Attachment_1_-Statement_of_Work_-_Doty_State_Fence.pdf
PDF 829 KB Posted
- Attached to
- BLM WY - DOTY STATE FENCE - RAWLINS FEILD OFFICE Federal contract opportunity
- Solicitation number
- 140L6224Q0045
About this file
This document is a Statement of Work for the Doty State Fence project located in Carbon County, Wyoming. The proposed work includes the removal of approximately 16,368 linear feet of existing fence and the installation of new wildlife-friendly four-strand wire fence, a section of all-wood set post fence with a wood top rail and wire, and a riparian exclosure section with wood posts and woven wire. The new fence construction is to be provided by the awardee.
The project location is accessible via Wyoming Highway 789 and County Road 608. A pre-bid site tour is scheduled, but optional. The contract requires the removal and disposal of the existing fence materials. No blading is allowed, and vegetation along the fence line may only be cut, not removed. The work is to be inspected by the Contracting Officer's Representative before acceptance. Payment will be made based on the linear feet of fence constructed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L6224Q0045_Amd_0001.pdf | ||
| Prebid_site_tour_sheet_0001.pdf | ||
| Attachment_2-_Updated_Bid_Schedule_-Doty_State_Fence_0001.xlsx | XLSX spreadsheet | |
| SOW_Doty_Fence_Final_JLC_0001.pdf | ||
| Attachment_8-__Limitations_on_Subcontracting_Breakout.pdf | ||
| Attachment_6-_Photos.pdf | ||
| Attachment_7-_SF_1442_Completion_Instructions.pdf | ||
| Attachment_5_-Wage_Determination_WY20240037.pdf | ||
| Sol_140L6224Q0045.pdf | ||
| Attachment_2-_Bid_Schedule_-Doty_State_Fence_.xlsx | XLSX spreadsheet | |
| Attachment_3_-Project_Notes.pdf | ||
| Attachment_4_-Maps_Doty_State_Fence.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work:
Doty State Fence 2024
Introduction The Doty State Fence project is located within Carbon County, WY. The proposed work includes the removal of an estimated 16,500Liner Feet of existing fence and replacing it with new construction and like materials; all to be provided by the awardee.
New fence construction will consist of 3 different construction Styles of fencing on a continuous line.
Fence Style 1 is approximately 14,000 Liner Feet (LF) of wildlife friendly four strand wire fence (3 barbed wires and 1 smooth bottom wire) with wood line posts (every third line post) with approximately (6) 3-post corners, (18) h-braces, (4) 16-foot wire gates, and (2) 8-foot meatal pipe gates.
Fence Style 2 is approximately 1,000 Liner Feet protecting (riparian exclosure) and will require all wood set pots at 12 ft spacing with a 16 ft wood top rail (attached with 9” long x 0.5” diameter Zinc coated lag bolts and washers) and 39” woven wire (field fence) stretched below, with approximately (4 H-braces).
Fence Style 3 is approximately 1,500 Liner Feet of all wood set post with a 16’ wood top rail (attached using lag bolts w/ washers) and 3 wires (2 stands of barbed wire and single strand of smooth wire) spaced below the wood rails with approximately (2 end panels).
Project Location From Creston (the junction of WY HWY 789 and I-80), travel South on 789 (towards Baggs, WY) for approximately 28.5 miles. At the junction of WY HWY 789 and County Rd 608 (Wild Cow Rd) and County Rd 701 head east. Travel East then Southeast on County 3308 (Wild Cow Rd) for approximately 5.89 miles to the junction of County Rd 608 (Wild Cow Rd) and BLM Road 3305 (Willows Rd). Travel East then Northeast on BLM 3305 for approximately 8.25 miles to the South fence line of the project area.
T.17N R.91.W Sec. 24 and 13.
See Project Maps
Pre-Bid Tour A pre-bid tour of the project site will be scheduled, with agency personal. Attendance of the pre-bid tour is optional, but highly recommend, to ensure a reasonable understanding of the scope of work and work site conditions.
2024 RAWLINS FIELD OFFICE – DOTY STATE FENCE PROJECT - SOW - 1
2024 RAWLINS FIELD OFFICE – DOTY STATE FENCE PROJECT - SOW - 3
DOTY STATE FENCE PROJECT MAP
Doty State Fence 2024 STATEMENT OF WORK
SOW - 1
Statement of Work:
Doty State Fence 2024
Introduction
The Doty State Fence project is located within Carbon County, WY. The proposed work includes the removal of an estimated 3.1 miles / 16,368 Liner Feet (gps’d) of existing fence and replacing it with new construction and like materials; all to be provided by the awardee. Much of the fence route will require mowing or mastication (no blading) for the purpose of vegetation removal prior to new fence construction. New fence construction will consist of approximately 14,000
Liner Feet (LF) of wildlife friendly four strand wire fence (3 barbed wires and 1 smooth bottom wire) with wood line posts (every fourth line post) along identified sections. Construction will also include a section of fence 1500’ Liner Feet (LF) of all wood set post with a 16’ wood top rail (attached using lag bolts w/ washers) and 3 wires (2 stands of barbed wire and single strand of smooth wire) spaced below the wood rails. An additional 875’ Liner Feet (LF) section
(riparian exclosure) will require all wood set pots at 12 ft spacing with a 16 ft wood top rail
(attached with lag bolts and washers) and 39” woven wire (field fence) stretched below. General fence construction will be a standard wildlife friendly steel fence construction with treated wood materials utilized for all set posts, H-braces, cross posts, stress panels and fence corner construction. The fence is accessible via Wyoming Hwy 789 and County Road 608 (Wild Cow
Road). Then turning north on BLM 3305 (Willows Road). Travel North six (8.25) miles on
BLM 3305 to the project site located on the boundary line of BLM and Wyoming State Trust
Land ownership.
Project Location
From Creston (the junction of WY HWY 789 and I-80), travel South on 789 (towards Baggs, WY) approximately 28.5 miles to Dad, the junction of WY HWY 789, County Rd 608 (Wild
Cow Rd) and County Rd 701 (Wamsutter-Dad Rod). Travel East then Southeast on County 3308
(Wild Cow Rd) for approximately 5.89 miles to the junction of County Rd 608 (Wild Cow Rd) and BLM Road 3305 (Willows Rd). Travel East then Northeast on BLM 3305 for approximately
8.25 miles to the South fence line of the project area.
The general project area runs East to West and then North along the section lines within
T.17N R.9.W Sec. 24 and 13.
See Project Maps
Pre-Bid Tour
A pre-bid tour of the project site will be scheduled, with agency personal. Attendance of the pre-bid tour is optional, but highly recommend, to ensure a reasonable understanding of the scope of work and work site conditions.
Deliverables
Doty State Fence 2024 STATEMENT OF WORK
SOW - 2
Bids will be accepted based on bid schedule attached. All work shall follow specifications and drawings.
Project Contacts
TBD
mailto:mmurry@blm.gov mailto:askordas@blm.gov
Doty State Fence 2024 GENERAL INFORMATION AND REQUIREMENTS
01009 - 1
SECTION 01009
GENERAL INFORMATION AND REQUIREMENTS
PART 1: GENERAL
1.1 SUMMARY:
A. Description of Work: Furnishing material, labor, and equipment, to remove old and construct new, approximately 14,000 Linear Feet (LF) of wildlife friendly four strand wire fence (3 barbed wires and 1 smooth bottom wire) with wood line posts (every fourth line post) along identified sections.
Construction will also include a section of fence 1500’ Liner Feet (LF) of all wood set post at 12 ft spacing with a 16’ wood top rail (attached utilizing lag bolts and washers) and 3 wires (2 stands of barbed wire and a single strand of smooth wire) placed below the wood rails. An additional 875’
Liner Foot (LF) section (riparian exclosure) will require all wood set pots at 12 ft spacing with a 16’ wood top rail (attached with lag bolts and washers) and 36” woven wire (field fence) stretched below.
B. Location: Work under this Contract is in Carbon County, Wyoming. Work locations are shown on the maps.
C. Work Data Sheet: Designates the type and quantity of work required at the project location, and dimensions required for typical drawings.
D. Debris: Debris consisting of wood posts, poles, steel posts, and wire shall become the property of the Contractor and shall be removed from the work site. The Contractor shall be responsible for disposal of construction debris in a legal manner, and for payment of any fees required. Burning of debris is not permitted on any federal or state owned property.
1.2 REFERENCES
A. Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/ standards referred to herein may be procured by the Contractor, from the following:
ALSC American Lumber Standards Committee
PO Box 210
Germantown, MD 20875
ANSI American National Standards Institute
11 W 42nd St.
New York, NY 10036
AWPA American Wood Preservers' Association
P.O. Box 286
Woodstock MD 21163
AWPA C 1-95 All Timber Products, Pressure Treatment
AWPA C 5-95 Fence Posts, Pressure Treatment
AWPA M 4-95 Care of Pressure Treated Wood Products
AWPA P 5-95 Waterborne Preservatives
AWPA P 8-95 Oil-Borne Preservatives
AWPA P 9-92 Solvents for Organic Preservative Systems
01009 - 2
CFR Code of Federal Regulations (Available from the Government Printing Office)
N. Capitol St. between G and H St., NW
Washington, DC 20402
FS Federal Standard
General Services Administration
Specifications Branch
Room 6039, GSA Building
7th and D Streets, S.W.
Washington, DC 20407
GSA General Services Administration
F St. and 18th St., NW
Washington, DC 20405
OSHA Occupational Safety and Health Administration
US Department of Labor
200 Constitution Ave., NW
Washington DC 20210
OSHA 2207-91 Construction Industry
WWPA Western Wood Products Association
522 SW 5th Avenue, Yeon Bldg
Portland, OR 97204-2122
1.3 SUBMITTALS
(There are no applicable requirements)
1.4 DELIVERY, STORAGE, AND HANDLING:
A. Delivery: The Contractor shall protect products incorporated into the work from damage while in transit to the site.
B. Storage: The Contractor shall provide temporary storage facilities for products. Storage shall comply with the manufacturer’s instructions. The storage area shall permit access for inspection and handling.
C. Handling: The Contractor shall load and unload products in such a manner that protects them from damage.
1.5 QUALITY ASSURANCE:
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference with the same force and effect as when they were given in full text.
B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
1.6 PROJECT/SITE CONDITIONS:
A. Access to the Work:
01009 - 3
1. The work locations are shown on the drawings.
2. Access to the work shall be provided by and at the Contractors expense. No roads shall be constructed by the Contractor or off road driving permitted without prior written permission from the Contracting Officer.
3. Contractor shall exercise care to prevent unnecessary surface disturbance to existing grass, vegetation, and to existing roads and two-tracks.
4. Public, State, or private access roads damaged by the Contractor shall be restored, at the
Contractor’s expense, to the same condition they were in at the commencement of work.
B. Environmental Considerations:
1. No blading will be allowed.
2. Avoid disturbing all corner markers or monuments marking section lines along the fence line.
3. The contractor is responsible for doing a utility One-Call for safety. Tickets may be entered at: https://www.onecallofwyoming.com/
1.7 SEQUENCING AND SCHEDULING:
A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, the
Contractor shall submit an updated schedule within three calendar days. As a minimum, the estimated start and completion dates shall be shown in the schedule.
PART 2: PRODUCTS
(There are no applicable requirements.)
PART 3: EXECUTION
3.1 PROJECT MEETINGS:
A. Pre-Work Conference:
1. A pre-work conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.
3. The Contractor shall be prepared to summarize and explain procedures planned for the project.
B. Progress Meetings:
1. Meetings shall be held at the project site, or as determined by the Contracting Officer.
2. Meetings may be called by either the Contracting Officer or the Contractor. Request shall state who should attend and include an agenda.
https://www.onecallofwyoming.com/
01009 - 4
C. Final Inspection:
1. Meeting shall be held at the project site, or as determined by the Contracting Officer.
2. The Contractor shall notify the Contracting Officer in writing at least 3 working days before the completion date so the Government can schedule final inspection.
3. The Contractor shall require the superintendent to be present during this inspection.
3.2 PREPARATION
A. Work Limits and Control Points: Will be established by the Contracting Officer.
3.3 SALVAGEABLE ITEMS
A. Requirements: Salvaged items consisting of wire and wood shall become the property of the
Contractor and shall be disposed of properly. Fence staples and clips shall be disposed of by the contractor. All steel t-posts removed and remaining in good condition will remain the property of the Federal Government Rawlins BLM Field Office. These t-posts will be neatly piled in location at either end of the project site.
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT:
A. Units: Work described in this section will not be measured for payment.
4.2 BASIS OF PAYMENT:
A. Payment: No direct payment for the work described under this section will be made. The
Contractor shall include consideration for this item in the bid price for other items of the Contract.
END OF SECTION 01009
SECTION 01505
MOBILIZATION
Doty State Fence 2024 MOBILIZATION
01505 - 1
1.1 SUMMARY:
A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies, and incidentals to the project site; and for other work and operations which must be performed, or costs incurred prior to beginning work on the various items on the project site.
4.1 METHOD OF MEASUREMENT:
A. Units: Progress payments will be made as follows:
1. When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.
2. When 10% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 10% of the original Contract amount, whichever is lesser, will be paid.
4.2 BASIS OF PAYMENT:
Payment: Prices and payment will be full compensation for the work described in this section.
Payment will be made under:
Pay Item Pay Unit
Mobilization Lump Sum
END OF SECTION 01505
Doty State Fence 2024 WIRE FENCES AND GATES
02824 - 1
SECTION 02824
WIRE FENCES AND GATES
1.1 SUMMARY
A. Section Includes: Installing barbed wire, steel posts, double h-braces, and stress panels.
Remove existing wire fence and dispose of properly.
B. Related Sections:
General Information and Requirements Section 01009
1.2 SUBMITTALS
A. General: Submittals shall be according to Section 01009 - General Information and
Requirements.
1.3 QUALITY ASSURANCE
A. General: Contractor – All work will be inspected by the Contracting Officer’s
Representative before acceptance.
2.1 CONTRACTOR - FURNISHED MATERIALS
A. All building supplies and materials will be furnished by the Contractor including labor and equipment to install the fences.
3.1 PREPARATION
A. Clearing: No blading will be allowed. Cutting (i.e., mowing, chain sawing) of vegetation, along the established fence line route, shall be allowed. Dispose of cut and mowed brush by scattering it evenly adjacent to the fence line.
3.2 INSTALLATION
A. General:
02824 - 2
1. Steel posts shall not be used for end-panel, corner-panel, gate-panel, or stress-panel posts.
2. When treated posts must be bored or cut during construction, thoroughly swab untreated surfaces with copper naphthenate.
B. Driving Posts:
1. Wood Posts: Driving wood posts (set posts and line posts) shall be allowed.
2. Steel Posts: Drive into the ground to the depth shown on the drawings or until the anchor plate is slightly below the ground surface. Posts shall be driven plumb.
When rock formations prevent driving, remove anchor plate and excavate or drill holes a minimum of 18-inches deep and slightly larger than the diameter of the post. Place posts in the holes and grout the post solidly in position.
C. Setting Posts (set posts and line posts):
Dig holes or tamp/pound/drive wood posts to the depth as shown on the Work Data
Sheet. Set posts plumb and to the spacing and grades as shown on the drawings, unless staked otherwise. Space posts within 6-inches of the dimension shown on the drawings or specified on the Work Data Sheet. Holes shall provide adequate open space around the post so backfill can be tamped the full depth around the post. Backfill with soil gradually and uniformly around each post. Holes shall be backfilled firmly, from the bottom of the hole to the top of ground surface.
D. Corner Post, Gate Post, Corner Panel, Brace, End Panel, and Stress Panel Assemblies:
Construct as shown on the drawings or as staked in the field. Rock jacks shall not be substituted for these items. Construct stress panels on crests of hills, and a maximum of
1320 feet center-to-center for barbed wire sections. In addition, stress panels are required at points between which wire is to be stretched. Construct end panels at the end of fence runs unless shown otherwise on the drawings.
E. Wire: Stretch tightly and staple to wood posts or securely attach to steel posts with standard wire clips. Wire is properly stretched when it is springy to the touch. Drive staples crosswise with the grain of the wood. The wire shall be free to move through the staples as it expands and contracts. Terminate wire at each end post, gate post, corner post, or stress panel. Wrap wire around the post two times and tie off by wrapping around the incoming wire a minimum of four times.
F. Brace Wire: Twist tight with a lever. Leave one end of the lever long enough to fasten behind the horizontal brace to prevent wire from unwinding.
02824 - 3
1. The lever shall be a straight ridged rod, consisting of dimension wood ripped and cut to length or a minimum #4 rebar cut to length.
2. Bracing wire(s) shall be double wrapped/looped. This includes two full wraps/loops of wire around both set posts prior to twisting/tightening with the lever.
G. Spiking: For spikes larger than 40d, predrilled lead holes shall be used. The hole diameter shall be 3/4 the diameter of the spike and drilled to a depth no greater than 1/2 the length of the spike.
H. Minor Drainage Crossings: Additional steel posts shall be set at the top and bottom of breaks or the centerline of the drainage depending on the size and shape of the drainages. Additional wire shall start and end from the main fence. Shall be in locations staked in the field or as directed by the Contracting Officer.
I. Fence Stays: Wood fence stays are required in this Contract.
4.1 METHOD OF MEASUREMENT
A. Units: The work described in this section will be measured and paid for by the job, each section, for fence constructed.
B. No direct payment will be made for drainage crossings or dead-men. The Contractor shall include consideration for these items in the bid price for other items of the contract.
C. Fence removal will be measured and paid for as incidental under this Section 02824.
4.2 BASIS OF PAYMENT
A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Fence Construction Linear Foot
END OF SECTION
Doty State Fence 2024 FENCE-DRAINAGE CROSSINGS
02826 - 1
SECTION 02826
FENCE-DRAINAGE CROSSINGS
A. Section Includes: Furnishing and installing drainage crossings at the locations shown on the drawings, or as staked in the field.
1.1 PROJECT/SITE CONDITIONS
A. Requirements: Access roads shall not be constructed along fence lines and to the construction site unless written approval is granted by the Contracting Officer. Cross country travel with wheeled or tracked vehicles shall be only to and along fence lines.
2.1 MATERIALS
A. Wire Fence Materials: Shall be according to Section 02824 - Wire Fences and Gates and as shown on the drawings.
3.1 PREPARATION
A. Clearing: Only vegetation that interferes with the fence, or immediately adjacent to the fence route (restricting travel along its route) shall be removed. All debris shall be disposed of in the immediate vicinity.
3.2 INSTALLATION
A. Type A: Construct Type A drainage crossings as shown on the drawings, with an auxiliary fence of wire, rock weights, and posts constructed under and independent of the main fence, so that when the crossing washes out, the main fence will not be damaged.
A. Units: The work described in this section will be measured and paid for as part of the fence and not a separate unit.
Doty State Fence 2024 FENCE-DRAINAGE CROSSINGS
02826 - 2
Fence Construction Linear Foot
END OF SECTION
Doty State Fence 2024 FENCE REMOVAL
02827 - 1
SECTION 02827
FENCE REMOVAL
A. Section Includes:
1. Removing (est. 16.368 Liner Feet): of miscellaneous 3&4-wire fence, wood rail / woven wire (field fence) and wood rail with 3 wire stands strands. To include all existing gates, set post and line posts.
B. Requirements: Access roads shall not be constructed along fence lines or to the jobsite unless written approval is granted by the Contracting Officer. Cross-country travel with wheeled or tracked vehicles shall be only to and along fence lines.
2.1 MATERIALS
A. Requirements: Furnish labor and materials required to remove all existing fence construction materials, and gates.
3.1 REMOVAL
A. Removal of Fence: Remove existing fence as directed by the contractors authorized representative (Contracting Officer Representative - COR) on the project. All materials removed from the fence shall become property of the contractor. Disposal of debris shall be according to Section 01009 – General Information and Requirements.
A. Units: Fence removal will be measured and paid for by the linear foot removed as measured along the ground surface next to the fence prior to removal, including distance across gate openings, end, stress, and corner panels and drainage crossings.
Doty State Fence 2024 FENCE REMOVAL
02827 - 2
02827(1) Fence Removal Linear Foot
END OF SECTION 02827
Doty State Fence 2024 Material Specifications
Material Specifications
A. Barbed Wire: A strand of two 12-1/2-gauge galvanized wires twisted together with
2-point barbs of 14-gauge wire spaced 4-inches apart. Wire and barbs shall be zinc-coated steel, with a zinc coating of at least 0.3 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb-force. The barbed wire shall conform to ASTM A 121.
B. Barbless Wire: A strand of two 12-1/2-gauge galvanized wires twisted together. Wire shall be zinc-coated steel wire of at least 0.3 oz/ft2 of coated surface area. The minimum breaking strength of each wire shall be 950 lb-force. The barbless wire shall conform to ASTM A 121.
C. Wood Stays: Straight, sound single-stem members. Shall be 42” long, 2” (milled) in diameter made from Ponderosa pine, or Lodgepole Pine. Peeled and CCA treated.
D. Steel Fence Posts: ASTM A 702; painted green with white or silver tops "T" bar type, with a welded or riveted anchor plate. Furnish with clip-type wire fasteners (punched tabs for fastening wires are not acceptable). Steel posts shall be manufactured from wrought, rail, or new billet steel, and shall have a minimum weight of 1.33 lb/ft. The anchor plates shall weigh a minimum of 0.67 pounds +5 percent, be a minimum of 18 square inches in area, and be 18-inches from the bottom of the post. The posts shall be
5.5’ in length.
E. Wood Line Posts: Straight, sound single-stem members. Shall be 72” long, 4” (milled) in diameter made from Ponderosa pine, or Lodgepole Pine. Peeled and CCA treated.
F. Wood Set Posts and Braces:
1. Acceptable Wood Posts: Sound single-stem members. A slight bend in one plane is acceptable. Posts may be full stem members, sawed members of square cross section, or split members (western red cedar only). The diameter for treated posts shall be a minimum of 6-inches. The length of all set post will be
6.5 feet (78 inches). The following species will be acceptable: Ponderosa pine, Lodgepole pine, fir, and tamarack. All treated posts shall be free of bark with ends cut square.
2. Basis for Rejection: Posts are not acceptable when sweep causes a straight line joining the center of the top to the center of the butt to fall outside the body of the post, or at point 2-inches or more from the center of the post. Posts that are
Doty State Fence 2024 Material Specifications charred, twisted, rotted, or excessively bent are not acceptable. Seasoning checks, single or opposite each other with a sum total equal to or more than 1/2 the thickness of the post is not acceptable.
3. Wood Treatment Practices: General: The following treatments may be used. Treatment method shall be in accordance with AWPA C 1.
1. Chromate Copper Arsenic Method: chromate copper arsenate, waterborne preservative (conforming to Type B in AWPA 5) shall be applied. Minimum net retention of solid preservative shall be 0.4 pounds per cubic foot (gauge only) using the full-cell pressure treatment process.
2. Assay Report: The Supplier shall furnish an assay report, for all treated wood products, from an independent testing laboratory to the Contracting Officer. A minimum of five-inch boring shall be taken from each bundle of 50 posts as samples for the assay report.
A written submittal for all materials shall be submitted for approval to the COR, CS, and CO prior to shipping the products. Contact COR, CS, and CO with any questions.
WORK DATA SHEET
For
SECTION 02824 – FOUR WIRE FENCES AND GATES
Fence type: 4-Wire Wildlife-Friendly Fence & Gates
Type of top wire: Barbed
Type of intermediate wires: Barbed
Type of bottom wire: Smooth/Barbless
Wire locations/dimensions in inches:
D: Barbed - TOP WIRE _ 40”
C: Barbed 28”
B: Barbed _22”
A: Smooth_- BOTTOM WIRE_16”
GROUND LEVEL__________________
Ratio of wood to steel line posts: All line Posts are to be steel.
All Line post spacing (L): 16 ft 6 inches
Type of fence Stays: 2.5-3” diameter x 4’ wood stays (not required in this contract)
Stay spacing (l): 16 ft. 6 inches (1 between each 16.5’ post section)
Length of wood set posts (H2): 6 ft 6 inches
Depth of wood set posts in ground (H2): 2 ft 6 inches
Length of steel posts (H3): 5 ft 6 inches
Depth of steel posts in ground (H3): 1 ft 6 inches
Number of wire gates: 6 (Wire w/ wood stays)
Number of hung steel gates: 2 (8’ powder river style with chain closure)
Number of mechanical gate closers: 0 each
Doty State Fence 2024 WOVEN WIRE W/ WOOD TOP RAIL FENCES AND GATES
SECTION 02824 – Wood Top Rail w/ 3-Strands of Wire
Fence type: Top Rail (wood) w/ Woven Wire
Type of top rail (wood): 16’(feet) x 4-5” (inch)wood rail
Type of intermediate wires: Barbed
Type of bottom wire: Smooth/Barbless
Wood Rail / Wire locations/dimensions in inches:
D: Top Rail (wood)_ __ _ _ 42-40”
C: Barbed Wire 36”
B: ___Barbed Wire_______________24”
A: ___Smooth Wire_______________16”
GROUND LEVEL__________ ___ _________
All line Posts (set posts) are to be wood in this design.
All Set post spacing (L): 12 ft 0 inches
All wood Top-rails are to be hung at a height of 40” (inches)on the high side with a 2’(foot) over-hang on each set posts. Posts are to be hung in a stair step pattern with every wood rail, high side, resting on the previous wood rail low side.
Number of wire gates: 0 (Wire w/ wood stays)
Number of hung steel gates: 0 (8’ powder river style with chain closure)
Doty State Fence 2024 WOVEN WIRE W/ WOOD TOP RAIL FENCES AND GATES
SECTION 02824 – Wood Top Rail w/ Woven Wire (Field Fence)
Fence type: Top Rail (wood) w/ Woven Wire
Type of top rail (wood): 16’(feet) x 4-5” (inch)wood rail
Type of intermediate wires: 39” (inch) Woven Wire (Field Fence)
Wood Rail / Wire locations/dimensions in inches:
D: Top Rail (wood)_ _ _ 42-39”
C: Woven Wire 39” to ground
GROUND LEVEL__________ _________
All line Posts (set posts) are to be wood in this design.
All Set post spacing (L): 12 ft 0 inches
All wood Top-rails are to be hung level and at a height of 42” – 39” (inches)with a 2’(foot) over-hang on each set posts. Posts are to be hung in an over/under pattern with every other rail resting on the tops of the previous and or next rail.
Number of wire gates: 0 (Wire w/ wood stays)
Number of hung steel gates: 0 (8’ powder river style with chain closure)
| A04_SOW_SP.7.25.pdf |
| 1.SOW_Doty_State_Fence.mvo.pdf |
| 2. 01009 general_Doty_State_Fence.mvo.pdf |
| 3. 01505 Mobilization_Doty_State_Fence.mvo.pdf |
| 4. 02824 Wire Fence and Gates_Doty_State_Fence.mvo (1).pdf |
| 5. 02826 Fence-Drainage Crossings_Doty_State_Fence.mvo.pdf |
| 6. 02827 fence removal_Doty_State_Fence.mvo.pdf |
| 7. Material Specifications_Doty_State_Fence.mvo.pdf |
| 8. Work Data Sheet_Doty_State_Fence_4wire.mvo.pdf |
| 9. Work Data Sheet_Doty_State_Fence_RailTop_3wire.mvo (1).pdf |
| 10. Work Data Sheet_Doty_State_Fence_RailTopWoven.mvo.pdf |