Attachment_10_IA_C713_Progress_Report.pdf
PDF 125 KB Posted
- Attached to
- Sports Complex FY24- Jeehdeez'a Elementary School Federal contract opportunity
- Solicitation number
- 140A2324R0022
About this file
This document is a Contract Progress Report for a Department of the Interior, Indian Affairs contract. The report covers the progress made during a specified reporting period, providing details on work elements, percentage of work completed, and remarks. The report contains a certification of satisfactory completion of the indicated percentage of the contract per specifications, and requires approval by the Contracting Officer. This report may be used by the Contracting Officer to compute progress payments, according to the contract's payment clause.
The related federal contract opportunity is for the construction of a Sports Complex at the Jeehdeez'a Elementary School, solicited by the Department of the Interior Bureau of Indian Affairs Bureau of Indian Education. The solicitation number is 140A2324R0022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140A2324R0022_Amd_0001.pdf | ||
| Attachment_2_AZ20240027_(Wage_Determination).pdf | ||
| Sol_140A2324R0022.pdf | ||
| Attachment_8_IA_Form_3000_Material_Approval_Submittal.pdf | ||
| Attachment_11_SF1413_Statement_and_Acknowledgement.pdf | ||
| Attachment_3_RFP_Questions_and_Answers_Log.xlsx | XLSX spreadsheet | |
| Attachment_1_Statement_of_Work_(SOW)_Jeehdeeza_FY24.pdf | ||
| Attachment_6_SF-_25A_Payment_Bond_Form.pdf | ||
| Attachment_4_SF24_Bid_Bond.pdf | ||
| Attachment_5_SF25_Performance_Bond.pdf | ||
| Attachment_7_Federal_Health_and_Safety_Codes_and_Standards_BIA_Office_of_Facilities_Management_and_Construction.pdf | ||
| Attachment_9_IA_C113_Progress_Schedule.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of the Interior, Indian Affairs
CONTRACT PROGRESS REPORT
CONTRACTOR ADDRESS
REPORT NO. PERIOD COVERED
FROM: TO:
PROJECT NO. CONTRACT NO. COMPLETION DATE
LINE
NO.
WORK ELEMENT % OF
TOTAL
% COMPLETED
THIS PERIOD
% COMPLETED
CUMULATIVE
TOTAL
REMARKS
At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be used for computing progress payments.
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.
SUBMITTED BY: _________________________
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
REVIEWED BY OR FOR CONTRACTING OFFICER
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
FORM IA-C713
Have payrolls been submitted for this time period? YES / NO
File details come from the government source that posted it. Updated .