About this file

This statement of work outlines requirements for the purchase and installation of a metal shear at the Defense Distribution Depot Red River facility in Texarkana, Texas. The contractor shall provide all necessary labor and materials to deliver, install, and place into operation one new 120-inch hydraulic metal shear with a minimum sheet capacity of 1/2 inch thick mild steel. Additional requirements include electrical connection to existing sources, operator and service manuals, one day of training, and final acceptance inspection and certification by the receiving agency. The point of contact for coordination of delivery is provided.

The related federal contract opportunity is a solicitation issued by the Defense Logistics Agency Distribution seeking proposals for the metal shear and associated requirements specified in the statement of work for the Defense Distribution Depot Red River facility.

View the file

Other files for this federal contract opportunity

Other files attached to Metal Shear DLA Red River, newest first.
File Type Posted
TAB 11 - Amendment 0002 Final.pdf PDF
TAB 11 - Amendment 0001 Final.pdf PDF
Attachment 2 - Schedule of Supplies.xlsx XLSX spreadsheet
Tab 11 - CSS SP3300-23-Q-0192.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Purchase and install Metal Shear (1) each at DDRT.

Background:

a. Requiring Organization Defense Distribution Depot Red River, TX (DDRT)

b. History Shear is required to replace existing shear that has exceeded service life.

c. Purpose of the Statement of Work (SOW):

Purchase new metal Shear (1) ea.

1. Scope of Work to be Performed by Contractor:

The contractor shall provide all necessary labor and material to construct, deliver and place into operation one (1) new Shear. All equipment furnished shall be new from the manufacturer’s most current production. The shear shall be in compliance with all OSHA, federal, state, and local codes and regulations and shall conform to the best quality of materials and workmanship. Accessories not specifically mentioned herein, but necessary to furnish complete systems ready for use, shall also be included and named. All transportation/shipping of the purchased saws shall be provided by the contractor.

The machines must be equal to or greater than the below listed Metal Shear:

1ea 120” Metal Shear Baleigh Industrial SH-120500-HD Hydraulic Shear .

Salient Characteristics:

• 480v 3ph

• 120” Shearing length

• Sheet Capacity: ½” thick mild steel

• 15hp Motor

• Programmable back gauge with 100 program internal memory

• Adjustable rake angle

• Adjustable blade gap

• Shadow Line positioner

• 18 strokes per minute

Exterior color – Manufacturer’s standard.

Warranty Coverage - Warranty coverage shall be manufacturer’s standard warranty but not less than one year parts and labor.

Operator, Parts and Service Manual(s) and Training – The contractor shall provide with delivery, one (1) complete set of manuals with each machine.

2. Definitions of Terms and Abbreviations:

a. DDRT: Defense Distribution Depot Red River

b. OSHA: Occupational Safety Health Administration

3. Description of Contractor’s Tasks:

Task 1: Fabricate and Deliver one (1) each Metal Shear. Shear to be connected to existing electrical connections, no requirement for additional electrical work is required.

Task 2: Install one(1) Metal Shear in locations identified in section 1.

Task 3: Provide one (1) 8 hour period of training instruction on the safe operation of the installed Metal Shear. Training to be conducted at one location to be identified by personnel at the receiving location on the day of delivery and installation.

4. Certification and Acceptance:

Final acceptance of the Metal Shear will be performed by personnel at the receiving location.

5. Performance and/or Delivery Schedule:

The contractor shall coordinate the delivery to the locations listed below with the POC listed below.

7. Shipping Location

QTY: 1EA

Defense Logistics Agency

Defense Distribution Depot Red River, TX 10th Street & K Ave. BLDG 499 Texarkana, TX 75507-5000 POC: Steve Brookman @ 903-334-4546

File details come from the government source that posted it. Updated .