Attachment 1 Statement of Work_NLZG222005_05.30.2023.docx

DOCX document 33 KB Posted

Attached to
OH ANG Rickenbacker Outbound Gate Repair
Solicitation number
W50S8P-23-B-0003
Issued by

About this file

This statement of work outlines requirements for two construction projects at Rickenbacker Air National Guard Base in Ohio. The projects include resetting the existing gate motor drive base at the main gate and installing a new foundation for spike strips in the outbound lane at the security checkpoint. The contractor must disconnect and remove the existing gate operator and pedestal, excavate and replace the subgrade with crushed aggregate, and reconnect all mechanical and electrical components to reset the gate drive base. For the spike strip installation, the contractor must saw cut and remove pavement and subgrade for the new foundation, install required conduit and power feeds, and construct the foundation with specified backfill, rebar and concrete. The contractor must submit safety documentation, hazardous material inventories, and waste tracking information. Bids must separate pricing for the two contract line items. The selected contractor will coordinate with the 121st Civil Engineering Squadron and adhere to all OSHA and hazardous material requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project # NLZG222005 Outbound Gate Rework

STATEMENT OF WORK

Outbound Gate Rework

1.01 SCOPE: Reset existing Gate Motor Drive Base at Main Gate and install new foundation for Spike Strips in the Outbound Lane at the Security Checkpoint

1.02 LOCATION: Rickenbacker ANGB. Main Gate Area.

1.03 COORDINATION: Notify 121st Civil Engineering at 614-492-4121 or contact Mr. Michael Hissom at (614) 492-4459 a minimum of two days prior to starting any work. Coordination with the 121st CES is mandatory.

1.04 SUBMITTALS:

A. Quote must contain an itemized list for labor, parts, materials, equipment rental and any other incidental expenses.

B. Contractor shall provide a detailed schedule of construction for this project.

C. Contractor shall include with their proposal what GREEN Procurement (Re-Cycled-Bio Based Content) items which they intend to use on the contract (if applicable).

The following web sites should be reviewed for materials which can be used in the Governments Green Procurement effort.

Information on Recycled content requirements: www.epa.gov/cpg (Check under Products/Construction Material) Information on Bio based program: www.biobased.oce.usda.gov

D. The following items must be submitted by the Contractor after award at the Pre-Construction Conference:

1. Contractor will provide SDS Sheets for all: concrete, glues, sealants, solvents, additives, cleaners, and fuels to be used. All other substances of a flammable, corrosive and toxic nature shall be submitted as well.

2. Contractor will ensure that each of the aforementioned SDS items are listed on a Transient Organization Hazardous Material Inventory Sheet and submitted for approval prior to starting work.

3. To be turned in upon completion of work. Contractor will fill out a Solid Waste Disposal Spreadsheet, which tracks construction debris that goes to dump sites or that is recycled. (When applicable). The intent is to capture quantities and costs.

1.05 WORK TO BE ACCOMPLISHED:

1. Background:

a. The Motor Drive for the Main Gate is currently inoperative due to the support base sinking and knocking the Drive out of alignment. Security Forces has also requested the installation of Spike Strips in the outbound lane to meet current Doctrinal requirements.

2. Requirements: The contractor shall:

i. Main Gate Drive Pad Reset:

1. Disconnect (electrically and mechanically) and remove gate operator and concrete pedestal to facilitate subbase repairs.

2. Store gate opener and pedestal for reuse and reinstallation by contractor.

3. Excavate existing subgrade to facilitate placement of 4” of crushed aggregate.

4. Compact existing subgrade and place 4” of crushed aggregate.

5. Reinstall pedestal and Gate Opener. Verify base course and gate opener/pedestal at proper height and level.

6. Contractor will reconnect the gate operator, including all mechanical and electrical connections, and verify correct operation.

ii. Spike Strip Installation

1. Contractor shall saw-cut and remove existing pavement and subgrade for new spike strip base.

2. Contractor is responsible for maintaining site barricading, cleanliness, and runoff protection.

3. Contractor will install all required conduit, embedded power, and control feeds for the spike strip system.

4. Contractor shall install new foundations including specified backfill, rebar and concrete. Contractor will perform all required compaction tests and take prescribed number of concrete test cylinders, test at 7,14-, & 30-day intervals and report results to the Base Civil Engineer.

1.06 BID SCHEDULE: Bids shall be submitted with the price broken out in two contract line numbers. (CLIN).

CLIN 0001: Main Gate Opener Base Replacement CLIN 0002: Installation of Spike Strips in the Outbound Lane.

1.07 SAFETY: All precautions necessary to ensure the safety of personnel and the protection of existing equipment and structures will be strictly enforced. All additional electrical safety precautions shall be followed. All OSHA standards shall be met.

1.08 CONSTRUCTION DIRT AND DEBRIS: The contractor shall remove any dirt, debris, construction waste that collects during construction on the traveled roadways or existing pedestrian facilities on the base as directed by the Base Civil Engineer.

1.09 CONSTRUCTION STAGING OF EQUIPMENT: The contractor shall coordinate with the Base Civil Engineer appropriate locations for overnight storage/staging of construction equipment.

1.010 HAZARDOUS MATERIALS REQUIREMENTS:

HAZMAT shall not be stored on base unless with written permission from contracting officer and HMP. When Hazardous Material (HM) is to be stored for use on Rickenbacker ANGB, the contractor shall establish a hazardous material storage and distribution system that complies with all Federal, State, and Local environmental regulations.

The contractor shall register through the Contracting Officer with the base Hazardous Material Pharmacy (HMP) prior to start of work.

The contractor shall submit to the Contracting Officer for approval the following for all HM, as defined by Federal Standard 313 Table I and Table II, to be used in the accomplishment of the work / service to be provided to the government: See paragraph 1.04 Submittals.

1.011 SITE CONDITIONS: Submission of a proposal by a contractor shall be considered evidence that the contractor has examined the statement of work and is satisfied as to the nature and location of the work and all matters, which can in any way affect the work or the cost of the work under the proposal. Any failure of the contractor to become acquainted with all available information, including a physical survey of the site for the proposed work will not relieve the contractor from successfully fulfilling all work that is required for a complete and acceptable job.