $2 million to $5 million. The applicable NAICS code is 236220 with a size standard of $39.5 million. All questions must be submitted in writing to the specified email by the date specified in the forthcoming solicitation.

View the file

Other files

File Type Posted
36E77620R0054 0002.docx DOCX document
P14_Spec01_91_00Commissioning.docx DOCX document
Upgrade Fiber Backbone - 2013.pdf PDF
Updated RFP 36E77620R0054 - 11-24-2020.docx DOCX document
Fiber Optics Nework - 1997.pdf PDF
SignalManholePictures.pdf PDF
SPEC_270800_CommissioningCommunicationsSystems.docx DOCX document
Technical Questions Tracking Spreadsheet - Fort Meade DB - 11-25-20.pdf PDF
36E77620R0054 0001.docx DOCX document
Attachment 15 - Construction Wage Rates - Meade County - 05-01-2020.pdf PDF
Attachment 7 - Spec 01 45 29 Testing - 07-10-2020.pdf PDF
Attachment 4 - Spec 01 33 23 Shop Drawings - 07-10-2020.pdf PDF
Attachment 12 - 157-166 Telecom.pdf PDF
Attachment 18 - SECURITY REQUIREMENTS.pdf PDF
Attachment 14 - T296.pdf PDF
Attachment 9 - 130026 VA FtMeade As-Builts.pdf PDF
Attachment 10 - DRAWINGS May 2018 - SPS_ENDO - REVISED FINAL.pdf PDF
Attachment 5 - Spec 01 35 26 Safety Requirements - 07-10-2020.pdf PDF
Attachment 2 - Spec 01-00-00 General Requirements - 08-13-2020.pdf PDF
Attachment 16 - Labor Wage Rates - Meade County - 06-30-2020.pdf PDF
Attachment 13 - CAI 2019 Hospital Complex 8-29-2019.pdf PDF
Attachment 1 - Final SOW - Upgrade Overhead Page Nurse Call System - 08-13-2020.pdf PDF
Attachment 6 - Spec 01 45 00 Quality Control - 07-10-2020.pdf PDF
Attachment 8 - 113_Inpatient_MaxBeds_Plan.pdf PDF
Attachment 3 - Spec 01 32 16.16 Project Schedule 07-09-2020.pdf PDF
36E77620R0054_2.docx DOCX document
Attachment 17 - CONTRACTOR SAFETY AND ENV RECORD EVAL FORM.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A

Pre-Construction Risk Assessment Project Title:

Project Location:

Project Coordinator:

Assessment Date: Planned Start Date

Safety/Life Safety Risk Assessment - Safety Officer should be involved in the design/planning of all projects

Y N CONSTRUCTION ACTIVITY If NO, indicate ILSM from below list or describe other intervention

Will exit egress routes from occupied areas remain unchanged?

Will exit stairs remain unobstructed & fire separated?

Will fire & smoke compartments remain intact & unchanged?

Will fire alarm detection systems remain functional & unimpaired?

Will fire suppression systems remain functional & unimpaired?

Will construction area be separated by non-combustible smoke tight partitions?

Will access to emergency department remain unobstructed?

Will emergency access by fire department remain unobstructed?

Will the construction area have two remote exits?

Y N CONSTRUCTION ACTIVITY If YES, indicate ILSM from below list or describe other intervention

Will there be excessive distance to exit?

Will there be impacts to the environment (GEMS concerns)? Hazardous areas unprotected, hazardous waste generated, etc.

Will there be any anticipated utility shutdowns? (Communications, electrical, heating/cooling, HVAC, medical gases, vacuum, water, server) Will there be unusual noise levels for adjacent areas?

Will vibration levels be excessive for hospital machinery to operate properly?

Will there be conflicts with emergency disaster plan?

Will the construction compromise security?

Fire/Safety Officer Signature: Safety/Life Safety Additional Requirements and Comments:

Interim Life Safety Measures (IlSM) A. Ensure Egress B. Emergency Forces Access C. Fire Department Notification D. Ensuring Operational Life Safety Systems E. Temporary Construction

F. Additional Fire Fighting Equipment G. Control Combustible Loading H. Conduct 2 Fire Drills Per Shift in All Areas I. Conduct 2 Fire Drills Per Shift in Local Area J. Increase Hazard Surveillance

K. Compartmentation Training of Personnel L. Conduct Organization Training on Life Safety M. Conduct Additional Training on Incident

Response N. Institute a Fire Watch for Sprinkler Shutdown

Patient Safety Risk Assessment

Y N CONSTRUCTION ACTIVITY

Does this project involve a patient care area?

Is this project adjacent to a patient care area?

Will this project alter patient access/egress to/from the building/patient care area, either temporarily or permanently?

If any are YES, involve the patient safety manager in design/planning, especially with regard to the following items:

Access/ Egress

1. The new/temporary access/egress path should be intuitive, i.e.easy to follow.

2. Signage should be adequate for decreased visual acuity and at appropriate viewing levels for both ambulating and w/c bound patients/ visitors.

3. The access/egress path should be smooth, without tripping hazards.

4. The access/egress path should be handicap accessible.

5. For applicable clinical areas, the construction barriers prevent unauthorized patient egress.

Hazardous Areas/ Materials

1. Hazardous areas should not be accessible by patients/visitors.

2. Signage for hazardous areas should be visually adequate (see above).

3. Hazardous chemicals and tools should be stored appropriately to preclude patient/visitor access.

Critical Alarms

Critical clinical alarms should be functional and audible within and adjacent to the construction zone, including but not limited to:

a. Emergency Code Systems

b. Medical Gas alarms (Oxygen, Air, Suction)

c. Wander Guard Technology

d. Cardiac and other Vital Sign Monitoring Systems

e. Medication/Nutrition Delivery Systems

f. Nurse Call Systems

Patient Safety Officer Signature: Patient Safety Additional Requirements/Comments:

(Qtr/FY):

Attachment A

Infection Control Risk Assessment (Match construction activity to patient risk group to determine project class)

CONSTRUCTION ACTIVITY TYPE PATIENT RISK GROUP

A: Inspection, non-invasive activity-includes, not limited to removal of ceiling tiles for inspection (1/50 sq ft), painting (not sanding), wall covering, electrical trim work, minor plumbing, activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.

Low Risk- (Office Areas)

B: Small scale, short duration, moderate to high levels-includes but not limited to installation of telephone/computer cabling, access to chase spaces, cutting of walls or ceiling where dust migration can be controlled.

Medium Risk- (Cardiology, ECHO, Endoscopy, Nuclear Medicine, Physical Therapy, Radiology/MRI, Respiratory Therapy)

C: Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies. Includes but not limited to sanding of walls for painting or wall covering; removal of floor coverings, ceiling tiles, and casework; new wall construction; minor duct work or electrical work above the ceilings; major cabling activity; any activity which cannot be completed in a single work shift.

High Risk- (CCU, ER, Labor & Delivery, Laboratories (specimen), Newborn Nursery, Outpatient Surgery, Pediatrics, Pharmacy, Post Anesthesia care, Surgical Units)

D: Major duration and construction activities-Includes, but not limited to:

activities that require consecutive work shifts; requires heavy demolition or removal of a complete cabling system; new construction.

Highest Risk- (Any area caring for Immunocompromised patients, Burn Unit, Cardiac Cath Lab, Central Sterile Supply, ICU, Medical Unit, Negative pressure isolation rooms, Oncology, Operating rooms including C-section)

Project Class

Patient Risk Group TYPE A TYPE B TYPE C TYPE D LOW Risk I II II III/IV MEDIUM Risk I II III IV HIGH Risk I II III/IV IV HIGHEST Risk II III/IV III/IV IV

During Construction Project Upon Completion of Project

CLASS I 1. Execute work by methods to minimize raising dust from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

CLASS II

1. Include all items from Class I above

2. Provides active means to prevent air-borne dust from dispersing into atmosphere

3. Water mist work surfaces to control dust while cutting.

4. Seal unused doors with duct tape.

5. Block off and seal air vents.

6. Place dust mat at access points of work area.

7. Contain construction waste before transport in tightly covered containers.

8. Isolate HVAC system in areas where work is being performed to prevent contamination of duct system.

1. Wipe surfaces with disinfectant.

2. Contain construction waste before transport in tightly covered containers.

3. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.

4. Remove isolation of HVAC system in areas where work is being performed.

CLASS III

1. Include all items from Class I/II above

2. Involve infection control in design/planning before construction begins.

3. Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.

4. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.

5. Cover transport receptacles or carts. Tape covering unless solid lid.

1. Include all items from Class I/II above

2. Do not remove barriers from work area until completed project is thoroughly cleaned as required by the owner’s Safety Department and/or Infection Control Department.

3. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

4. Vacuum work area with HEPA filtered vacuums.

5. Wet mop area with disinfectant

CLASS IV

1. Include all items from Class I/II/III above

2. Involve infection control in design/planning before construction begins.

3. Seal holes, pipes, conduits, and punctures appropriately.

4. If exiting to a patient care area, construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time they leave the work site.

5. Walk-off mats are recommended to minimize tracking of heavy dirt and dust from construction areas. Shoe covers may be considered in certain areas.

1. Include all items from Class I/II/III above

Infection Control Officer Signature:

NOTES:

NO YES Is there a risk to the Contractor of T.B. exposure?

Infection Control Additional Requirements/Comments:

PROJECT CLASS:

Project Title:
Project Location:
Project Coordinator:
Assessment Date:
Planned Start Date QtrFY:
If NO indicate ILSM from below list or describe other interventionWill fire smoke compartments remain intact unchanged:
If NO indicate ILSM from below list or describe other interventionWill fire alarm detection systems remain functional unimpaired:
If NO indicate ILSM from below list or describe other interventionWill fire suppression systems remain functional unimpaired:
If NO indicate ILSM from below list or describe other interventionWill construction area be separated by noncombustible smoke tight partitions:
If NO indicate ILSM from below list or describe other interventionWill access to emergency department remain unobstructed:
If NO indicate ILSM from below list or describe other interventionWill emergency access by fire department remain unobstructed:
If NO indicate ILSM from below list or describe other interventionWill the construction area have two remote exits:
If YES indicate ILSM from below list or describe other interventionWill there be excessive distance to exit:
If YES indicate ILSM from below list or describe other interventionWill there be impacts to the environment GEMS concerns Hazardous areas unprotected hazardous waste generated etc:
If YES indicate ILSM from below list or describe other interventionWill there be any anticipated utility shutdowns Communications electrical heatingcooling HVAC medical gases vacuum water server:
If YES indicate ILSM from below list or describe other interventionWill there be unusual noise levels for adjacent areas:
If YES indicate ILSM from below list or describe other interventionWill vibration levels be excessive for hospital machinery to operate properly:
If YES indicate ILSM from below list or describe other interventionWill there be conflicts with emergency disaster plan:
If YES indicate ILSM from below list or describe other interventionWill the construction compromise security:
SafetyLife Safety Additional Requirements and Comments:
Patient Safety Additional RequirementsComments:
Infection Control Additional RequirementsComments:
If NO indicate ILSM from below list or describe other interventionWill exit stairs remain unobstructed fire separated:
If NO indicate ILSM from below list or describe other interventionWill exit egress routes from occupied areas remain unchanged:
Group1: Off
Group10: Off
Group11: Off
Group12: Off
Group13: Off
Group14: Off
Group15: Off
Group16: Off
P1: Off
P2: Off
P3: Off
TB: Off
Dropdown5: [<SELECT>]
Group2: Off
Group3: Off
Group4: Off
Group5: Off
Group6: Off
Group7: Off
Group8: Off
Group9: Off
Clear:
Risk Group: Off
Activity: Off
Notes: